ATS Picturesque Reprieves Phase 2 is a RERA-registered residential project by ATS HOMES PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ396176). Registered with a completion deadline of 29 Mar 2027.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ396176 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Noida Authority |
| Proposed start | 1 Jul 2019 |
| Project duration | 93 months |
| Address | Dadri, Gautam Budh Nagar |
| Tehsil | Dadri |
| Applicant type | Company |
| Applicant address | ATS Tower, Plot-16, Sector-135, Noida-201305 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
M/V/N/2016/IV-1493/940
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 27 Feb 2019 |
| Original completion | 30 Sept 2026 |
| Revised completion | 29 Mar 2027 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,51,000 |
| Sanctioning authority | Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 3 BHK490 76%
- 4 BHK144 22%
- PENTHOUSE10 2%
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 144 | 191-247 |
| 3 BHK | 490 | 115-137 |
| PENTHOUSE | 10 | 155-212 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Tower 1, 29 · OTHER, 4 BHK, 3 BHK | 39 | 284 | 115-247 |
| Tower 2, 3 · OTHER, 4 BHK, PENTHOUSE | 39 | 144 | 191-212 |
| Tower 4, 5, 6 · OTHER, 3 BHK, PENTHOUSE | 39 | 216 | 137-155 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Initial Survey |
| 2 | Boundary Wall RCC / Brick work in boundary wall |
| 3 | Road Work WBM with paver |
| 4 | Footpaths Polycrete tile/Paver |
| 5 | Water Supply Including Drinking Water Facilities Provided central water supply to all unit as given in the drawing , for flushing & irrigation Dual Plumbing system |
| 6 | Sewer System Two pipe line system for sewage disposal & finally treated through STP |
| 7 | Drain Collected through piping & catch basin network , under ground water through harvesting pit |
| 8 | Parks Park area are given as per the design |
| 9 | Tree Planting Tree plant area are given as per the design |
| 10 | Design For Electric Supply Including Street Lighting Through LT and Sub Distribution Panels |
| 11 | Community Buildings Club & other facilities provided shared with other Phases |
| 12 | Treatment and Disposal System of Sewage and Sullage water Through Sewage Treatment Plant |
| 13 | Solid Waste Management And Disposal System Through Solid Waste Machine |
| 14 | Water Conservation System Through Rain water harvesting Pit |
| 15 | Energy Management System Including Use of Renewable Energy Automatic PLC, Solar , LED |
| 16 | Fire Protection And Fire Safety System Integrated fire alarm system as per NBC |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services Fire escapes staircase as per NBC |
| 19 | Other Miscellaneous Work NA |
Registered agents
26 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | 360 REALTORS LLP | UPRERAAGT10868 |
| 2 | ANAROCK Property Consultants Private Limited | UPRERAAGT10265 |
| 3 | Anjul Panjabi | UPRERAAGT13477 |
| 4 | ASAD NAFIS | UPRERAAGT14918 |
| 5 | BULLMEN REALTY INDIA PRIVATE LIMITED | UPRERAAGT10138 |
| 6 | CBRE SOUTH ASIA PRIVATE LIMITED | UPRERAAGT14785 |
| 7 | EMPOWER REALTECH PRIVATE LIMITED | UPRERAAGT10623 |
| 8 | GATEWAY PROPMART PVT LTD | UPRERAAGT10384 |
| 9 | GAURAV PRAKASH | UPRERAAGT11684 |
| 10 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
| 11 | JAI AMBEY CONSULTANTS | UPRERAAGT11064 |
| 12 | Md Samser Khan | UPRERAAGT13178 |
| 13 | MONISHA VOHRA | UPRERAAGT11491 |
| 14 | Nitin Jain | UPRERAAGT14291 |
| 15 | Parmender Kumar Chawda | UPRERAAGT13661 |
| 16 | PARMESHWAR PRASAD | UPRERAAGT14454 |
| 17 | PROPCASA CONSULTANCY PVT. LTD. | UPRERAAGT10038 |
| 18 | REALTY WORLD INFRATECH PVT. LTD. | UPRERAAGT10531 |
| 19 | SMC Real Estate Advisors Private Limited | UPRERAAGT10113 |
| 20 | SQUARE YARDS CONSULTING PRIVATE LIMITED | UPRERAAGT10119 |
| 21 | Stalwart Realty LLP | UPRERAAGT12657 |
| 22 | star estate | UPRERAAGT10202 |
| 23 | SUNIL JULKA | UPRERAAGT11642 |
| 24 | UMANG ESTATES C/O VIRENDER SINGH | UPRERAAGT11784 |
| 25 | VIJAY CHAUHAN | UPRERAAGT15406 |
| 26 | YASHPAL SINGH BHATI | UPRERAAGT10579 |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 7 Nov 2021.
Sanctioned by Noida Authority · 29,110 sqm of land · an approved plan of 3 blocks and 644 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| M/V/N/2016/IV-1493/940 | 8 Nov 2016 | 7 Nov 2021 | 7 Nov 2026 | 30 Sept 2026 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 29 Mar 2027.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 30 Sept 2026 | 29 Mar 2027 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
14 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| PLOT NO- SC-01/01, SEC-152, NOIDA, G.B Nagar U.P | 29110.35 | Plot |
| Lease deed · 7037 The deed by which a development authority leased the land to the promoter, with the term and the conditions on it. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 7 Feb 2019 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 6 Feb 2019 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 6 Feb 2019 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 6 Feb 2019 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 6 Feb 2019 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 6 Feb 2019 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 6 Feb 2019 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 25 Feb 2019 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 6 Feb 2019 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 6 Feb 2019 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 6 Feb 2019 ↗ |
Quarterly progress reports
26 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
26 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 49.77% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 60.06% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 68.84% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 73.51% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | ATS HOMES PRIVATE LIMITED |
| Role | Promoter · current |
| RERA ID | UPRERAPRM2872 |
| PAN | AAJCA4360K |
| CIN / TAN | U70101DL2010PTC207984 |
| Name of chairman | Mr Getamber Anand |
| Registered address | ATS Tower, Plot-16, Sector-135, Noida-201305 |
| RERA contact | |
| Registered since | 2017 |
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | ATS HOMES PVT LTD ATS PR PH 2 PROJECT RERA ESCROW A/CBankHDFCBranchSector 104, NoidaA/C no.IFSCHDFC0004394 |
What has changed on this record
9 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Quarterly progress report 2026-Q2 | QPR 2026-Q2 newly filed with RERA | 15 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 84 (Under Registration - 2 ) → 84 (Under Registration - 1 ) changed in Estanzo’s record | 7 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 83 (Under Registration - 1 ) → 84 (Under Registration - 2 ) changed in Estanzo’s record | 1 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 83 (Under Registration - 2 ) → 83 (Under Registration - 1 ) changed in Estanzo’s record | 29 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 83 (Under Registration - 3 ) → 83 (Under Registration - 2 ) changed in Estanzo’s record | 23 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 83 (Under Registration - 4 ) → 83 (Under Registration - 3 ) changed in Estanzo’s record | 13 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 83 (Under Registration - 5 ) → 83 (Under Registration - 4 ) changed in Estanzo’s record | 7 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 82 (Under Registration - 4 ) → 83 (Under Registration - 5 ) changed in Estanzo’s record | 1 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 81 (Under Registration - 3 ) → 82 (Under Registration - 4 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 7 Oct 2026 · 8 movements on record |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about ATS Picturesque Reprieves Phase 2
Is ATS Picturesque Reprieves Phase 2 RERA registered?
Yes. ATS Picturesque Reprieves Phase 2 is registered with UPRERA under registration number UPRERAPRJ396176, registered on 27 Feb 2019. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for ATS Picturesque Reprieves Phase 2?
The completion date filed with UPRERA is 29 Mar 2027. No completion certificate is on record yet.
Who is the builder of ATS Picturesque Reprieves Phase 2?
ATS HOMES PRIVATE LIMITED is the promoter entity that filed ATS Picturesque Reprieves Phase 2 with UPRERA (promoter RERA ID UPRERAPRM2872). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted ATS Picturesque Reprieves Phase 2 more time to complete?
UPRERA's record carries 1 completion extension for ATS Picturesque Reprieves Phase 2, the latest running to 29 Mar 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does ATS Picturesque Reprieves Phase 2 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is ATS Picturesque Reprieves Phase 2 located?
ATS Picturesque Reprieves Phase 2 is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in ATS Picturesque Reprieves Phase 2?
The unit plan filed with UPRERA lists OTHER, 4 BHK, 3 BHK and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in ATS Picturesque Reprieves Phase 2?
The approved unit plan filed with UPRERA runs from 115 to 247 m² of carpet area (about 1,240 to 2,655 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in ATS Picturesque Reprieves Phase 2?
The approved unit plan describes 3 blocks and 644 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is ATS Picturesque Reprieves Phase 2?
About 90 units per acre: 644 planned units across 7.19 acres (29,110 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗