Timeline Bar

Registered16 Oct 2018
Promised5 Oct 2023
Today29 Jul 2026

Timeline

Promised completion5 Oct 2023
Revised completion5 Oct 2023
Actual completion
Possession delay34 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,11,000
Project cost (in ₹ Lakhs)₹21,056 Lakhs
Project duration66 months
Project categoryCommercial
Locality
Original start date
Proposed start date15 Oct 2018

Inventory

Total units633
Unit TypeUnitsCarpet Area (sqm)
SHOP1924.5–2895
OTHER61424–2263.5

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9311921937
Emailanthurium.rera@gmail.com
Coordinator9818822551
AddressB-3/3 1st Floor Shop No. 12 East Krishna Nagar Delhi, East Delhi, India 110051

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
V-9398 Oct 20187 Oct 20235 Oct 20236 Oct 2023
NOIDA/CAP/2018/V-939/394

Revalidated: NOIDA/CAP/2018/V-939/394 (4 Jan 2019)

4 Jan 20193 Jan 2024

Revalidated upto: 1 Jan 1900

5 Oct 20233 Jan 2024

Land Parcels

Khasra No.AreaPlot Type
320002.00Plot

Approved Unit Plan

Unit plan rows on file251
Total flats (sum of rows)633
Total shops19
BlocksA, B
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Anthurium?

The RERA registration number of Anthurium is UPRERAPRJ17793, as recorded on the UP-RERA portal.

What is the RERA status of Anthurium?

As reported by UP-RERA, the status of Anthurium is "Registered".

Where is Anthurium located?

As reported to UP-RERA, Anthurium is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Anthurium be completed?

The latest completion date reported to UP-RERA for Anthurium is 5 Oct 2023.

Is Anthurium delayed?

Measured against the latest completion date reported to UP-RERA, Anthurium is 34 months beyond that date.