Exotica 132

UPRERARegistered

Exotica 132 is a RERA-registered commercial project by EXOTICA INFRATECH LLP in Sector 132, Noida, Gautam Budh Nagar (RERA ID UPRERAPRJ731857). Registered with a completion deadline of 10 Jan 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'25
—Q2'25
2.9%Q3'25
7.2%Q4'25
8.16%Q1'26
8.43%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ731857
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Mar 2025
Project duration59 months
AddressPlot No. A-3A, Sector 132, Noida, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeLimited Liability Partnership (LLP)
Applicant address228 BASEMENT JAGRITI ENCLAVE GATE NO 1 SHAHDARA , NEW DELHI-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    2024/12/27/11748

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered15 Apr 2025
Original completion10 Jan 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,32,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors400 · 2 · 28 (units from plan)
Homes · commercial units294 · 106 (shops and offices filed in the same plan)
  • OTHER294 74%
  • SHOP106 27%
ConfigurationUnitsCarpet area
SHOP10620-61
OTHER29444-470
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Commercial · SHOP310620-61
Tower-2 · OTHER2829444-470
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 148.21 m² for a SHOP, 181.51 m² for a SHOP, 181.51 m² for a SHOP and 1 other unit like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
MR. KULMEET SHANGARI
License CA/1997/21741
E-24 South Extension-1, New Delhi 110049, India
Engineer
ALPA RAMESH SHETH
83/84, 8th Floor Shekhar Bhawan, Nariman Point Mumbai-400021
Contractor
A To Z Contractor Pvt Ltd
257, IIIrd Floor Gali No.-2, Bhhola Nath Nagar Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
As per Lease plan
2Boundary Wall
Front Boundary wall 1.5m High and Side Boundary Wall 2.0m high boundary wall. Brick work and permanent furnishing on boundary wall.
3Road Work
6.0 m wide internal road finished in a Cement concrete.
4Footpaths
Stone Paving as per landscape architect plan.
5Water Supply Including Drinking Water Facilities
Water supply to be taken from Concern Authority.
6Sewer System
Underground Sewer Line will be laid. STP will be installed. Sewer connection will be obtained from authority.
7Drain
Drain line will be laid and connection will be obtained from authority.
8Parks
Landscaping with plantation including trees, shrubs and ground covers and recreational areas with benches and walkways.
9Tree Planting
As per landscape consultant / as per IGBC green building norms. One tree per 100 sqmt. of open area is proposed.
10Design For Electric Supply Including Street Lighting
HT power connection will be hired from concern Authority. Electrical substation will be installed in the project with dedicated Transformers, HT/LT Panels and DG Sets. Street lights will be installed with Grid Power supply as well as backup power supply.
11Community Buildings
N/A
12Treatment and Disposal System of Sewage and Sullage water
Dedicated Sewage Treatment Plant will be installed for Sewage Treatment.
13Solid Waste Management And Disposal System
Organic waste composter will be installed for solid waste management. Disposal of organic waste will be done through authorised agency.
14Water Conservation System
Rain water harvesting chambers will be installed.
15Energy Management System Including Use of Renewable Energy
Grid Supply - Concern Authority. Backup Power - DG with CPCB guidelines Emergency power - UPS Renewable power - Solar as per MOEF guidelines Equipment selection - with proper energy efficiency as per green building norms.
16Fire Protection And Fire Safety System
The project falls under IT/ITES Project Buildings. Fire Protection and Fire Safety System shall as per the NBC-2016 and other relavent code. Internal and external fire hydrant system shall be provided with landing valve, hose reel with shut off nozzle, short branch pipe with nozzle and fire mans axe. Automatic sprinkler system is provided. The system shall be suitably zoned for its optimum functional performance. Sprinklers shall be distributed throughout the building as per the National Building code.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Common Washroom at Ground Ivl. etc.
18Emergency Evacuation Services
Fire Staircase provided as per sanction plan.
19Other Miscellaneous Work
As Per Plan
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

26 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 DEGREE VENTURES PRIVATE LIMITEDUPRERAAGT18728
2360 REALTORS LLPUPRERAAGT10868
3ANAROCK Property Consultants Private LimitedUPRERAAGT10265
4BLUE SAPPHIRE INFRASTRUCTURE LLPUPRERAAGT23418
5BLUECRUMBS INFRA PRIVATE LIMITEDUPRERAAGT16897
6BOP REALTY PRIVATE LIMITEDUPRERAAGT10206
7BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
8BUNIYAD REALTY LIMITED (Formerly BUNIYAD RETAIL INDIA PRIVATE LIMITED)UPRERAAGT11569
9FINDMYPROPERTY PRIVATE LIMITEDUPRERAAGT11867
10FIRSTDOOR REALTY LLPUPRERAAGT23971
11KARTIK INFRATOWN PRIVATE LIMITEDUPRERAAGT10413
12M/s MONEYTREE REALTY SERVICES LIMITED formally known as (M/s Moneytree Reality Services Private Limited)UPRERAAGT25048
13M/s Northbrick Consultancy Pvt Ltd.(formerly Known as Northbrick ventures Pvt Ltd)UPRERAAGT16860
14muskan realtorsUPRERAAGT10510
15ORANGE DOOR INFRA PRIVATE LIMITEDUPRERAAGT15693
16Pankaj GuptaUPRERAAGT26341
17Propertypistol Realty Pvt LtdUPRERAAGT12730
18RAVS INFRATECH PRIVATE LIMITEDUPRERAAGT20392
19Rudra prop solutions Bharat singhUPRERAAGT16810
20Sachan Estate Pvt LtdUPRERAAGT10143
21SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
22star estateUPRERAAGT10202
23TRUHOMES REALTYUPRERAAGT10997
24VishalUPRERAAGT24345
25WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
26WEALTHCHOICE INFRATECH PRIVATE LIMITEDUPRERAAGT25654
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 10 Jan 2030.

Sanctioned by Noida Authority · 12,146 sqm of land · an approved plan of 2 blocks and 400 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
2024/12/27/1174811 Jan 202510 Jan 203010 Jan 203510 Jan 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
A3A, Sector 132, NOIDA20242.60Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 7138, Bahi 1, Zild No. 1427, Page Nos. from 191 to 390
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New10 Mar 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New19 Mar 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New19 Mar 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New19 Mar 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New10 Mar 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Mar 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New10 Mar 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New10 Mar 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New10 Mar 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Mar 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New10 Mar 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New10 Mar 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New19 Mar 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.

QuarterConstructionCertificates
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q22.9%CA ↗ · Arch ↗ · Eng ↗
2025-Q37.2%CA ↗ · Arch ↗ · Eng ↗
2025-Q48.16%CA ↗ · Arch ↗ · Eng ↗
2026-Q18.43%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameEXOTICA INFRATECH LLP
RolePromoter · current
RERA IDUPRERAPRM343361
PANAAKFE9860C
CIN / TANDELE18406D
Registered address228 BASEMENT JAGRITI ENCLAVE GATE NO 1 SHAHDARA , NEW DELHI-110092
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Exotica Infratech LLP Collection Account for Exotica 132BankPunjab & Sind BankBranchAtta, NoidaBranch addressD2C Sector 18 Noida Gautam Buddha NagarBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPSIB0000426Branch emailA0426@PSB.CO.IN
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Exotica Infratech LLP Separate Bank Account for Exotica 132BankPunjab and Sind BankBranchAtta, NoidaBranch addressD2C Sector 18 Noida Gautam Buddha NagarBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPSIB0000426
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Exotica Infratech LLP RERA Transaction Account for Exotica 132BankPunjab and Sind BankBranchAtta, NoidaBranch addressD2C Sector 18 Noida Gautam Buddha NagarBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCPSIB0000426
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

20 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Filed document
viewprojects · 17
Proforma of Agreement for Sale
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 16
ENGINEERS CERTIFICATE
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 15
ARCHITECT CERTIFICATE
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 14
CA CERTIFICATE
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 13
Affidavit (Form-B)
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 12
Development Work Plan
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 11
Electricity Supply Plan
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 10
Water Supply Plan
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 9
Waste Disposal Plan
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 8
Proforma of Conveyance Deed
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 7
Proforma of Allotment Letter
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 6
Proforma of Application Form
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 5
Other Plan(If Any)
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 4
Commencement Certificate
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 3
Details of Encumbrances
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 2
Other
newly filed with RERA
18 Oct 2026
Filed document
viewprojects · 1
Proforma of Completion Certificate(Occupancy)
newly filed with RERA
18 Oct 2026
Filed document
summary · 18
Details of Encumbrances
no longer on the record
18 Oct 2026
Filed document
summary · 17
Commencement Certificate
no longer on the record
18 Oct 2026
Filed document
summary · 16
Other Plan(If Any)
no longer on the record
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Exotica 132

Is Exotica 132 RERA registered?

Yes. Exotica 132 is registered with UPRERA under registration number UPRERAPRJ731857, registered on 15 Apr 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Exotica 132?

The completion date filed with UPRERA is 10 Jan 2030. No completion certificate is on record yet.

Who is the builder of Exotica 132?

EXOTICA INFRATECH LLP is the promoter entity that filed Exotica 132 with UPRERA (promoter RERA ID UPRERAPRM343361). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Exotica 132 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Exotica 132 located?

Exotica 132 is registered in Sector 132, Noida, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Exotica 132?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Exotica 132?

The approved unit plan filed with UPRERA runs from 20 to 470 m² of carpet area (about 212 to 5,056 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Exotica 132?

The approved unit plan describes 2 blocks and 400 units of which 294 are homes and 106 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Exotica 132?

About 133 units per acre: 400 planned units across 3.00 acres (12,146 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗