Registered6 Jul 2022
Promised12 Mar 2026
Today4 Aug 2026

Timeline

Promised completion12 Mar 2026
Revised completion12 Mar 2026
Actual completion
Possession delay5 mo delay

Registration & Cost Details

Registration fee (in ₹)₹65,500
Project cost (in ₹ Lakhs)₹24,736 Lakhs
Project duration48 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2022

Inventory

Total units507
Unit TypeUnitsCarpet Area (sqm)
2 BHK30964.213–73.746
3 BHK14587.893–107.361
4 BHK2128.42
5 BHK2175.96
SHOP272.02–25.56
OTHER223.16–10.91

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9312632920
Emailastra@expressbuildersltd.com
Coordinator9312832920
AddressRegistered Office Address- 810, Surya Kiran Building 19, Kasturba Gandhi Marg, Connaught Place, New Delhi-110001 Corporate Office Address- H-139, Sector-63, Noida, U.P. Site Address- Plot No. GH-06A, Sector-1, Greater Noida, U.P.

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q257.0%
2025-Q377.0%
2025-Q466.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG(BP)3280/168913 Mar 202012 Mar 202512 Mar 202630 Mar 2030

Land Parcels

Khasra No.AreaPlot Type
GH-06A, SECTOR 01, GREATER NOIDA23912.50Plot

Approved Unit Plan

Unit plan rows on file290
Total flats (sum of rows)507
Total shops27
BlocksA, B, Commercial NON TOWER, Commercial TOWER A, Commercial TOWER B, H, I, J
Floor types2 BHK, 3 BHK, 4 BHK, 5 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Express Astra (Phase-II)?

The RERA registration number of Express Astra (Phase-II) is UPRERAPRJ229234, as recorded on the UP-RERA portal.

What is the RERA status of Express Astra (Phase-II)?

As reported by UP-RERA, the status of Express Astra (Phase-II) is "Registered".

Where is Express Astra (Phase-II) located?

As reported to UP-RERA, Express Astra (Phase-II) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Express Astra (Phase-II) be completed?

The latest completion date reported to UP-RERA for Express Astra (Phase-II) is 12 Mar 2026.

Is Express Astra (Phase-II) delayed?

Measured against the latest completion date reported to UP-RERA, Express Astra (Phase-II) is 5 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026