Promised30 Oct 2019
Registered3 Sept 2021
Today4 Aug 2026

Timeline

Promised completion30 Oct 2019
Revised completion30 Oct 2019
Actual completion
Possession delay81 mo delay

Registration & Cost Details

Registration fee (in ₹)₹60,750
Project cost (in ₹ Lakhs)₹3,100 Lakhs
Project duration76 months
Project categoryMixed
Locality
Original start date
Proposed start date4 Jul 2013

Inventory

Total units292
Unit TypeUnitsCarpet Area (sqm)
2 BHK6748.524–118.052
SHOP2256.235–528.55

Promoters & Contact

Contact Details

Applicant TypeLocal authority
Mobile7290061455
Emailmanishonmail123@gmail.com
Coordinator9415550089
AddressLaxmi Nagar,Zila Panchayat, Bulandshahr - 203001

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
9971/Bu.Vi.Pra/20139 May 20138 May 201830 Oct 20198 May 2019

Land Parcels

Khasra No.AreaPlot Type
6789105Khasra

Approved Unit Plan

Unit plan rows on file132
Total flats (sum of rows)292
Total shops225
Blocks1
Floor types2 BHK, SHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of BULAND CITY CENTER?

The RERA registration number of BULAND CITY CENTER is UPRERAPRJ377342, as recorded on the UP-RERA portal.

What is the RERA status of BULAND CITY CENTER?

As reported by UP-RERA, the status of BULAND CITY CENTER is "Registered".

Where is BULAND CITY CENTER located?

As reported to UP-RERA, BULAND CITY CENTER is located at Bulandshahr, Bulandshahr, Uttar Pradesh.

When will BULAND CITY CENTER be completed?

The latest completion date reported to UP-RERA for BULAND CITY CENTER is 30 Oct 2019.

Is BULAND CITY CENTER delayed?

Measured against the latest completion date reported to UP-RERA, BULAND CITY CENTER is 81 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026