Estanzo

Timeline Bar

Registered11 Jun 2019
Promised1 Jul 2024
Revised30 Dec 2024
Completed20 Aug 2025

Timeline

Promised completion1 Jul 2024
Revised completion30 Dec 2024
Actual completion20 Aug 2025
Possession delay8 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,26,000
Project cost (in ₹ Lakhs)₹17,023 Lakhs
Project duration75 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Jul 2019

Inventory

Total units309
Unit TypeUnitsCarpet Area (sqm)
SHOP3088.36–1437.66
OTHER12408.96

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailkabanahigh@atsgreens.com
Coordinator9643007884
AddressATS Tower Plot No -16 Sector 135 Noida 201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q490.0%
2025-Q193.0%
2025-Q297.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
202 Map No-10/PMAY GDA/M.P/201820 Apr 201919 Apr 20241 Jul 202419 Apr 2027
202 Map No-10/PMAY GDA/M.P//2018

Revalidated: 202 Map No-10/PMAY GDA/M.P//2018 (20 Apr 2019)

20 Apr 201919 Apr 2024

Revalidated upto: 19 Apr 2027

30 Dec 202419 Apr 2027
202 Map No-10/PMAY GDA/M.P/2018

Revalidated: 202 Map No-10/PMAY GDA/M.P/2018 (20 Apr 2019)

20 Apr 201919 Apr 2024

Revalidated upto: 19 Apr 2027

30 Dec 202419 Apr 2027

Land Parcels

Khasra No.AreaPlot Type
397,398, 399, 400,401,402,407,408,409,410,411,59411540Khasra

Approved Unit Plan

Unit plan rows on file146
Total flats (sum of rows)309
Total shops308
BlocksCommercial
Floor typesSHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of ATS Khyber Range?

The RERA registration number of ATS Khyber Range is UPRERAPRJ904685, as recorded on the UP-RERA portal.

What is the RERA status of ATS Khyber Range?

As reported by UP-RERA, the status of ATS Khyber Range is "Registered".

Where is ATS Khyber Range located?

As reported to UP-RERA, ATS Khyber Range is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is ATS Khyber Range completed?

As reported to UP-RERA, ATS Khyber Range was completed on 20 Aug 2025.

Is ATS Khyber Range delayed?

Measured against the latest completion date reported to UP-RERA, ATS Khyber Range is 8 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026