AURUM ALUMNI ACCORD

UPRERARegistered

AURUM ALUMNI ACCORD is a RERA-registered mixed project by FUTUREWORLD CONSTRUCTIONS PRIVATE LIMITED in JAYPEE GREEN SPORT CITY, SDZ SECTOR 25, YEIDA AREA, Gautam Budh Nagar (RERA ID UPRERAPRJ804196). Registered with a completion deadline of 10 Jul 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
9.15%Q3'25
9.95%Q4'25
14.98%Q1'26
21.29%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ804196
Project categoryMixed
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryYamuna Expressway Authority
Proposed start1 Dec 2024
Project duration44 months
AddressGH-A6, JAYPEE GREEN SPORT CITY, SDZ SECTOR 25, YEIDA AREA, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressA-162 , Sector -136 , noida
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PATRANK/Y.E.A/NIYOJAN/661/2024

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered13 Dec 2024
Original completion10 Jul 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,01,250
Sanctioning authorityYamuna Expressway Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors213 · 9 · 22 (units from plan)
Homes · commercial units210 · 3 (shops and offices filed in the same plan)
  • 4 BHK210 99%
  • SHOP3 1%
ConfigurationUnitsCarpet area
4 BHK210151
SHOP315
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
COMMUNITY HALL · OTHER10—
S1 · SHOP1115
S2 · SHOP1115
S3 · SHOP1115
TOWER A1 · 4 BHK2142151
TOWER A2 · 4 BHK2142151
TOWER A3 · 4 BHK2142151
TOWER B · 4 BHK2142151
TOWER C · 4 BHK2142151
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUJ AGARWAL
License CA/96/19503
A-244, KAUSHAMBI, GHAZIABAD
Engineer
PIYUSH KUMAR GUPTA
II C/199, NEHRU NAGAR, GHAZIABAD
Contractor
FUTUREWORLD CONSTRUCTIONS PVT LTD
F NO 56-E-A-3 KONDALI GHAROLI, EAST DELHI , DELHI
Sr.Development work declared to RERA
1Demarcation of Plots
the plot has (12442 sqm. ) of the are that will be demarcated as per the sanction and survey drawing.
2Boundary Wall
A boundary wall of ( approx 1024 m running length ) Rcc / brick with plaster and railing will be prepared
3Road Work
7.5 M wide access road to all towers will provided and the road will be designed to take up live load as per approvals .
4Footpaths
Designed a footpath in the complex as a walkway and jogging track .
5Water Supply Including Drinking Water Facilities
YEIDA authority shall supply water for the entire society and shall be traeated and pumped to all the houses .
6Sewer System
Centaralized STP to treat the sewage will be designed and provided .
7Drain
Rainwater drains will be provided as per the design to carry all the rainwater of the complex in a ring ling . the same shall be connected to rain water harvesting pits .
8Parks
Beautiful parks will be made for all the residents to enjoy . the parks will have relaxing and entertainment zones along with space meant for senior citizens ,kids and enjoyment.
9Tree Planting
As per the approved building plan , an apt no. of trees will be provided .The trees will be a mix of evergreen and flowering trees .there will be themed tree plantations and the complex will have a lush green outlook.
10Design For Electric Supply Including Street Lighting
power supply from Noida electricity board and street lighting as per the approved building plan . the lighting will be adequate to lit up the dark spaces and all pathways as well as driveways .
11Community Buildings
The club will be made as per the approved building plan and it will have all the modern facilities . social gathering places are also being provided in the complex .the residents will be able to enjoy in the club as as place for social gatherings and relaxation .
12Treatment and Disposal System of Sewage and Sullage water
Centralized STP to treat the sewage .the STP will treat all the sewage generate from the society and will be maintained properly .
13Solid Waste Management And Disposal System
collection , storage and disposal will be done as per sanction .good to collect of solid waste in the segregated system will be done so that the recyclable waste can be separated in an efficient way from the wet kitchen waste.
14Water Conservation System
rainwater harvesting system is being provided to conserve rainwater and dual flush system will also be provided with water saving fitting .
15Energy Management System Including Use of Renewable Energy
Usage of LED lights will be used all over the project and the use of solar lights will also be explored .
16Fire Protection And Fire Safety System
As per approved building plan , we will design the best fire protection system consisting of sprinklers , smoke detectors and fire alarms .
17Social Infrastructure And Other Public Amenities Including Public Health Services
Social gathering places are being provided in the complex . these places will be spread over the whole complex and residents will be able to enjoy the same .swimming pool , gym , indoor play areas , playing courts all these facilities will be provided .
18Emergency Evacuation Services
As per the approved building plan and fire approvals , fire staircase are being provided.all fir exit passages shall be kept clear all the time and proper audits as we as fire drills will be done in the society .
19Other Miscellaneous Work
as per approved building plans ,any and all the work will be done to make the project very comfortable and good quality for all the residents.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 10 Jul 2028.

Sanctioned by Yamuna Expressway Authority · 12,442 sqm of land · an approved plan of 9 blocks and 213 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PATRANK/Y.E.A/NIYOJAN/661/202418 Sept 202410 Jul 202810 Jul 203110 Jul 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
PLOT NO GH-A612442Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · I-4285/16
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · POSSESSION LETTER (JAYPEE TO FUTURE WORLD)
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Lease deed · LEASE.DEED.YEIDAtoJAYPEE(11625/11)
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · MASTER.PLAN_SECTOR-25
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · NO DUES CERTFICATE ..CLEARCOPY
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · LAYOUTPLANsector25yeida
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Registry document · LAND SEARCH REAPORT
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New26 Oct 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New26 Oct 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New11 Nov 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New26 Oct 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New26 Oct 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New26 Oct 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New26 Oct 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New26 Oct 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New11 Nov 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New11 Nov 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Oct 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Oct 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New26 Oct 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New26 Oct 2024 ↗

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2024-Q3 to 2026-Q1.

QuarterConstructionCertificates
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q29.15%CA ↗ · Arch ↗ · Eng ↗
2025-Q39.95%CA ↗ · Arch ↗ · Eng ↗
2025-Q414.98%CA ↗ · Arch ↗ · Eng ↗
2026-Q121.29%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameFUTUREWORLD CONSTRUCTIONS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM326770
PANAACCF2226J
CIN / TANDELF05310E
Name of chairmanMr. Sachin Garg
Registered addressA-162 , Sector -136 , noida
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
FCPL AURUM ALUMNI ACCORD COLLECTION ACBankHDFC BANKBranchHDFC BANK LTDBranch addressELDECO STUDIO APARTMENT, PLOT NO 3, SECTOR 93 A, NOIDABranch districtUttar PradeshA/C no.IFSCHDFC0002830Branch emailpunit.kaur1@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
FCPL AURM ALUMNI ACCORD SEPARATE ACBankHDFC BANKBranchHDFC BANK LTDBranch addressELDECO STUDIO APARTMENT , PLOT NO 3, SECTOR 93 A, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
FCPL AURM ALUMNI ACCORD TRANSACTION ACBankHDFC BANKBranchHDFC BANK LTDBranch addressELDECO STUDIO APARTMENT PLOT NO 3, SECTOR 93 A, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002830
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about AURUM ALUMNI ACCORD

Is AURUM ALUMNI ACCORD RERA registered?

Yes. AURUM ALUMNI ACCORD is registered with UPRERA under registration number UPRERAPRJ804196, registered on 13 Dec 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for AURUM ALUMNI ACCORD?

The completion date filed with UPRERA is 10 Jul 2028. No completion certificate is on record yet.

Who is the builder of AURUM ALUMNI ACCORD?

FUTUREWORLD CONSTRUCTIONS PRIVATE LIMITED is the promoter entity that filed AURUM ALUMNI ACCORD with UPRERA (promoter RERA ID UPRERAPRM326770). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does AURUM ALUMNI ACCORD have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is AURUM ALUMNI ACCORD located?

AURUM ALUMNI ACCORD is registered in JAYPEE GREEN SPORT CITY, SDZ SECTOR 25, YEIDA AREA, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in AURUM ALUMNI ACCORD?

The unit plan filed with UPRERA lists 4 BHK, SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in AURUM ALUMNI ACCORD?

The approved unit plan filed with UPRERA runs from 15 to 151 m² of carpet area (about 161 to 1,620 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in AURUM ALUMNI ACCORD?

The approved unit plan describes 9 blocks and 213 units of which 210 are homes and 3 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is AURUM ALUMNI ACCORD?

About 69 units per acre: 213 planned units across 3.07 acres (12,442 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗