BIBHAB LACASA

UPRERARegistered

BIBHAB LACASA is a RERA-registered residential project by CHANDRA CONSTRUCTION COMPANY in Agra (RERA ID UPRERAPRJ120936). Registered with a completion deadline of 5 Jul 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
39.17%Q3'25
42.34%Q4'25
42.34%Q1'26
47.25%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ120936
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAgra Development Authority
Proposed start1 Oct 2021
Project duration58 months
AddressAgra, Agra
TehsilAgra
Applicant typePartnership Firm
Applicant address86,BIBHAB TRADE CENTRE, BYE PASS ROAD AGRA-282007
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. valid to

    Permit revalidated

    1374/B.F.H-2/03/13-14/ADA

  2. 2 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Jan 2022
Original completion6 Jul 2024
Revised completion5 Jul 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹25,500
Sanctioning authorityAgra Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors31 · 1 · 9 (units from plan)
  • 4 BHK18 58%
  • 3 BHK13 42%
ConfigurationUnitsCarpet area
4 BHK18153
3 BHK13131
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
BIBHAB LACASA · OTHER, 4 BHK, 3 BHK931131-153
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Rohit Khandelwal
License CA 98/22525
717,Gaur Heights, Sector 4, Vishali, Ghaziabad, 201010
Engineer
P.K. Gupta
BF-102, First Floor, Janakpuri, New Delhi-110058
Contractor
Self
86, Bibhab Trade Center, Bypass Road, Agra 282007
Sr.Development work declared to RERA
1Demarcation of Plots
The project land will be demarcated with the boundary-wall. The setbacks of the building and peripheral wall will be established as per approved layout.
2Boundary Wall
A 6 to 8 feet high boundary wall will be constructed . The Brick wall will be plastered and painted. The foundation of the wall will be minimum of 4feet depth. The design of the same will be earthquake resistant
3Road Work
The Roads will be laid to the desired width as approved in sanctioned plan. The road will be built-up on the compacted earth with the layer of 100mm Lean cement concrete. The Paver block resistant to seasonal and traffic abrasions will be laid of the depth of 4 inches and M-20 strength
4Footpaths
Interlocking paver tiles will be laid in the footpath areas laid over the compacted earth, 2 inch sand bed. A 4 inch interlocking tiles will be laid in color patterns to enhance the visibility and walking experience.
5Water Supply Including Drinking Water Facilities
A potable ground water supply will be arranged for the domestic use of the project. The ground water will be pumped through a submersible pump set the underground water tank from where the water will be pumped to terrace tank to e further supplied to each flat.
6Sewer System
A sewerage system consisting of soil pipes and U-chambers will be installed in the entire project carrying the sewer to the man holes. The Pipelines will also have the check points for maintenance. The multiple man holes will be installed. The sewer will be carried through pipe arrangement to sewage treatment plant
7Drain
Closed lined drains will be installed/ constructed along the the project boundaries designed to carry the domestic / runoffs. The trapezium shaped drains installed on the DLC will create the head for smooth and rapid egress to drain water.
8Parks
Lush green park along with play area for kids will be constructed/ developed in the project as per the sanctioned plan
9Tree Planting
Multi tree types will be planted in the park area and at suitable locations near the boundary. The plants will be so selected as to enhance the greenery of the project and at the same time causing zero interference with the functioning of the utilities of the project.
10Design For Electric Supply Including Street Lighting
The electrical connection and loads will be as per design specification of the the Torrent Power Limited. The Electrical room will also be constructed . The connections will lead to each flat through chain of distribution for domestic purpose. The Street lights will be installed along the boundary wall of the project and the common open areas.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
A state of art multi stage sewage treatment plant will be installed in the project . The domestic sewage collected will be treated to bring the effluents within the permissible limit before being disposed to the municipal drain.
13Solid Waste Management And Disposal System
The waste collection chutes and the dustbins will be installed to all the
14Water Conservation System
The 70 m bore will be dug and the perforated pipe will be installed for collection of water in order to recharge te water table. . A stratified collection camber will be constructed to collect and filter the water before being allowed to enter the perforated pipes to keep the water table clean
15Energy Management System Including Use of Renewable Energy
Not Applicable- Yet the energy saving practice will be observed and the LED lightings will be installed at all common locations.
16Fire Protection And Fire Safety System
The fire norms will be applied through out the project . There will be wet risers on all floors, Pumping by Steve alarm system. The fire extinguishers will be installed at all floors and common areas.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
The stairwell are designed for minimum width required for easy and rapid egress of the occupants in case of fire. The installations will be done as per norms of fire safety department.
19Other Miscellaneous Work
All the activities for the betterment of the project.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 10 Jul 2021. 1 of them carries a revalidation, valid to 10 Jul 2024.

Sanctioned by Agra Development Authority · 4,034 sqm of land · an approved plan of 1 block and 31 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
1374/B.F.H-2/03/13-14/ADA11 Jul 201610 Jul 20216 Jul 20246 Jul 2024—
1374/B.F.H-2/03/13-14/ADA11 Jul 201610 Jul 202111 Jul 20246 Jul 202411 Jul 2016
valid to 10 Jul 2024
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 5 Jul 2026.

#Granted fromExtended uptoNote
16 Jul 20245 Jul 2026—

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Minjumla Kh.No. 282and 345 inclusive Plot No. 1 to 94034.05Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 4045
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New22 Nov 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New22 Nov 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New22 Nov 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New22 Nov 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Oct 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Oct 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Oct 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New22 Nov 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New22 Nov 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New22 Nov 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Oct 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Oct 2021 ↗

Quarterly progress reports

19 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

19 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2026-Q1.

QuarterConstructionCertificates
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q239.17%CA ↗ · Arch ↗ · Eng ↗
2025-Q342.34%CA ↗ · Arch ↗ · Eng ↗
2025-Q442.34%CA ↗ · Arch ↗ · Eng ↗
2026-Q147.25%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCHANDRA CONSTRUCTION COMPANY
RolePromoter · current
RERA IDUPRERAPRM153495
PANAADFC2963R
CIN / TANAGRC11591G
Registered address86,BIBHAB TRADE CENTRE, BYE PASS ROAD AGRA-282007
RERA contact
Registered since2021
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Agra

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Chandra Construction Company Collection Account For Bibhab LacasaBankICICIBranchBelanganj, AgraBranch address6/313A, Baroliya Building, Belanganj, AgraBranch districtAgraA/C no.IFSCICIC0003519
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Chandra Construction Company Separate Account For Bibhab LacasaBankICICIBranchBelanganj, AgraBranch address6/313A, Baroliya Building, Belanganj, AgraBranch districtAgraA/C no.IFSCICIC0003519
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Chandra Construction Company Transaction Account For Bibhab LacasaBankICICIBranchBelanganj, AgraBranch address6/313A, Baroliya Building, Belanganj, AgraBranch districtAgraA/C no.IFSCICIC0003519
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about BIBHAB LACASA

Is BIBHAB LACASA RERA registered?

Yes. BIBHAB LACASA is registered with UPRERA under registration number UPRERAPRJ120936, registered on 1 Jan 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for BIBHAB LACASA?

The completion date filed with UPRERA is 5 Jul 2026. No completion certificate is on record yet.

Who is the builder of BIBHAB LACASA?

CHANDRA CONSTRUCTION COMPANY is the promoter entity that filed BIBHAB LACASA with UPRERA (promoter RERA ID UPRERAPRM153495). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted BIBHAB LACASA more time to complete?

UPRERA's record carries 1 completion extension for BIBHAB LACASA, the latest running to 5 Jul 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does BIBHAB LACASA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is BIBHAB LACASA located?

BIBHAB LACASA is registered in Agra, as filed with UPRERA.

What configurations are available in BIBHAB LACASA?

The unit plan filed with UPRERA lists OTHER, 4 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in BIBHAB LACASA?

The approved unit plan filed with UPRERA runs from 131 to 153 m² of carpet area (about 1,405 to 1,652 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in BIBHAB LACASA?

The approved unit plan describes 1 block and 31 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is BIBHAB LACASA?

About 31 units per acre: 31 planned units across 1.00 acres (4,034 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗