Estanzo

Timeline Bar

Registered31 Jul 2017
Promised31 Dec 2019
Completed20 Oct 2021

Timeline

Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion20 Oct 2021
Possession delay22 mo delay

Registration & Cost Details

Registration fee (in ₹)₹77,000
Project cost (in ₹ Lakhs)₹18,000 Lakhs
Project duration88 months
Project categoryResidential
Locality
Original start date1 Mar 2014
Proposed start date1 Mar 2014

Inventory

Total units393
Unit TypeUnitsCarpet Area (sqm)
2 BHK12172.04–90.42
3 BHK23578.51–105.34
4 BHK33114.5–121.3
OTHER41–121.3

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810498811
Emailmailexpressproperties@gmail.com
Coordinator9999553000
AddressHS 38 Kailash Colony, New Delhi-110048

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
35/196/THA/GH/07(Revised)

Revalidated: 35/196/THA/GH/07(Revised) (13 Apr 2013)

13 Apr 201313 Apr 2018

Revalidated upto: 13 Apr 2021

31 Dec 201913 Apr 2021

Land Parcels

Khasra No.AreaPlot Type
GH 1/123485Plot

Approved Unit Plan

Unit plan rows on file393
Total flats (sum of rows)393
BlocksD, E, F
Floor types2 BHK, 3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
175652 Jul 2010
178624 Jan 2007

Frequently Asked Questions

What is the RERA registration number of EXPRESS GREENS (Phase III)?

The RERA registration number of EXPRESS GREENS (Phase III) is UPRERAPRJ5573, as recorded on the UP-RERA portal.

What is the RERA status of EXPRESS GREENS (Phase III)?

As reported by UP-RERA, the status of EXPRESS GREENS (Phase III) is "Registered".

Where is EXPRESS GREENS (Phase III) located?

As reported to UP-RERA, EXPRESS GREENS (Phase III) is located at Ghaziabad, Ghaziabad, Uttar Pradesh.

Is EXPRESS GREENS (Phase III) completed?

As reported to UP-RERA, EXPRESS GREENS (Phase III) was completed on 20 Oct 2021.

Is EXPRESS GREENS (Phase III) delayed?

Measured against the latest completion date reported to UP-RERA, EXPRESS GREENS (Phase III) is 22 months beyond that date.