APNAA AWAS is a RERA-registered residential project by ATUL INFRAESTATE LLP. in Agra (RERA ID UPRERAPRJ17447). Registered with a completion deadline of 31 Dec 2026.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ17447 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Agra Development Authority |
| Proposed start | 15 Sept 2018 |
| Project duration | 100 months |
| Address | Agra, Agra |
| Tehsil | Agra |
| Applicant type | Company |
| Applicant address | Nehru Nagar, Agra |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated
01/PMAY/2018-2019
3 building permits sanctioned
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- valid to
Permit revalidated
01/PMAY/2018-2019
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 27 Aug 2018 |
| Original completion | 25 Jul 2023 |
| Revised completion | 31 Dec 2026 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹93,500 |
| Sanctioning authority | Agra Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 1 BHK932 99%
- SHOP12 1%
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 932 | 23 |
| SHOP | 12 | 10-13 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| A · 1 BHK | 4 | 52 | 23 |
| B · 1 BHK | 4 | 52 | 23 |
| C · 1 BHK | 4 | 52 | 23 |
| D · 1 BHK | 4 | 52 | 23 |
| E · 1 BHK | 4 | 52 | 23 |
| F · 1 BHK | 4 | 52 | 23 |
| G · 1 BHK | 4 | 52 | 23 |
| H · 1 BHK | 4 | 52 | 23 |
| I · 1 BHK | 4 | 52 | 23 |
| J · 1 BHK, SHOP | 4 | 56 | 12-23 |
| K · 1 BHK | 4 | 52 | 23 |
| L · 1 BHK | 4 | 52 | 23 |
| M · 1 BHK | 4 | 52 | 23 |
| N · 1 BHK | 4 | 52 | 23 |
| O · 1 BHK | 4 | 52 | 23 |
| P · 1 BHK | 4 | 52 | 23 |
| Q · 1 BHK | 4 | 52 | 23 |
| R · 1 BHK | 4 | 52 | 23 |
| SHOP · SHOP | 1 | 4 | 10 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Rectangular Plot having 18479.65 sqm area, Accessible from 24 m wide road. Plot is 88.71m wide at the Front side, from the right = 190.37m, from the left =206.99 & the rear side is 88.98m wide. |
| 2 | Boundary Wall Using 230 mm thick brick wall having ms grills on the top. |
| 3 | Road Work There are 6 m and 4.5 m wide internal road are provided. In which 6 m is for fire tender movement. |
| 4 | Footpaths "750 mm wide footpath is provided. street lights, plantation and other services are also provided in footpath." |
| 5 | Water Supply Including Drinking Water Facilities We have provided overhead tanks. |
| 6 | Sewer System Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for tretement after treatement ,water shall be recycle and it will use in gardening and flushing system and oveflow from the STP shall be connect with the Municiple sewarage system. |
| 7 | Drain Storm water drain shall be Provided. Storm water from Roof,Roads and other lanscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit to recharge the Ground water and overflow shall be connect with Municple drain line. |
| 8 | Parks Green area/parks are located at the center of plot in two parts and third one is along the boundary wall. |
| 9 | Tree Planting Indegenious trees are proposed for planting. |
| 10 | Design For Electric Supply Including Street Lighting We have design the system as per local electricity Board. |
| 11 | Community Buildings N/A |
| 12 | Treatment and Disposal System of Sewage and Sullage water Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for tretement after treatement ,water shall be recycle and it will use in gardening and flushing system and oveflow from the STP shall be connect with the Municiple sewarage system. |
| 13 | Solid Waste Management And Disposal System For solid waste proper garbage collection area provided at site. |
| 14 | Water Conservation System We will use low flow fixtures and rain water harvesting system to reduce the water consumption and improve the ground water level. |
| 15 | Energy Management System Including Use of Renewable Energy We will use energy efficient lights fitting in all area. In STP and Pump room all the equipment shall have energy efficient motor. |
| 16 | Fire Protection And Fire Safety System N/A |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services "Sewerage ,Storm water and water supply system shall be Provided. Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic as well as flushing tanks. All Sewgage shall be go to the STP for recycling the water. Storm water for Roof,Roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municple drain." |
| 18 | Emergency Evacuation Services 3 no of exits are provided in each block, and staircase is open from the front. |
| 19 | Other Miscellaneous Work N/A |
Registered agents
1 agent
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | star estate | UPRERAAGT10202 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 25 Jul 2023. 2 of them carry a revalidation, the latest valid to 25 Jul 2026.
Sanctioned by Agra Development Authority · 17,610 sqm of land · an approved plan of 19 blocks and 944 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 01/PMAY/2018-2019 | 26 Jul 2018 | 25 Jul 2023 | 25 Jul 2026 | 25 Jul 2023 | — | |
| 01/PMAY/2018-2019 | 26 Jul 2018 | 25 Jul 2023 | 25 Jul 2026 | 25 Jul 2023 | 26 Jul 2018 | |
| 01/PMAY/2018-2019 | 26 Jul 2018 | 25 Jul 2023 | 25 Jul 2026 | 24 Jan 2024 | 18 May 2025 valid to 25 Jul 2026 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 31 Dec 2026.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 25 Jul 2023 | 24 Jan 2024 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 24 Jan 2024 | 31 Dec 2026 | — |
Land & documents
14 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| KHASRA NO. 30 | 17610.20 | Khasra |
| Sale deed · BAHI NO - 01 JILD NO - 7605 PAGE NO 17-116 SERIAL NO - 2826 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 23 Aug 2018 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 7 May 2019 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 7 May 2019 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 7 May 2019 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 23 Aug 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 23 Aug 2018 ↗ |
Quarterly progress reports
25 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 49.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 58.95% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 58.95% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | ATUL INFRAESTATE LLP. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM55910 |
| PAN | ABMFA7261N |
| CIN / TAN | AGRA14072C |
| Name of chairman | SHOBHIK GOYYAL |
| Registered address | Nehru Nagar, Agra |
| RERA contact | |
| Registered since | 2018 |
Nearby projects
Agra
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | M/S ATUL INFRAESTATE LLP LTD.BankYES BANK LTDBranchYES BANK LTD Sanjay Place AgraA/C no.IFSCYESB0000050 |
What has changed on this record
1 movement
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 3 (Under Registration - 1 ) → 3 (Under Registration - 0 ) changed in Estanzo’s record | 25 Sept 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 25 Sept 2026 |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about APNAA AWAS
Is APNAA AWAS RERA registered?
Yes. APNAA AWAS is registered with UPRERA under registration number UPRERAPRJ17447, registered on 27 Aug 2018. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for APNAA AWAS?
The completion date filed with UPRERA is 31 Dec 2026. No completion certificate is on record yet.
Who is the builder of APNAA AWAS?
ATUL INFRAESTATE LLP. is the promoter entity that filed APNAA AWAS with UPRERA (promoter RERA ID UPRERAPRM55910). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted APNAA AWAS more time to complete?
UPRERA's record carries 2 completion extensions for APNAA AWAS, the latest running to 31 Dec 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does APNAA AWAS have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is APNAA AWAS located?
APNAA AWAS is registered in Agra, as filed with UPRERA.
What configurations are available in APNAA AWAS?
The unit plan filed with UPRERA lists 1 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in APNAA AWAS?
The approved unit plan filed with UPRERA runs from 10 to 23 m² of carpet area (about 112 to 245 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in APNAA AWAS?
The approved unit plan describes 19 blocks and 944 units of which 932 are homes and 12 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is APNAA AWAS?
About 217 units per acre: 944 planned units across 4.35 acres (17,610 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗