Timeline Bar

Registered1 Apr 2022
Promised19 Feb 2025
Today4 Aug 2026

Timeline

Promised completion19 Feb 2025
Revised completion19 Feb 2025
Actual completion
Possession delay17 mo delay

Registration & Cost Details

Registration fee (in ₹)₹20,500
Project cost (in ₹ Lakhs)₹2,081 Lakhs
Project duration53 months
Project categoryResidential
Locality
Original start date1 Oct 2021
Proposed start date1 Oct 2021

Inventory

Total units78
Unit TypeUnitsCarpet Area (sqm)
2 BHK7850.6–53.03

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7571811111
Emailinfo@excellainfra.in
Coordinator7570000823
AddressB-2/345, Vikas Khand, Gomti Nagar, Lucknow-226010

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q290.0%
2025-Q393.3%
2025-Q496.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
4090012 Jan 202219 Feb 202419 Feb 202519 Feb 2025
40900

Revalidated: 40900 (12 Jan 2022)

12 Jan 202219 Feb 2024

Revalidated upto: 9 Aug 2028

19 Feb 20259 Aug 2028

Land Parcels

Khasra No.AreaPlot Type
2678/11200Khasra
26771840Khasra

Approved Unit Plan

Unit plan rows on file78
Total flats (sum of rows)78
BlocksB-1
Floor types2 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Excella Kutumb Phase-IV?

The RERA registration number of Excella Kutumb Phase-IV is UPRERAPRJ541833, as recorded on the UP-RERA portal.

What is the RERA status of Excella Kutumb Phase-IV?

As reported by UP-RERA, the status of Excella Kutumb Phase-IV is "Registered".

Where is Excella Kutumb Phase-IV located?

As reported to UP-RERA, Excella Kutumb Phase-IV is located at Mohanlalganj, Lucknow, Uttar Pradesh.

When will Excella Kutumb Phase-IV be completed?

The latest completion date reported to UP-RERA for Excella Kutumb Phase-IV is 19 Feb 2025.

Is Excella Kutumb Phase-IV delayed?

Measured against the latest completion date reported to UP-RERA, Excella Kutumb Phase-IV is 17 months beyond that date.