Timeline Bar
Registered28 Jul 2017
Promised8 Aug 2021
Revised7 Feb 2022
Completed3 Jul 2025
Timeline
Promised completion8 Aug 2021
Revised completion7 Feb 2022
Actual completion3 Jul 2025
Possession delay41 mo delay
Registration & Cost Details
Registration fee (in ₹)₹2,18,500
Project cost (in ₹ Lakhs)₹33,000 Lakhs
Project duration96 months
Project categoryResidential
Locality—
Original start date18 Oct 2013
Proposed start date9 Aug 2016
Inventory
Total units735
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 52 | 44–55 |
| 2 BHK | 413 | 65.3–98.8 |
| 3 BHK | 170 | 111.7–126.77 |
| 4 BHK | 72 | 116–153.8 |
| SHOP | 6 | 15.01–143.41 |
| STUDIO | 7 | 22.3–37.28 |
| OTHER | 15 | 5.3–251.75 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile7607900304
Emailashishalokchandra@gmail.com
Coordinator7607119900
Address1st Floor Nikhilesh Palace,
17/4 Ashok Marg
Lucknow 226 001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 40361 | 12 Aug 2016 | 8 Aug 2021 | 8 Aug 2021 | 7 Aug 2024 |
| 40361 | 12 Aug 2016 | 8 Aug 2021 | 8 Aug 2021 | 7 Feb 2023 |
| 40361 | 12 Aug 2016 | 28 Apr 2021 | 7 Feb 2022 | 8 Aug 2023 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 48P/46P/64P/429P | 13361.348 | — |
| 429P/417P | 16817.5 sq mtr | — |
| 416P/417P | 7761.924 sq mtr | — |
| 416P/590P/591P/592P/594P | 4743.398 sq mtr | — |
| 48P/46P/64P/429P | 13361.348 | Khasra |
| 429P/417P | 16817.5 | Khasra |
| 416P/417P | 7761.924 | Khasra |
| 416P/590P/591P/592P/594P | 4743.398 | Khasra |
Approved Unit Plan
Unit plan rows on file308
Total flats (sum of rows)735
Total shops6
BlocksA, B, C, D
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP, STUDIO, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 26428 | 4 Dec 2014 | — | — |
| 7017 | 27 Mar 2014 | — | — |
| 7018 | 27 Mar 2014 | — | — |
| 205914 | 17 Apr 2013 | — | — |
| 26428 | 4 Dec 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of Chandra Panorama?
The RERA registration number of Chandra Panorama is UPRERAPRJ3425, as recorded on the UP-RERA portal.
What is the RERA status of Chandra Panorama?
As reported by UP-RERA, the status of Chandra Panorama is "Registered".
Where is Chandra Panorama located?
As reported to UP-RERA, Chandra Panorama is located at Lucknow, Lucknow, Uttar Pradesh.
Is Chandra Panorama completed?
As reported to UP-RERA, Chandra Panorama was completed on 3 Jul 2025.
Is Chandra Panorama delayed?
Measured against the latest completion date reported to UP-RERA, Chandra Panorama is 41 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026