Estanzo

Timeline Bar

Registered1 Aug 2017
Promised25 Oct 2024
Today3 Aug 2026

Timeline

Promised completion25 Oct 2024
Revised completion25 Oct 2024
Actual completion
Possession delay21 mo delay

Registration & Cost Details

Registration fee (in ₹)₹1,02,677
Project cost (in ₹ Lakhs)₹1,97,500 Lakhs
Project duration90 months
Project categoryResidential
Locality
Original start date26 Oct 2017
Proposed start date26 Oct 2017

Inventory

Total units932
Unit TypeUnitsCarpet Area (sqm)
3 BHK774115.2–246.66
4 BHK140191.25–191.29
PENTHOUSE18155.15–212.47

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailhomes@atsgreens.com
Coordinator9999597406
AddressATS Tower, Plot-16, Sector-135, Noida-201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
M/V/N/2016/IV-1493/9408 Nov 20167 Nov 202125 Oct 20247 Nov 2026

Land Parcels

Khasra No.AreaPlot Type
PLOT NO- SC-01/01, SEC-152, G.B Nagar, NOIDA38450.15Plot

Approved Unit Plan

Unit plan rows on file117
Total flats (sum of rows)932
BlocksTower-18,19,20,21,22,31 & 32, Tower-23 & 24, Tower-25 & 30
Floor types3 BHK, 4 BHK, PENTHOUSE, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
703730 Dec 2015

Frequently Asked Questions

What is the RERA registration number of ATS Picturesque Reprieves Phase 1?

The RERA registration number of ATS Picturesque Reprieves Phase 1 is UPRERAPRJ631, as recorded on the UP-RERA portal.

What is the RERA status of ATS Picturesque Reprieves Phase 1?

As reported by UP-RERA, the status of ATS Picturesque Reprieves Phase 1 is "Registered".

Where is ATS Picturesque Reprieves Phase 1 located?

As reported to UP-RERA, ATS Picturesque Reprieves Phase 1 is located at Plot No: SC - 01/01, SECTOR - 152, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will ATS Picturesque Reprieves Phase 1 be completed?

The latest completion date reported to UP-RERA for ATS Picturesque Reprieves Phase 1 is 25 Oct 2024.

Is ATS Picturesque Reprieves Phase 1 delayed?

Measured against the latest completion date reported to UP-RERA, ATS Picturesque Reprieves Phase 1 is 21 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026