DWAARIKA HEIGHTS

UPRERARegistered

DWAARIKA HEIGHTS is a RERA-registered residential project by EMM VEE INFRASTRUCTURES (INDIA) PRIVATE LIMITED in Meerut (RERA ID UPRERAPRJ5937). Registered with a completion deadline of 31 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
67.84%Q3'25
70%Q4'25
73%Q1'26
76%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ5937
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMeerut Development Authority
Proposed start1 Feb 2013
Original start1 Jan 2013
Project duration167 months
AddressMeerut, Meerut
TehsilMeerut
Applicant typeCompany
Applicant addressOPP. APPEX COLLEGE VED VYAS PURI, MEERUT- DEHRADUN BY PASS ROAD MEERUT UP 250103
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. Building permit sanctioned

    568/13

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. to

    Extension granted

  7. Permit revalidated

    GroupHousing/06909/MDA/BP/23-24/0096/01102024

  8. Building permit sanctioned

    GroupHousing/06909/MDA/BP/23-24/0096/01102024

  9. to

    Extension granted

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered4 Aug 2017
Original completion31 Mar 2020
Revised completion31 Dec 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹79,500
Sanctioning authorityMeerut Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors446 · 6 · 16 (units from plan)
Homes · commercial units436 · 10 (shops and offices filed in the same plan)
  • 2 BHK168 38%
  • 3 BHK104 23%
  • 4 BHK76 17%
  • 5 BHK48 11%
  • OTHER21 5%
  • Other29 6%
ConfigurationUnitsCarpet area
5 BHK48154
4 BHK76114-136
3 BHK104107-114
2 BHK16880-88
OTHER2113-25
1 BHK1936
SHOP1015
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
CLUB · OTHER, 1 BHK, SHOP65013-36
GOPALA/1 · 5 BHK, 4 BHK, 3 BHK1272114-154
GOVINDA/4 · 2 BHK148480-88
KANHA/2 · 2 BHK148480-88
KRISHNA/5 · 5 BHK, 4 BHK, 3 BHK1272114-154
SHAYAMA/3 · 4 BHK, 3 BHK1484107-114
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 137.53 m² for a OTHER, far outside the rest of that type, so the ranges above leave it out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
DISIGN NET C/O ABHAY SRIVASTAVA
License CA-88/11528
H-23 SECTOR - 39 NOIDA - 201301
Engineer
PERCEPTIONS C/O SANJAY JAYASWAL
11/165 SECTOR 11, VASUNDHARA GHAZIABAD - 201012
Contractor
RADHA BUILDTECH (INDIA) PRIVATE LIMITED
4/2885 GALI NO. 1 BIHARI COLONY DELHI - 110032
Sr.Development work declared to RERA
1Demarcation of Plots
ALREADY SHOWN ON APPROVED PLAN BY M.D.A.
2Boundary Wall
DONE AS PER PLAN PARTTY
3Road Work
YET TO BE COMPLETED
4Footpaths
YET TO BE COMPLETED
5Water Supply Including Drinking Water Facilities
TUBE WELL EXISTS
6Sewer System
YET TO BE COMPLETED
7Drain
SHALL BE DEVELOPED
8Parks
YET TO BE DEVELOPED
9Tree Planting
PARTTY DONE & GOING ON
10Design For Electric Supply Including Street Lighting
AS PER APPROVED PLAN
11Community Buildings
AS PER APPROVED PLAN
12Treatment and Disposal System of Sewage and Sullage water
THRU TRUNK SEVER CONNECTION
13Solid Waste Management And Disposal System
TO BE DONE AT FINISHING TIME
14Water Conservation System
BY WATER HARVESTING
15Energy Management System Including Use of Renewable Energy
ROOF SHALL BE UTILISED FOR RENEWABLE ENERGY
16Fire Protection And Fire Safety System
AS PER APPROVED PLAN
17Social Infrastructure And Other Public Amenities Including Public Health Services
AS PER APPROVED PLAN
18Emergency Evacuation Services
DUAL LIFTS & DOUBLE STAIR CASES WITH THREE GATES OFFERED
19Other Miscellaneous Work
SHALL BE DONE AS PER APPROVED PLAN
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 26 Oct 2029. 1 of them carries a revalidation.

Sanctioned by Meerut Development Authority · 14,865 sqm of land · an approved plan of 6 blocks and 446 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
568/1323 Jul 201322 Jul 201822 Jul 202131 Mar 2020—
GroupHousing/06909/MDA/BP/23-24/0096/0110202426 Oct 202426 Oct 202923 Jan 203130 Sept 202026 Oct 2024
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 31 Dec 2026.

#Granted fromExtended uptoNote
131 Mar 202030 Sept 2020Six months extension in view of force majeure caused by covid-19 pandemic
230 Sept 202013 Dec 2025—
313 Dec 202531 Dec 2026—

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
997250—
100010784—
10002061—
1004/11770—
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

3 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 9 Dec 2009.

Registry no.DateTypeArea
113609 Dec 2009self—
1653324 Dec 2011self—
1653424 Dec 2011self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 11360
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 11360
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 16534
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New27 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New27 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New27 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New27 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New31 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Jul 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterIN HOUSE GROUND WATER PUMPING SET FACILITY
Fire safety (as filed with RERA)SHALL BE PROVIDED AS PER APPROVED PLAN
Other facilitiesCLUB, SWIMMING POOL AND DAILY GROCERY SHOPS

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q267.84%CA ↗ · Arch ↗ · Eng ↗
2025-Q370%CA ↗ · Arch ↗ · Eng ↗
2025-Q473%CA ↗ · Arch ↗ · Eng ↗
2026-Q176%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameEMM VEE INFRASTRUCTURES (INDIA) PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM12097
PANAABCE0893K
CIN / TANU45309UP1999PTC024680
Name of chairmanVIJAY PAL YADAV
Registered addressOPP. APPEX COLLEGE VED VYAS PURI, MEERUT- DEHRADUN BY PASS ROAD MEERUT UP 250103
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Meerut

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
EMM VEE INFRASTRUCTURES (INDIA) PRIVATE LIMITEDBankCORPORATION BANKBranchPRABHAT NAGAR SAKET MEERUTA/C no.IFSCCORP0002104
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about DWAARIKA HEIGHTS

Is DWAARIKA HEIGHTS RERA registered?

Yes. DWAARIKA HEIGHTS is registered with UPRERA under registration number UPRERAPRJ5937, registered on 4 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for DWAARIKA HEIGHTS?

The completion date filed with UPRERA is 31 Dec 2026. No completion certificate is on record yet.

Who is the builder of DWAARIKA HEIGHTS?

EMM VEE INFRASTRUCTURES (INDIA) PRIVATE LIMITED is the promoter entity that filed DWAARIKA HEIGHTS with UPRERA (promoter RERA ID UPRERAPRM12097). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted DWAARIKA HEIGHTS more time to complete?

UPRERA's record carries 3 completion extensions for DWAARIKA HEIGHTS, the latest running to 31 Dec 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does DWAARIKA HEIGHTS have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is DWAARIKA HEIGHTS located?

DWAARIKA HEIGHTS is registered in Meerut, as filed with UPRERA.

What configurations are available in DWAARIKA HEIGHTS?

The unit plan filed with UPRERA lists 5 BHK, 4 BHK, 3 BHK, 2 BHK, OTHER, 1 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in DWAARIKA HEIGHTS?

The approved unit plan filed with UPRERA runs from 13 to 154 m² of carpet area (about 136 to 1,659 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in DWAARIKA HEIGHTS?

The approved unit plan describes 6 blocks and 446 units of which 436 are homes and 10 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is DWAARIKA HEIGHTS?

About 121 units per acre: 446 planned units across 3.67 acres (14,865 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗