DINESH NAGAR is a RERA-registered residential project by Platina Real States Pvt Ltd in Ghaziabad (RERA ID UPRERAPRJ4908). Registered with a completion deadline of 31 May 2019.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ4908 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Hapur Pilkhuwa Development Authority |
| Proposed start | 1 Jun 2015 |
| Original start | 1 Jun 2015 |
| Project duration | 48 months |
| Address | Hapur, Ghaziabad |
| Tehsil | Hapur |
| Applicant type | Company |
| Applicant address | Dinesh Nagar Pilkhuwa,Hapur |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Permit revalidated (2)
3 building permits sanctioned
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 31 Jul 2017 |
| Original completion | 31 May 2019 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 17 Apr 2024 |
| Registration fee | ₹20,000 |
| Sanctioning authority | Hapur Pilkhuwa Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 1 BHK92 90%
- SHOP10 10%
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 92 | 28-49 |
| SHOP | 10 | 8-15 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Block-38 · 1 BHK | 4 | 32 | 28-33 |
| Block-42 · 1 BHK | 4 | 24 | 35-49 |
| Block-43 · 1 BHK | 4 | 24 | 35-49 |
| Block-45 · SHOP, 1 BHK | 4 | 22 | 8-33 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots DINESH NAGAR Group Housing PROJECT Pabla Modinagar Road near Pilkhuwa Railway station Pilkhuwa. |
| 2 | Boundary Wall Brick work Boundry wall. |
| 3 | Road Work Interlocking block have been provided at road area. |
| 4 | Footpaths Interlocking block have been provided at foothpath. |
| 5 | Water Supply Including Drinking Water Facilities Overhead Water Tank of 350 KL capacity. |
| 6 | Sewer System Underground System using RCC (NP-2) Sewer pipes. |
| 7 | Drain Open Drainage System with cover blocks. |
| 8 | Parks Parks , Green Area Provided as per approved drawings by H.P.D.A. |
| 9 | Tree Planting Ashoka and kadamn trees already planted. |
| 10 | Design For Electric Supply Including Street Lighting Transformer (Compact Sub station) of 400 KVA, 11 / 0.4 KV capacity shall be used along with necessary switch-gear for distributing electricity at LT voltage. All street / landscape lighting shall be LED based. |
| 11 | Community Buildings Not applicable as per approved drawings by H.P.D.A. |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP already existed. Treated water shall be used for irrigation, carwash, pathway cleaning & excess water shall be discharged into the Municipal drain out side complex. |
| 13 | Solid Waste Management And Disposal System Solid waste collection chamber proposed on sites as per approved drawings by H.P.D.A. Waste will be disposed through a local Nagar Palika. |
| 14 | Water Conservation System Rain Water Harvesting facilities shall be provided. |
| 15 | Energy Management System Including Use of Renewable Energy Not applicable |
| 16 | Fire Protection And Fire Safety System Fire fighting system along with pumps & water storage tanks shall be provided as per NBC & NOC from Fire Department. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Shopping complex already exist within group Housing Project. |
| 18 | Emergency Evacuation Services Not applicable |
| 19 | Other Miscellaneous Work No |
Registered agents
1 agent
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | SUPRIYA MITTAL | UPRERAAGT12709 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 19 Aug 2020. 2 of them carry a revalidation, the latest valid to 31 May 2019.
Sanctioned by Hapur Pilkhuwa Development Authority · 2,980 sqm of land · an approved plan of 4 blocks and 102 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 153/MAP/HPDA/15-16 | 20 Aug 2015 | 19 Aug 2020 | 19 Aug 2023 | 31 May 2019 | — | |
| 153/MAP/HPDA/15-16 | 20 Aug 2015 | 19 Aug 2020 | 19 Aug 2023 | 31 May 2019 | 20 Aug 2015 valid to 31 May 2019 | |
| 153/MAP/HPDA/15-16 | 20 Aug 2015 | 19 Aug 2020 | 19 Aug 2023 | 31 May 2019 | 20 Aug 2015 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
28 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 225 | 1608 | — |
| 235 | 130 | — |
| 756 | 245 | — |
| 792/4 | 997 | — |
| 235M | 130 | Khasra |
| 225M | 1012 | Khasra |
| 792/4 | 997 | Khasra |
| 756 | 245 | Khasra |
| 225/1 | 596 | Khasra |
5 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 30 Aug 2006.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 16145 | 1 Dec 2007 | self | — |
| 13252 | 30 Aug 2006 | self | — |
| 11353 | 2 Aug 2011 | self | — |
| 17172 | 30 Nov 2011 | self | — |
| 13922/23 | 12 Sept 2006 | self | — |
| Sale deed · 11353 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 13252 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 17172 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8139 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 13922 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 16145 The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 4 Jul 2018 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 4 Jul 2018 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 4 Jul 2018 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 4 Jul 2018 ↗ |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | New | 19 Mar 2019 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 4 Jul 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 4 Jul 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 4 Jul 2018 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 4 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 4 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 4 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 4 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 4 Jul 2018 ↗ |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | Old | 11 Oct 2017 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 11 Oct 2017 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | Old | 11 Oct 2017 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | Old | 12 Oct 2017 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | Old | 12 Oct 2017 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | Old | 12 Oct 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | AS PER NORMS |
| Fire safety (as filed with RERA) | AS PER NORMS |
| Renewable energy | AS PER NORMS |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
7 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
7 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Platina Real States Pvt Ltd |
| Role | Promoter · current |
| RERA ID | UPRERAPRM5887 |
| PAN | AADCP9947K |
| CIN / TAN | U70102UP2006PTC040427 |
| Name of chairman | Vipin Kumar Mittal |
| Registered address | Dinesh Nagar Pilkhuwa,Hapur |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Ghaziabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | CURRENT ACCOUNTBankPUNJAB NATIONAL BANKBranchGT ROAD GHAZIABADA/C no.IFSCPUNB0018000 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about DINESH NAGAR
Is DINESH NAGAR RERA registered?
Yes. DINESH NAGAR is registered with UPRERA under registration number UPRERAPRJ4908, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has DINESH NAGAR been completed?
UPRERA still lists DINESH NAGAR as Registered, so it is not shown as completed here. A completion certificate dated 17 Apr 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of DINESH NAGAR?
Platina Real States Pvt Ltd is the promoter entity that filed DINESH NAGAR with UPRERA (promoter RERA ID UPRERAPRM5887). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does DINESH NAGAR have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is DINESH NAGAR located?
DINESH NAGAR is registered in Ghaziabad, as filed with UPRERA.
What configurations are available in DINESH NAGAR?
The unit plan filed with UPRERA lists 1 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in DINESH NAGAR?
The approved unit plan filed with UPRERA runs from 8 to 49 m² of carpet area (about 83 to 527 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in DINESH NAGAR?
The approved unit plan describes 4 blocks and 102 units of which 92 are homes and 10 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is DINESH NAGAR?
About 139 units per acre: 102 planned units across 0.74 acres (2,980 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗