SAHU CITY is a RERA-registered residential project by SAHU LAND DEVELOPERS PVT LTD in Lucknow (RERA ID UPRERAPRJ4655). Registered with a completion deadline of 22 Apr 2024.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ4655 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 23 Oct 2017 |
| Project duration | 78 months |
| Address | Mohanlalganj, Lucknow |
| Tehsil | Mohanlalganj |
| Applicant type | Company |
| Applicant address | 33/1 N.S Road Marshall House Room No. 933E Kolkata 700001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
41219
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
2 completion certificates filed
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 14 Aug 2017 |
| Original completion | 23 Oct 2023 |
| Revised completion | 22 Apr 2024 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 10 Apr 2024 |
| Registration fee | ₹3,43,000 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 1 BHK284 51%
- 2 BHK276 49%
| Configuration | Units | Carpet area |
|---|---|---|
| 1 BHK | 284 | 37-60 |
| 2 BHK | 276 | 60 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| TOWER-1 · 1 BHK, 2 BHK | 14 | 112 | 37-60 |
| TOWER-2 · 1 BHK, 2 BHK | 14 | 112 | 37-60 |
| TOWER-3 · OTHER, 1 BHK, 2 BHK | 15 | 112 | 37-60 |
| TOWER-4 · 1 BHK, 2 BHK | 14 | 112 | 37-60 |
| TOWER-5 · 1 BHK, 2 BHK | 14 | 112 | 37-60 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots This is single plot of roughly rectangular shape, having total 1 no. of entry gate and 1 no. of exit gate from the 18.288 mtr (60 Feet) wide front road Site is surrounded by other plots on two side |
| 2 | Boundary Wall 1.8 - 2.1 m high and 230 mm thick Boundary wall designed . Brick Work of 9 inches and rcc work in column and beam may be used as per design. MS Broad entrance and exit gates are developed with boundary |
| 3 | Road Work High quality Bitumen road over 200 mm thick WBM will be used as per design suggested by the Architects for internal road |
| 4 | Footpaths All internal roads will have 1.50 m wide footpath in 60-80 mm thick concrete pavers or equivalent finishes |
| 5 | Water Supply Including Drinking Water Facilities UP JAl Board will provide the water supply to the Plot and Individual . Ground water may also be used. Also end user shall be used their individual RO system as per their requirement. Overhead tanks shall be provided on building terrace for distribution through gravity |
| 6 | Sewer System Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment after treatment ,water shall be recycle and it will use in gardening and overflow from the STP shall be connect with the Municipal sewerage system. |
| 7 | Drain Storm water system shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line. |
| 8 | Parks There is one main park on the entrance with play area for children and different recreational activities. Facility of Open Gym will be provided as per Architect designs. |
| 9 | Tree Planting There are 5 type of trees provided in site which are kachnar, gulmauhar, amaltas, kusum and neem. |
| 10 | Design For Electric Supply Including Street Lighting We have design the system as per local electricity Board and consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, STP, Pump room etc. |
| 11 | Community Buildings NA |
| 12 | Treatment and Disposal System of Sewage and Sullage water Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment after treatment ,water shall be recycle and it will use in gardening and flushing system and overflow from the STP shall be connect with the Municipal sewerage system. |
| 13 | Solid Waste Management And Disposal System There are a proper garbage collection area provided for the solid waste management. |
| 14 | Water Conservation System A well designed rain water harvesting system shall be provided for the whole building complex to conserve water |
| 15 | Energy Management System Including Use of Renewable Energy We will use LED lights fitting in external area as well as solar lights. In STP and Pump room all the equipment shall have energy efficient motor. |
| 16 | Fire Protection And Fire Safety System Since the building is less than 45m in height all the fire norms shall be followed as NBC and approval of fire department |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Sewerage ,Storm water and water supply system shall be Provided. We have Proposed common Pump Room with Primary filtration, Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic as well as flushing tanks. All Sewage shall be go to the STP for recycling the water. Storm water for Roof, Roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain. |
| 18 | Emergency Evacuation Services NA |
| 19 | Other Miscellaneous Work - |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 25 Aug 2021.
Sanctioned by Lucknow Development Authority · 6,969 sqm of land · an approved plan of 5 blocks and 560 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 41219 | 30 Mar 2017 | 25 Aug 2021 | 25 Aug 2024 | 23 Oct 2023 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Project approval The approval the promoter filed as the basis for registering the project. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned building plan The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
UPRERA’s record carries 1 completion extension for this project, running to 22 Apr 2024.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 23 Oct 2023 | 22 Apr 2024 | Six months extension in view of force majeure caused by covid-19 pandemic |
Land & documents
20 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 862, 863, 864, 865, 866 | 13560 Sq.Mt. | — |
| 58,59,60,61,62,63,64,65,67,68KHA, 70,71,72,73,74,7 | 26695 Sq.Mt. | — |
| 1, 3, 3 KA | 27334 | — |
| 58, 59, 60, 61, 62, 63, 64, 65, 67, 68 KHA, 70, 71, 73, 74, 78, 79, 182, 213, 214, 218, 219, 220, 221, 222, 223, 224,226KA, 226KHA, 228, 229, 230, 231, 231 MIJULA, 225, 84, 1&3, 3KA, 862, 863, 865, 864, 866 | 70023.30 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 26 Aug 2015.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 626 | 26 Aug 2015 | other | — |
| Registry document · 626 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | not reported | — |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 22 Dec 2019 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 10 Sept 2019 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 10 Sept 2019 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 10 Sept 2019 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 10 Sept 2019 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 10 Sept 2019 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 12 Jun 2020 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 12 Jun 2020 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 12 Jun 2020 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jul 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jul 2017 ↗ |
| Agreement for other land The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title. | Old | 29 Jul 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | YES |
| Fire safety (as filed with RERA) | YES |
| Health service | YES |
| Renewable energy | YES |
| Other facilities | THERE IS INTER COLLEGE, GUEST HOUSE, SHOPPING CENTER, TEMPLE, STP PLANT, ESS, ETC |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
17 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
17 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2024-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | SAHU LAND DEVELOPERS PVT LTD |
| Role | Promoter · current |
| RERA ID | UPRERAPRM6199 |
| PAN | AAMCS1205N |
| CIN / TAN | U70101WB2007PTC118275 |
| Name of chairman | Neeraj Kumar Sahu |
| Registered address | 33/1 N.S Road Marshall House Room No. 933E Kolkata 700001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | SAHU LAND DEVELOPERS PVT. LTD.-SAHU CITY-RERA RETENTION ACCOUNTBankICICI BANKBranchICICI BANK HAZRATGANJ LUCKNOW BRANCH, SHALIMAR TOWER, 31/54, M. G. MARG, HAZRATGANJ LUCKNOW-226001A/C no.IFSCICIC0006281 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about SAHU CITY
Is SAHU CITY RERA registered?
Yes. SAHU CITY is registered with UPRERA under registration number UPRERAPRJ4655, registered on 14 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has SAHU CITY been completed?
UPRERA still lists SAHU CITY as Registered, so it is not shown as completed here. A completion certificate dated 10 Apr 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of SAHU CITY?
SAHU LAND DEVELOPERS PVT LTD is the promoter entity that filed SAHU CITY with UPRERA (promoter RERA ID UPRERAPRM6199). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted SAHU CITY more time to complete?
UPRERA's record carries 1 completion extension for SAHU CITY, the latest running to 22 Apr 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does SAHU CITY have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is SAHU CITY located?
SAHU CITY is registered in Lucknow, as filed with UPRERA.
What configurations are available in SAHU CITY?
The unit plan filed with UPRERA lists OTHER, 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in SAHU CITY?
The approved unit plan filed with UPRERA runs from 37 to 60 m² of carpet area (about 400 to 648 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in SAHU CITY?
The approved unit plan describes 5 blocks and 560 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is SAHU CITY?
About 325 units per acre: 560 planned units across 1.72 acres (6,969 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗