Timeline Bar
Registered14 Aug 2017
Promised30 Jun 2018
Completed7 Mar 2020
Timeline
Promised completion30 Jun 2018
Revised completion30 Jun 2018
Actual completion7 Mar 2020
Possession delay20 mo delay
Registration & Cost Details
Registration fee (in ₹)₹16,000
Project cost (in ₹ Lakhs)₹1,300 Lakhs
Project duration48 months
Project categoryResidential
Locality—
Original start date18 Jul 2014
Proposed start date18 Jul 2014
Inventory
Total units56
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 21 | 223.32 |
| 3 BHK | 35 | 451.95 |
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile9415375704
Emailcbtiwari2233@gmail.com
Coordinator9415375704
Address23C SIDDHARTH RESIDENCY KOSHALESH NAGAR NARIYA VARANASI 221005
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 170 | 19 Sept 2015 | 18 Sept 2020 | 30 Jun 2018 | 18 Sept 2023 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 79/1 | 930.25 | — |
| 80 | 1172.33 | — |
Approved Unit Plan
Unit plan rows on file14
Total flats (sum of rows)56
Blocks1
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 486/57-78/2424/1 | 26 Feb 2014 | — | — |
| 192/361-404/2400/1 | 27 Jan 2014 | — | — |
| 242/63-86/2405/1 | 31 Jan 2014 | — | — |
| 526/23-52/2427/1 | 3 Mar 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of BENARAS HEIGHT?
The RERA registration number of BENARAS HEIGHT is UPRERAPRJ7227, as recorded on the UP-RERA portal.
What is the RERA status of BENARAS HEIGHT?
As reported by UP-RERA, the status of BENARAS HEIGHT is "Registered".
Where is BENARAS HEIGHT located?
As reported to UP-RERA, BENARAS HEIGHT is located at Varanasi, Varanasi, Uttar Pradesh.
Is BENARAS HEIGHT completed?
As reported to UP-RERA, BENARAS HEIGHT was completed on 7 Mar 2020.
Is BENARAS HEIGHT delayed?
Measured against the latest completion date reported to UP-RERA, BENARAS HEIGHT is 20 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.