Timeline Bar
Registered1 Aug 2017
Promised19 Aug 2021
Completed17 Mar 2022
Timeline
Promised completion19 Aug 2021
Revised completion19 Aug 2021
Actual completion17 Mar 2022
Possession delay7 mo delay
Registration & Cost Details
Registration fee (in ₹)₹3,14,000
Project cost (in ₹ Lakhs)₹34,094 Lakhs
Project duration66 months
Project categoryCommercial
Locality—
Original start date20 Aug 2016
Proposed start date20 Aug 2016
Inventory
Total units605
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 102 | 5.84–360.29 |
| OTHER | 503 | 45.97–296.66 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9643007884
Emaildreamzone@atsgreens.com
Coordinator9643007884
AddressATS Tower, Plot-16,
Sector-135, Noida-201305
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| NOIDA/M.V.N./2016/V-824/60 | 31 May 2016 | 30 May 2021 | 19 Aug 2021 | 30 May 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| NA | 0 | — |
| PLOT NO-A 2/2, SECTOR-132, NOIDA | 30363.9 | Plot |
Approved Unit Plan
Unit plan rows on file290
Total flats (sum of rows)605
Total shops102
BlocksRETAIL SHOP, TOWER- A (COMMERCIAL), TOWER- B (COMMERCIAL), TOWER- C (COMMERCIAL)
Floor typesSHOP, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 11601 | 28 Dec 2011 | — | — |
Frequently Asked Questions
What is the RERA registration number of ATS BOUQUET?
The RERA registration number of ATS BOUQUET is UPRERAPRJ2612, as recorded on the UP-RERA portal.
What is the RERA status of ATS BOUQUET?
As reported by UP-RERA, the status of ATS BOUQUET is "Registered".
Where is ATS BOUQUET located?
As reported to UP-RERA, ATS BOUQUET is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.
Is ATS BOUQUET completed?
As reported to UP-RERA, ATS BOUQUET was completed on 17 Mar 2022.
Is ATS BOUQUET delayed?
Measured against the latest completion date reported to UP-RERA, ATS BOUQUET is 7 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026