Registered16 May 2025
Revised14 Jan 2026
Today3 Aug 2026
Promised16 May 2029

Timeline

Promised completion16 May 2029
Revised completion14 Jan 2026
Actual completion
Possession delay7 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,05,000
Project cost (in ₹ Lakhs)₹2,440 Lakhs
Project duration53 months
Project categoryResidential
LocalitySector: IRW (Pocket-A), Kalindipuram, Prayagraj
Original start date
Proposed start date15 Jan 2025

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeSocieties
Mobile8787218496
Emailawhoprayag@gmail.com
Coordinator9839066525
Helpline05222209859
AddressArmy Welfare Housing Organisation South Hutments, Kashmir House Rajaji Marg, New Delhi-110011

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2024-Q4
2025-Q113.5%
2025-Q224.0%
2025-Q344.9%
2025-Q461.0%
2026-Q1100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Plotted Resi development/Plotted Housing/03582/PDA/LD/22-23/0605/1904202417 May 202416 May 202914 Jan 202616 May 2029

Land Parcels

Khasra No.AreaPlot Type
Sector-IRW, Pocket-A, Kalindipuram Awas Yojna, Kasari Masari, Prayagraj20000Plot

Frequently Asked Questions

What is the RERA registration number of ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ?

The RERA registration number of ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ is UPRERAPRJ188388, as recorded on the UP-RERA portal.

What is the RERA status of ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ?

As reported by UP-RERA, the status of ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ is "Registered".

Where is ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ located?

As reported to UP-RERA, ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ is located at Plot No. IRW (Pocket-A), Kalindipuram, Awas Yojna Kasari Masari, Prayagraj, Sector: IRW (Pocket-A), Kalindipuram, Prayagraj, Allahabad, Prayagraj, Uttar Pradesh.

When will ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ be completed?

The latest completion date reported to UP-RERA for ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ is 14 Jan 2026.

Is ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ delayed?

Measured against the latest completion date reported to UP-RERA, ARMY WELFARE HOUSING ORGANISATION PLOTTED DEVELOPMENT AT KALINDIPURAM, PRAYAGRAJ is 7 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026