Timeline Bar

Registered1 Aug 2017
Promised19 Aug 2021
Completed17 Mar 2022

Timeline

Promised completion19 Aug 2021
Revised completion19 Aug 2021
Actual completion17 Mar 2022
Possession delay7 mo delay

Registration & Cost Details

Registration fee (in ₹)₹3,14,000
Project cost (in ₹ Lakhs)₹34,094 Lakhs
Project duration66 months
Project categoryCommercial
Locality
Original start date20 Aug 2016
Proposed start date20 Aug 2016

Inventory

Total units605
Unit TypeUnitsCarpet Area (sqm)
SHOP1025.84–360.29
OTHER50345.97–296.66

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emaildreamzone@atsgreens.com
Coordinator9643007884
AddressATS Tower, Plot-16, Sector-135, Noida-201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/M.V.N./2016/V-824/6031 May 201630 May 202119 Aug 202130 May 2026

Land Parcels

Khasra No.AreaPlot Type
NA0
PLOT NO-A 2/2, SECTOR-132, NOIDA30363.9Plot

Approved Unit Plan

Unit plan rows on file290
Total flats (sum of rows)605
Total shops102
BlocksRETAIL SHOP, TOWER- A (COMMERCIAL), TOWER- B (COMMERCIAL), TOWER- C (COMMERCIAL)
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1160128 Dec 2011

Frequently Asked Questions

What is the RERA registration number of ATS BOUQUET?

The RERA registration number of ATS BOUQUET is UPRERAPRJ2612, as recorded on the UP-RERA portal.

What is the RERA status of ATS BOUQUET?

As reported by UP-RERA, the status of ATS BOUQUET is "Registered".

Where is ATS BOUQUET located?

As reported to UP-RERA, ATS BOUQUET is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is ATS BOUQUET completed?

As reported to UP-RERA, ATS BOUQUET was completed on 17 Mar 2022.

Is ATS BOUQUET delayed?

Measured against the latest completion date reported to UP-RERA, ATS BOUQUET is 7 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.