Estanzo

Timeline Bar

Registered4 Jun 2021
Today3 Aug 2026
Promised18 Apr 2027

Timeline

Promised completion18 Apr 2027
Revised completion18 Apr 2027
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹1,13,500
Project cost (in ₹ Lakhs)₹53,249 Lakhs
Project duration72 months
Project categoryResidential
Locality
Original start date
Proposed start date1 May 2021

Inventory

Total units788
Unit TypeUnitsCarpet Area (sqm)
3 BHK78890.07–97.3

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailkabanahigh@atsgreens.com
Coordinator9643007884
AddressATS Tower Plot No -16 Sector 135 Noida 201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q279.0%
2025-Q383.0%
2025-Q489.0%
2026-Q196.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
202 MAP No. 10/PMAY/GDA/MP/201820 Apr 201919 Apr 202418 Apr 202719 Apr 2027
202 MAP No. 10/PMAY/GDA/MP/2018

Revalidated: 202 MAP No. 10/PMAY/GDA/MP/2018 (20 Apr 2019)

20 Apr 201919 Apr 2024

Revalidated upto: 19 Apr 2027

18 Apr 202719 Apr 2027

Land Parcels

Khasra No.AreaPlot Type
393,394,395,396,403,404,405 and part of Khasra No 397,400,401,402,407 situated at village Mehrauli and part of Khasra No 137/1 of Mohalla Shahpur Bamheta21631Khasra

Approved Unit Plan

Unit plan rows on file462
Total flats (sum of rows)788
BlocksTower 1, Tower 10, Tower 11, Tower 12, Tower 2, Tower 3, Tower 4, Tower 5, Tower 6, Tower 7, Tower 8, Tower 9
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Floral Pathways?

The RERA registration number of Floral Pathways is UPRERAPRJ750395, as recorded on the UP-RERA portal.

What is the RERA status of Floral Pathways?

As reported by UP-RERA, the status of Floral Pathways is "Registered".

Where is Floral Pathways located?

As reported to UP-RERA, Floral Pathways is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

When will Floral Pathways be completed?

The latest completion date reported to UP-RERA for Floral Pathways is 18 Apr 2027.

Is Floral Pathways delayed?

Measured against the latest completion date reported to UP-RERA, Floral Pathways is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026