Estanzo

Timeline Bar

Registered13 Jun 2018
Promised8 Jun 2022
Completed3 Nov 2022
Revised7 Dec 2022

Timeline

Promised completion8 Jun 2022
Revised completion7 Dec 2022
Actual completion3 Nov 2022
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹25,500
Project cost (in ₹ Lakhs)₹2,200 Lakhs
Project duration55 months
Project categoryResidential
Locality
Original start date
Proposed start date9 Jun 2018

Inventory

Total units98
Unit TypeUnitsCarpet Area (sqm)
1 BHK646.93
2 BHK6380
3 BHK25118.5–126.93
4 BHK482.13–208.37

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9889844677
Emailsales@citizenhomes.in
Coordinator9307502104
AddressA/1 MG MARG, CIVIL LINES, ALLAHABAD-211001 Uttar Pradesh India

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
-101/PR AA (TA. SA. -2) ZONE 1/GR HA/2017-1820 Jan 201820 Jan 20238 Jun 2022

Revalidated: 101/PR AA/ZONE-1/FAR/2018-19DATE27/02/2021 (20 Jan 2023)

1 Jan 190020 Jan 2023

Revalidated upto: 20 Jan 2023

7 Dec 202220 Jan 2023

Land Parcels

Khasra No.AreaPlot Type
A/E/5 BANGLOW NO 48/12A/1 AND 46/21A, COLVIN ROAD4055Plot

Approved Unit Plan

Unit plan rows on file23
Total flats (sum of rows)98
BlocksBLOCK A, BLOCK B
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of CITIZEN NEOHEIGHTS?

The RERA registration number of CITIZEN NEOHEIGHTS is UPRERAPRJ16514, as recorded on the UP-RERA portal.

What is the RERA status of CITIZEN NEOHEIGHTS?

As reported by UP-RERA, the status of CITIZEN NEOHEIGHTS is "Registered".

Where is CITIZEN NEOHEIGHTS located?

As reported to UP-RERA, CITIZEN NEOHEIGHTS is located at Allahabad **, Prayagraj, Uttar Pradesh.

Is CITIZEN NEOHEIGHTS completed?

As reported to UP-RERA, CITIZEN NEOHEIGHTS was completed on 3 Nov 2022.

Is CITIZEN NEOHEIGHTS delayed?

Measured against the latest completion date reported to UP-RERA, CITIZEN NEOHEIGHTS is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.