Express Astra (Phase-1)

UPRERARegistered

Express Astra (Phase-1) is a RERA-registered residential project by Express Projects Pvt. Ltd. in Gautam Budh Nagar (RERA ID UPRERAPRJ479698). Registered with a completion deadline of 12 Mar 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
74%Q3'25
77%Q4'25
83%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ479698
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Sept 2020
Project duration79 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegistered Office Address- 810, Surya Kiran Building 19, Kasturba Gandhi Marg, Connaught Place, New Delhi-110001 Corporate Office Address- H-139, Sector-63, Noida, U.P. Site Address- Plot No. GH-06A, Sector-1, Greater Noida, U.P.
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered7 Dec 2020
Original completion
Revised completion12 Mar 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹64,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors524 · 6 · 27 (units from plan)
Homes · commercial units497 · 27 (shops and offices filed in the same plan)
  • 2 BHK317 60%
  • 3 BHK153 29%
  • OTHER27 5%
  • SHOP27 5%
ConfigurationUnitsCarpet area
OTHER272-15
SHOP2712-24
3 BHK15388-107
2 BHK31764-74
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Commercial · SHOP, OTHER1226-24
Tower- C · OTHER, SHOP, 3 BHK25652-107
Tower- D · SHOP, OTHER, 2 BHK, 3 BHK271196-88
Tower- E · 2 BHK2710664-74
Tower- F · 2 BHK2710664-74
Tower- G · 2 BHK, 3 BHK2710664-88
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Shashank Sharma- Fourth Dimension
License CA/97/22034
C-17, Basement, Anand Niketan, New Delhi
Engineer
Mr. V.D. Sharma- Optimum Design
B-24, Sector-67, NOIDA, U.P.
Contractor
Express Projects Pvt. Ltd.
810, Surya Kiran Building, 19, Kasturba Gandhi Marg, Connaught Place, New Delhi-110001
Sr.Development work declared to RERA
1Demarcation of Plots
Total Plot Area- 11900 sqm., N- 24m wide road, S- Plot no. 6B, E- Plot no.- 6C, W- 24.0 mtr. wide road.
2Boundary Wall
Yes, Masonary and Railing boundary Wall.
3Road Work
Yes, RCC Trimix/ Interlocking block road with inetrmittent Tile/ Stone paving.
4Footpaths
No.
5Water Supply Including Drinking Water Facilities
Yes, GNIDA water supply system in under ground water reservoirs. Terrace tanks filled with Pumps.
6Sewer System
Yes, RCC hume pipe with manhole , chambers and Collection chambers and Connections.
7Drain
Yes, RCC hume pipe with manhole , chambers and collection chamber with Rain water harvesting.
8Parks
Yes, landscape with Civil Work with Masonary and stone, Horiculture work and various types of Plantation, shrubs.
9Tree Planting
Yes, Tree Planting along some parts of the road inn the Project.
10Design For Electric Supply Including Street Lighting
Yes, As per Approved Layout.
11Community Buildings
Yes, with Community hall, Gym and Indoor games facilities.
12Treatment and Disposal System of Sewage and Sullage water
S.T.P. and through GNIDA Sewerage System.
13Solid Waste Management And Disposal System
Yes, Organic waste convertor and collection bins.
14Water Conservation System
Yes, Rain water harvesting pits.
15Energy Management System Including Use of Renewable Energy
Some solar energy lights in Common areas and External Areas.
16Fire Protection And Fire Safety System
Diesel Pump- 1 no., Electrical Pump for hydrant - 1 no.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Proper water supply and Sanitary facilities at one point in the Project.
18Emergency Evacuation Services
Yes, Refuse area provided at every towers on 18th Floor in addition to Fire Staircase.
19Other Miscellaneous Work
Yes, Guard Room, Entrance and Exit Gates, Commercial Facilities.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 13 Mar 2025. 2 of them carry a revalidation, the latest valid to 13 Mar 2030.

Sanctioned by Greater Noida Authority · 11,900 sqm of land · an approved plan of 6 blocks and 524 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/(BP)-3280/168913 Mar 202012 Mar 202512 Mar 203012 Mar 2026—
PLG(BP)-3280/168913 Mar 202013 Mar 202512 Mar 203012 Mar 202613 Mar 2020
valid to 12 Mar 2030
PLG(BP)-3280/168913 Mar 202013 Mar 202513 Mar 203512 Mar 202613 Mar 2020
valid to 13 Mar 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 12 Mar 2027.

#Granted fromExtended uptoNote
112 Mar 2027—

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
GH- 06A21718.56Plot
GH-06A2193.94Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 9405
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Lease deed · 17196
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Reply of Objection Letter
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Reply Letter to UP RERA
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New8 Oct 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New18 Sept 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New18 Sept 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New18 Sept 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Sept 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Sept 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Sept 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Sept 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New23 Sept 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New18 Sept 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New18 Sept 2020 ↗

Quarterly progress reports

24 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

24 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q274%CA ↗ · Arch ↗ · Eng ↗
2025-Q377%CA ↗ · Arch ↗ · Eng ↗
2025-Q483%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameExpress Projects Pvt. Ltd.
RolePromoter · current
RERA IDUPRERAPRM102583
PANAAACE8183F
CIN / TANU45102DL2000PTC104550
Name of chairmanMr. Vinay Goel
Registered addressRegistered Office Address- 810, Surya Kiran Building 19, Kasturba Gandhi Marg, Connaught Place, New Delhi-110001 Corporate Office Address- H-139, Sector-63, Noida, U.P. Site Address- Plot No. GH-06A, Sector-1, Greater Noida, U.P.
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
EPPL Collection A/c - Express Astra Ph1BankHDFC Bank Ltd.BranchSector - 62, NOIDABranch addressC-25, Stellar IT Park, Sector 62, NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649Branch emailsupport(at)hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
EPPL Separate A/c - Express Astra Ph1BankHDFC Bank Ltd.BranchSector 62, NoidaBranch addressC-25, Stellar IT Park, Sector 62, NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0002649Branch emailsupport(at)hdfcbank.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
EPPL Transaction A/c- Express Astra Ph1BankHDFC Bank Ltd.BranchRK Puram, Sector 4, New DelhiBranch addressPlot No. 8, RK Puram, Sector 4, New DelhiBranch districtSouth West Delhi, DelhiA/C no.IFSCHDFC0000588Branch emailsupport(at)hdfcbank.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

8 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Revised completion date on file2026-03-12 → 2027-03-12
changed in Estanzo’s record
9 Oct 2026
Completion date promised at registration2026-03-12
no longer on the record
9 Oct 2026
Permit paperwork
3 · Project Specifications
Project Specifications
newly filed with RERA
29 Sept 2026
Permit paperwork
3 · Floor Plan Of All Types
Floor Plan Of All Types
newly filed with RERA
29 Sept 2026
Permit paperwork
3 · Approved Map
Approved Map
newly filed with RERA
29 Sept 2026
Permit paperwork
3 · Sanctioned Letter
Sanctioned Letter
newly filed with RERA
29 Sept 2026
Permit paperwork
3 · Approved Layout
Approved Layout
newly filed with RERA
29 Sept 2026
Sanctioning permit
no. 3
PLG(BP)-3280/1689
newly filed with RERA
29 Sept 2026
When these facts last moved
Revised completion date on filechanged in Estanzo’s record · 9 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Express Astra (Phase-1)

Is Express Astra (Phase-1) RERA registered?

Yes. Express Astra (Phase-1) is registered with UPRERA under registration number UPRERAPRJ479698, registered on 7 Dec 2020. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Express Astra (Phase-1)?

The completion date filed with UPRERA is 12 Mar 2027. No completion certificate is on record yet.

Who is the builder of Express Astra (Phase-1)?

Express Projects Pvt. Ltd. is the promoter entity that filed Express Astra (Phase-1) with UPRERA (promoter RERA ID UPRERAPRM102583). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Express Astra (Phase-1) more time to complete?

UPRERA's record carries 1 completion extension for Express Astra (Phase-1), the latest running to 12 Mar 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Express Astra (Phase-1) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Express Astra (Phase-1) located?

Express Astra (Phase-1) is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Express Astra (Phase-1)?

The unit plan filed with UPRERA lists OTHER, SHOP, 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Express Astra (Phase-1)?

The approved unit plan filed with UPRERA runs from 2 to 107 m² of carpet area (about 24 to 1,156 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Express Astra (Phase-1)?

The approved unit plan describes 6 blocks and 524 units of which 497 are homes and 27 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Express Astra (Phase-1)?

About 178 units per acre: 524 planned units across 2.94 acres (11,900 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗