DARSHNA ENCLAVEUPRERA
Home › Projects › Hapur › DARSHNA ENCLAVE

DARSHNA ENCLAVE

UPRERARegisteredConstruction 100% · 2026 Q1updated 3 Aug 2026

DARSHNA ENCLAVE is a RERA-registered real-estate project in PIPLABANDPUR, Hapur (RERA ID UPRERAPRJ391760). Registered with a completion deadline of 31 May 2028. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
Project cost
₹8
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
30 Jun 2025

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2026 Q1
—Q3'24
—Q4'24
—Q1'25
59.9%Q2'25
90.59%Q3'25
95.98%Q4'25
100%Q1'26

Basic details

RERA IDUPRERAPRJ391760
Applicant typeProprietorship Firm
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start31 Dec 2024
Project duration42
AddressKHASRA NUMBER 87,88,89 VILLAGE PIPLABANDPUR TEHSIL DHAULANA DISTRICT HAPUR UTTAR PRADESH, PIPLABANDPUR, Dhaulana, Hapur

Registration & timeline

RERA registered30 Jun 2025
Promised completion31 May 2028
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹74,500

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
Plotted Resi development/ Plotted Housing/01482/HPDA/LD/24-25/0133/2608202416 Oct 202415 Oct 202931 May 2028

Land & documents

2 filings
KhasraAreaType
87,88,8912180Khasra
96/21640Khasra

Quarterly progress reports

7 filed reports
QuarterConstructionCertificatesSource
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q259.9%CA · Arch · Engview ↗
2025-Q390.59%CA · Arch · Engview ↗
2025-Q495.98%CA · Arch · Engview ↗
2026-Q1100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1.

Nearby projects

Hapur

Other projects registered in Hapur.

AANAND VIHAR RESIDENTIAL SCHEME
UPRERA no delay on record
ANANTTAM GREENS
UPRERA no delay on record
Aspire City Phase-1
UPRERA no delay on record
Aspire City Phase-2
UPRERA no delay on record
CHANDRA KANTA RESIDENCY
UPRERA ▲ 25 mo
Construction of 264 EWS Houses Hindalpur Hapur Under PMAY
UPRERA ▲ 13 mo

Common questions about DARSHNA ENCLAVE

Is DARSHNA ENCLAVE RERA registered?

Yes. DARSHNA ENCLAVE is registered with UPRERA under registration number UPRERAPRJ391760, registered on 30 Jun 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for DARSHNA ENCLAVE?

The completion date filed with UPRERA is 31 May 2028. No completion certificate is on record yet, and that deadline has not passed.

Where is DARSHNA ENCLAVE located?

DARSHNA ENCLAVE is registered in PIPLABANDPUR, Hapur, as filed with UPRERA.

Data as reported by UPRERA, last collected 3 Aug 2026. official source ↗

At a glance

StatusRegistered
QPR filingNo default reported
DistrictHapur
LocalityPIPLABANDPUR
Last updated3 Aug 2026

Location

AddressKHASRA NUMBER 87,88,89 VILLAGE PIPLABANDPUR TEHSIL DHAULANA DISTRICT HAPUR UTTAR PRADESH
View on map ↗

RERA buyer helpline

Coordinator9953766108
Helpline9953766108
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=4rn7NnbQXQ0=&hfFlag=xH7SHZuECpA=&NPJ6RAme=3UnZW2dot0G3MSKsVhLlWQ==&PaURJEMAN4=ZL9MNERkNdauSsYmS4ZoC3OiRTP4e50+&IRSAHEB=D6PY3lyims8=)