Floral Pathways

UPRERARegistered

Floral Pathways is a RERA-registered residential project by ATS Grand Realtors Private Limited in Ghaziabad (RERA ID UPRERAPRJ750395). Registered with a completion deadline of 18 Apr 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
79%Q3'25
83%Q4'25
89%Q1'26
96%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ750395
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 May 2021
Project duration72 months
AddressGhaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant addressATS Tower Plot No -16 Sector 135 Noida 201305
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    202 MAP No. 10/PMAY/GDA/MP/2018

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered4 Jun 2021
Original completion18 Apr 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,13,500
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors788 · 12 · 38 (units from plan)
ConfigurationUnitsCarpet area
3 BHK78890-97
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower 1 · OTHER, 3 BHK386690-97
Tower 10 · OTHER, 3 BHK386690-97
Tower 11 · OTHER, 3 BHK386690-97
Tower 12 · OTHER, 3 BHK386690-97
Tower 2 · OTHER, 3 BHK386690-97
Tower 3 · OTHER, 3 BHK376490-97
Tower 4 · OTHER, 3 BHK376490-97
Tower 5 · OTHER, 3 BHK386690-97
Tower 6 · OTHER, 3 BHK386690-97
Tower 7 · OTHER, 3 BHK386690-97
Tower 8 · OTHER, 3 BHK386690-97
Tower 9 · OTHER, 3 BHK386690-97
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Karan Singh
License CA/2012/55100
ATS Tower, Plot No 16, Sector 135, Noida
Engineer
Kamal Kumar Sabharwal
H-25, 2nd Floor(Level-3), Kailash Colony Market, New Delhi-110048
Contractor
ATS Grand Realtors Pvt Ltd
ATS Tower, Plot No-16, Sector 135, Noida
Sr.Development work declared to RERA
1Demarcation of Plots
This is a group housing project so there is no demarcation individual plot and demarcation of the plot and site barricading is done as per approved building plan. Land is in our possession.
2Boundary Wall
1.5 M high boundary wall along front road and 2.0 M high boundary wall along other sides with elegant design integrated with security rails as per design constructed in RCC/Brick work
3Road Work
7.5M wide internal Roads finished with concrete pavers with drainage arrangement. Internal Road acts as peripheral Loop road connects to each tower.
4Footpaths
Networks of footpaths connects the various part of Landscape, Towers and Gardens as per landscape design.
5Water Supply Including Drinking Water Facilities
Ghaziabad Authority will supply water supply to entire society and that will further be supplied to dwelling units after filtration from centralized plant.
6Sewer System
Sewage from all units will be treated through STP and recycled water will be recirculated for horticulture and flushing.
7Drain
Drainage through network of pipe and catch basins to dispersion trenches with over flow to authority drain.
8Parks
There is an ample central garden area in which locally adapted species of trees and plants will be grown along with outdoor sports amenities and walking tracks.
9Tree Planting
Locally adapted species will be grown. Majority plants with least maintenance will be planted.
10Design For Electric Supply Including Street Lighting
Individual units will get their electricity supply directly from discom and all infrastructure like LT panels and sub distribution networks will be provided by developer. This may subject to change as per prevailing bylaws of discom
11Community Buildings
Club proposed with multipurpose hall, Games room, Gymnasium, changing rooms etc.
12Treatment and Disposal System of Sewage and Sullage water
Treatment through STP and over flow to authority sewer line.
13Solid Waste Management And Disposal System
Solid waste will be segregated and organic based will be treated through OWC.
14Water Conservation System
Adequate number of recharge pits are proposed to harvest rain water.
15Energy Management System Including Use of Renewable Energy
LED Lights, timer control panels and solar power plant for energy saving management.
16Fire Protection And Fire Safety System
Integrated fire alarm systems and suppression system is proposed as per NBC.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Creche is provided below club for the community building.
18Emergency Evacuation Services
Separate Fire Escape staircase, Refuse terraces are proposed in all towers as per NBC.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

58 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2AADHAR PROPMART PRIVATE LIMITEDUPRERAAGT10142
3ACUBE SOLUTIONSUPRERAAGT10220
4Addressofchoice Realty Pvt LtdUPRERAAGT14990
5ajay goswamiUPRERAAGT14382
6Ambrish YadavUPRERAAGT16314
7AMIT KUMARUPRERAAGT14654
8ANAROCK Property Consultants Private LimitedUPRERAAGT10265
9ARVIND TOMARUPRERAAGT16590
10BULLMEN REALTY INDIA PRIVATE LIMITEDUPRERAAGT10138
11BUNIYAD REALTY LIMITED (Formerly BUNIYAD RETAIL INDIA PRIVATE LIMITED)UPRERAAGT11569
12EMPOWER REALTECH PRIVATE LIMITEDUPRERAAGT10623
13ETHEREAL HOMES PRIVATE LIMITEDUPRERAAGT15555
14FINDMYPROPERTY PRIVATE LIMITEDUPRERAAGT11867
15GATEWAY PROPMART PVT LTDUPRERAAGT10384
16GAURAV SARAFUPRERAAGT13979
17HABBY GUPTAUPRERAAGT13918
18HONEY MONEY ASSOCIATES LIMITEDUPRERAAGT11535
19Investor Mart C/o Amar SangwanUPRERAAGT13201
20INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
21JAI AMBEY CONSULTANTSUPRERAAGT11064
22JOINT BRICKS PROPMARTUPRERAAGT11518
23KARTIK INFRATOWN PRIVATE LIMITEDUPRERAAGT10413
24MADHYAM ESTATE LINKERS PVT LTDUPRERAAGT10509
25Mitresh SharmaUPRERAAGT14496
26Neeraj SaxenaUPRERAAGT10536
27Nirmal Estate C/O Satya Prakash OjhaUPRERAAGT12705
28pawan kumarUPRERAAGT15211
29PC MANTRA INFOSYSTEM PVT. LTD.UPRERAAGT10580
30PROPCASA CONSULTANCY PVT. LTD.UPRERAAGT10038
31PROPFIN SOLUTIONS PVT LTDUPRERAAGT14948
32Proprex Realty Private LimitedUPRERAAGT13343
33PROPSHOPUPRERAAGT10129
34PROPTIGER MARKETING SERVICES PRIVATE LIMITED(Formerly ELARA MARKETING SERVICES PRIVATE LIMITED)UPRERAAGT10032
35PROPZONE INFRATECHUPRERAAGT10285
36RAHULUPRERAAGT11454
37Rahul Kumar SinghUPRERAAGT12319
38RAJEEV CHHABRAUPRERAAGT10522
39RAJEEV KUMARUPRERAAGT10524
40RANJAN KUMAR C/O ANKUR REAL ESTATE DEVELOPERSUPRERAAGT13363
41REDMAPLE BUILDIKO PRIVATE LIMITEDUPRERAAGT14395
42RISHU KUMARUPRERAAGT14718
43Rohit BediUPRERAAGT12109
44Rohit JainUPRERAAGT13465
45Sachan Estate Pvt LtdUPRERAAGT10143
46Salman KhanUPRERAAGT15394
47SANG INFRATECH PVT. LTD.UPRERAAGT10024
48SHUBHAM RASTOGIUPRERAAGT16850
49SMC Real Estate Advisors Private LimitedUPRERAAGT10113
50SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
51star estateUPRERAAGT10202
52Supertrust Homes Pvt LtdUPRERAAGT16429
53Sushil vyasUPRERAAGT13744
54SYED ANWAR ZAIDIUPRERAAGT13761
55TRUHOMES REALTYUPRERAAGT10997
56TRUSTNEST PROPERTY CONSULTANTS LLPUPRERAAGT15462
57VARUN KUMAR SHUKLAUPRERAAGT14388
58Walmond Realty Dart Pvt LtdUPRERAAGT10777
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 19 Apr 2024. 1 of them carries a revalidation, valid to 19 Apr 2027.

Sanctioned by Ghaziabad Development Authority · 21,631 sqm of land · an approved plan of 12 blocks and 788 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
202 MAP No. 10/PMAY/GDA/MP/201820 Apr 201919 Apr 202419 Apr 202718 Apr 2027—
202 MAP No. 10/PMAY/GDA/MP/201820 Apr 201919 Apr 202419 Apr 202718 Apr 202720 Apr 2019
valid to 19 Apr 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
393,394,395,396,403,404,405 and part of Khasra No 397,400,401,402,407 situated at village Mehrauli and part of Khasra No 137/1 of Mohalla Shahpur Bamheta21631Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 86
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3350
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3769
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7857
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7859
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 8591
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7860
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4767
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 956602
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1424-1429
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1423-1428
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 3089
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New29 Apr 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New13 Apr 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New13 Apr 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New13 Apr 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New24 Jun 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New24 Jun 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New24 Jun 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Apr 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New14 Apr 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Apr 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Apr 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New13 Apr 2021 ↗

Quarterly progress reports

22 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

22 quarterly progress reports are on file with UPRERA, covering 2021-Q1 to 2026-Q2.

QuarterConstructionCertificates
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q279%CA ↗ · Arch ↗ · Eng ↗
2025-Q383%CA ↗ · Arch ↗ · Eng ↗
2025-Q489%CA ↗ · Arch ↗ · Eng ↗
2026-Q196%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameATS Grand Realtors Private Limited
RolePromoter · current
RERA IDUPRERAPRM76077
PANAAOCA3392A
CIN / TANU45309DL2016PTC298247
Name of chairmanGetamber Anand
Registered addressATS Tower Plot No -16 Sector 135 Noida 201305
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameVOYAGE REAL ESTATES PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressATS Tower Plot No- 16 Sector 135 Noida 201305
RERA contact

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ATS Grand Realtors Pvt Ltd - Separate AC. Floral PathwaysBankICICI Bank LtdBranchSector 18, NoidaA/C no.IFSCICIC0000031
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

2 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
Promoter’s complaints tally (all their projects)24 (Under Registration - 1 ) → 24 (Under Registration - 0 )
changed in Estanzo’s record
21 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 21 Sept 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Floral Pathways

Is Floral Pathways RERA registered?

Yes. Floral Pathways is registered with UPRERA under registration number UPRERAPRJ750395, registered on 4 Jun 2021. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Floral Pathways?

The completion date filed with UPRERA is 18 Apr 2027. No completion certificate is on record yet.

Who is the builder of Floral Pathways?

ATS Grand Realtors Private Limited is the promoter entity that filed Floral Pathways with UPRERA (promoter RERA ID UPRERAPRM76077). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Floral Pathways have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Floral Pathways located?

Floral Pathways is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in Floral Pathways?

The unit plan filed with UPRERA lists OTHER and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Floral Pathways?

The approved unit plan filed with UPRERA runs from 90 to 97 m² of carpet area (about 970 to 1,047 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Floral Pathways?

The approved unit plan describes 12 blocks and 788 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Floral Pathways?

About 147 units per acre: 788 planned units across 5.35 acres (21,631 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗