Estanzo

Timeline Bar

Registered9 Feb 2018
Promised31 Mar 2020
Completed13 Jul 2022

Timeline

Promised completion31 Mar 2020
Revised completion31 Mar 2020
Actual completion13 Jul 2022
Possession delay27 mo delay

Registration & Cost Details

Registration fee (in ₹)₹30,000
Project cost (in ₹ Lakhs)₹2,800 Lakhs
Project duration41 months
Project categoryCommercial
Locality
Original start date
Proposed start date10 Feb 2018

Inventory

Total units164
Unit TypeUnitsCarpet Area (sqm)
SHOP16459.91–491.99

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9717805421
Emailk2ninfra.rera@gmail.com
Coordinator9582152074
AddressB-113, Sector-64, Noida, UP-201301

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP-3202/CPA-5202

Revalidated: PLG/BP-4123/5054 (27 Jul 2018)

8 Aug 20138 Aug 2018

Revalidated upto: 27 Jul 2023

31 Mar 202027 Jul 2028
BP-3202/CPA-5202

Revalidated: PLG/BP-4123/5054 (27 Jul 2018)

8 Aug 20138 Aug 2018

Revalidated upto: 27 Jul 2023

31 Mar 202027 Jul 2028

Land Parcels

Khasra No.AreaPlot Type
CS-03,2000Plot

Approved Unit Plan

Unit plan rows on file7
Total flats (sum of rows)164
Total shops164
BlocksEmbark Plaza
Floor typesSHOP

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of EMBARK PLAZA?

The RERA registration number of EMBARK PLAZA is UPRERAPRJ15152, as recorded on the UP-RERA portal.

What is the RERA status of EMBARK PLAZA?

As reported by UP-RERA, the status of EMBARK PLAZA is "Registered".

Where is EMBARK PLAZA located?

As reported to UP-RERA, EMBARK PLAZA is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is EMBARK PLAZA completed?

As reported to UP-RERA, EMBARK PLAZA was completed on 13 Jul 2022.

Is EMBARK PLAZA delayed?

Measured against the latest completion date reported to UP-RERA, EMBARK PLAZA is 27 months beyond that date.