Registered14 Aug 2017
Promised24 Mar 2020
Completed31 Jul 2020

Timeline

Promised completion24 Mar 2020
Revised completion24 Mar 2020
Actual completion31 Jul 2020
Possession delay4 mo delay

Registration & Cost Details

Registration fee (in ₹)₹63,500
Project cost (in ₹ Lakhs)₹40,30,34,000 Lakhs
Project duration81 months
Project categoryResidential
Locality
Original start date3 Jul 2013
Proposed start date3 Jul 2013

Inventory

Total units156
Unit TypeUnitsCarpet Area (sqm)
2 BHK6095.72
3 BHK80118.95–133.36
4 BHK16169.6

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8979388333
Emailmohangoyal1967@gmail.com
Coordinator8126599333
AddressSHOP NO S-4,4A II ND FLOOR APARNA MALL HOSPITAL ROAD AGRA

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1441/BFH/12/10-117 Mar 20177 Mar 202224 Mar 20206 Mar 2025
1441/BFH/12/10-117 Mar 20177 Mar 202224 Mar 20206 Mar 2025

Land Parcels

Khasra No.AreaPlot Type
771,774,776 MAUZA KAKRETHA11643
Khasra no 771,776,77415540Khasra
Khasra no 771,776,774(Part)1330.88Khasra

Approved Unit Plan

Unit plan rows on file67
Total flats (sum of rows)156
BlocksTower A, Tower B, Tower C
Floor types2 BHK, 3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
43128 Jan 2013
999 Jun 2004
36012 May 2003
215719 May 2003
494721 Sept 2001
82820 Feb 2006
113312 Dec 2000

Frequently Asked Questions

What is the RERA registration number of APARNA PANCHSHEEL?

The RERA registration number of APARNA PANCHSHEEL is UPRERAPRJ10440, as recorded on the UP-RERA portal.

What is the RERA status of APARNA PANCHSHEEL?

As reported by UP-RERA, the status of APARNA PANCHSHEEL is "Registered".

Where is APARNA PANCHSHEEL located?

As reported to UP-RERA, APARNA PANCHSHEEL is located at Agra, Agra, Uttar Pradesh.

Is APARNA PANCHSHEEL completed?

As reported to UP-RERA, APARNA PANCHSHEEL was completed on 31 Jul 2020.

Is APARNA PANCHSHEEL delayed?

Measured against the latest completion date reported to UP-RERA, APARNA PANCHSHEEL is 4 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026