FairField Residency is a RERA-registered residential project by Shakuntalam Habitats Private Limited in Meerut (RERA ID UPRERAPRJ255302). Registered with a completion deadline of 8 Jun 2030.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ255302 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Meerut Development Authority |
| Proposed start | 10 Jul 2025 |
| Project duration | 59 months |
| Address | Plot No. 2/BL-02, Sector 02, Raksha Puram, Phase 1, Mawana Rad, Defence Colony, Meerut, Mawana, Meerut |
| Tehsil | Mawana |
| Applicant type | Company |
| Applicant address | H-27, W8, Western Avenue, Sainik Farm House, South Delhi, Delhi-110062 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
Plotted resi development/Plotted Housing/07607/MDA/LD/24-25/1341/03032025
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 7 Aug 2025 |
| Original completion | 8 Jun 2030 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹1,35,500 |
| Sanctioning authority | Meerut Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots All 44 plots will be precisely demarcated following vastu principles, aligned with planned road geometry to ensure coherent layout and optimal access |
| 2 | Boundary Wall Proposed secure periphery boundary wall with stone cladding, and artistic inlays is proposed for the entire unit to ensure safety and enhance visual aesthetics |
| 3 | Road Work Proposed internal road of 12 m and 9 m wide have been designed with cobble to promote, slow, safe vehicle movement |
| 4 | Footpaths One sided shaded pedestrian pathways integrated alongwtih internal roads oriented towards greenpark and community nodes. |
| 5 | Water Supply Including Drinking Water Facilities Provision of centralised water supply with necessary piping; drinking water points to be added at key park and community nodes |
| 6 | Sewer System Underground sever system designed in coordination with manhole and ramp locations, to ensure efficient drainage and low maintenance. |
| 7 | Drain Surface and stormwater drains integrated in road design using sustainable techniques. |
| 8 | Parks Five theme park developed across the layout including children park, elderly zone, sports corner, club lawn with unique landscaping amenities |
| 9 | Tree Planting Seasonal high canopy trees like Jacaranda, Gulmohar and amaltas planted along street for shade and visual identity, enhancing biodeiversity and microclimate |
| 10 | Design For Electric Supply Including Street Lighting Underground cabling proposed for electricity with smart street lighting along all road and park peripheries using energy efficient fixtures |
| 11 | Community Buildings Banquet lawn and pool deck with pavilioin designated as central gathering nodes to foster social gathering |
| 12 | Treatment and Disposal System of Sewage and Sullage water Project is facilitated with public seveage line by Meerut Development Authority and internal sever line will be conencted with it. |
| 13 | Solid Waste Management And Disposal System Planned waste seggregation at source with community collection areas and partnership proposed for waste to green initiatives. |
| 14 | Water Conservation System Including rain water harvesting through preamble pavements, recharge puts and water cachement zones, integrated into landscape design |
| 15 | Energy Management System Including Use of Renewable Energy Township design integrates smart lighting and provision for rooftop solar installation for residents. |
| 16 | Fire Protection And Fire Safety System Provision for fire hydrants along internal roads, with access planned for emergency services in accordance with building code and emergency services |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Incorporation of convenience retail space and health service to be added at later stage |
| 18 | Emergency Evacuation Services Wide Roadways with loop design will ensure clear emergency services and evacuation routes, open space and parks serve as assembly zones |
| 19 | Other Miscellaneous Work Include signages entry gate feature wall with township branding, art murals, community seating areas and instalaltion inspired by local ecology and culture |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 8 Jun 2030.
Sanctioned by Meerut Development Authority · 26,071 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| Plotted resi development/Plotted Housing/07607/MDA/LD/24-25/1341/03032025 | 9 Jun 2025 | 8 Jun 2030 | 8 Jun 2030 | 8 Jun 2030 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| BL-02 | 26071 | Plot |
| Registry document · IN-UP7930515394613X The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Allotment letter from the authority · BBB04240875187 The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 5 Jul 2025 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 5 Jul 2025 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 5 Jul 2025 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 5 Jul 2025 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 5 Jul 2025 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 5 Jul 2025 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 5 Jul 2025 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 5 Jul 2025 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 5 Jul 2025 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 5 Jul 2025 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 5 Jul 2025 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 5 Jul 2025 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 5 Jul 2025 ↗ |
| Agreement for sale (proforma) The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind. | New | 5 Jul 2025 ↗ |
Quarterly progress reports
3 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
3 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2025-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2025-Q2 | 37.5% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 26.74% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 95% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Shakuntalam Habitats Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM375150 |
| PAN | AATCS8361E |
| CIN / TAN | U70102DL2013PTC259187 |
| Name of chairman | Ashish Gupta |
| Registered address | H-27, W8, Western Avenue, Sainik Farm House, South Delhi, Delhi-110062 |
| RERA contact | |
| Registered since | 2025 |
Nearby projects
Meerut
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | Shakuntalam Habitats Pvt Ltd Collection A/c Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave, Garh Road, Meerut, Uttar PradeshBranch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975Branch emailkratika.chauhan@icicibank.com |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | Shakuntalam Habitats Pvt Ltd. Separate Bank A/C Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave, Garh Road, Meerut- Uttar Pradesh 250001Branch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | Shakuntalam Habitats Pvt Ltd Rera Transaction A/C Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave Garh Road, Meerut, Uttar Pradesh 250001Branch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about FairField Residency
Is FairField Residency RERA registered?
Yes. FairField Residency is registered with UPRERA under registration number UPRERAPRJ255302, registered on 7 Aug 2025. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for FairField Residency?
The completion date filed with UPRERA is 8 Jun 2030. No completion certificate is on record yet.
Who is the builder of FairField Residency?
Shakuntalam Habitats Private Limited is the promoter entity that filed FairField Residency with UPRERA (promoter RERA ID UPRERAPRM375150). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does FairField Residency have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is FairField Residency located?
FairField Residency is registered in Meerut, Meerut, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗