Timeline Bar

Registered1 Jan 2022
Promised6 Jul 2024
Today4 Aug 2026

Timeline

Promised completion6 Jul 2024
Revised completion6 Jul 2024
Actual completion
Possession delay25 mo delay

Registration & Cost Details

Registration fee (in ₹)₹25,500
Project cost (in ₹ Lakhs)₹1,736 Lakhs
Project duration58 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Oct 2021

Inventory

Total units31
Unit TypeUnitsCarpet Area (sqm)
3 BHK13130.53
4 BHK18153.43

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile8077991454
Emailbibhabbuilders86@gmail.com
Coordinator9719341222
Address86,BIBHAB TRADE CENTRE, BYE PASS ROAD AGRA-282007

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q239.2%
2025-Q342.3%
2025-Q442.3%
2026-Q147.3%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1374/B.F.H-2/03/13-14/ADA11 Jul 201610 Jul 20216 Jul 20246 Jul 2024
1374/B.F.H-2/03/13-14/ADA

Revalidated: 1374/B.F.H-2/03/13-14/ADA (11 Jul 2016)

11 Jul 201610 Jul 2021

Revalidated upto: 10 Jul 2024

6 Jul 202411 Jul 2024

Land Parcels

Khasra No.AreaPlot Type
Minjumla Kh.No. 282and 345 inclusive Plot No. 1 to 94034.05Khasra

Approved Unit Plan

Unit plan rows on file14
Total flats (sum of rows)31
BlocksBIBHAB LACASA
Floor types3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of BIBHAB LACASA?

The RERA registration number of BIBHAB LACASA is UPRERAPRJ120936, as recorded on the UP-RERA portal.

What is the RERA status of BIBHAB LACASA?

As reported by UP-RERA, the status of BIBHAB LACASA is "Registered".

Where is BIBHAB LACASA located?

As reported to UP-RERA, BIBHAB LACASA is located at Agra, Agra, Uttar Pradesh.

When will BIBHAB LACASA be completed?

The latest completion date reported to UP-RERA for BIBHAB LACASA is 6 Jul 2024.

Is BIBHAB LACASA delayed?

Measured against the latest completion date reported to UP-RERA, BIBHAB LACASA is 25 months beyond that date.