Dynasty By ORO is a RERA-registered real-estate project in Sarsawan, Lucknow (RERA ID UPRERAPRJ469558). Registered with a completion deadline of 14 Jun 2031. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ469558 |
| Applicant type | Partnership Firm |
| Project category | Residential |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Apr 2025 |
| Project duration | 75 |
| Address | Khasra No 784P, 790P, 791P, 792Kha P, Sarsawan, Sarojini Nagar, Lucknow |
| RERA registered | 13 Dec 2024 |
| Promised completion | 14 Jun 2031 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹28,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| 3 BHK | 104 | 92–92 |
| 2 BHK | 52 | 71–75 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| Ground Housing/13184/LDA/BP/21-22/2499/06092024 | 18 Oct 2024 | 17 Oct 2029 | 14 Jun 2031 |
| Khasra | Area | Type |
|---|---|---|
| 784P | 822 | Khasra |
| 790P | 336.50 | Khasra |
| 791P | 3318 | Khasra |
| 792 KHA P | 101.50 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2025-Q1 | — | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 2.55% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 3.9% | CA · Arch · Eng | view ↗ |
| 2025-Q4 | 7.55% | CA · Arch · Eng | view ↗ |
| 2026-Q1 | 6.01% | CA · Arch · Eng | view ↗ |
Yes. Dynasty By ORO is registered with UPRERA under registration number UPRERAPRJ469558, registered on 13 Dec 2024. Estanzo reproduces that filing; it does not verify the work behind it.
The completion date filed with UPRERA is 14 Jun 2031. No completion certificate is on record yet, and that deadline has not passed.
Dynasty By ORO is registered in Sarsawan, Lucknow, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗