Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
37.5%Q3'25
26.74%Q4'25
95%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ255302
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMeerut Development Authority
Proposed start10 Jul 2025
Project duration59 months
AddressPlot No. 2/BL-02, Sector 02, Raksha Puram, Phase 1, Mawana Rad, Defence Colony, Meerut, Mawana, Meerut
TehsilMawana
Applicant typeCompany
Applicant addressH-27, W8, Western Avenue, Sainik Farm House, South Delhi, Delhi-110062
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Plotted resi development/Plotted Housing/07607/MDA/LD/24-25/1341/03032025

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered7 Aug 2025
Original completion8 Jun 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,35,500
Sanctioning authorityMeerut Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mohit Bhatnagar
License CA/1999/25208
T-38, First Floor, Ganpati Complex, Abu Lane, Meerut
Engineer
Deepanshu Arneja
B-274/1, Second Floor, Derawal Nagar, Gujrawala Town, New Delhi- 110009
Contractor
Not Applicable
Not Applicable
Sr.Development work declared to RERA
1Demarcation of Plots
All 44 plots will be precisely demarcated following vastu principles, aligned with planned road geometry to ensure coherent layout and optimal access
2Boundary Wall
Proposed secure periphery boundary wall with stone cladding, and artistic inlays is proposed for the entire unit to ensure safety and enhance visual aesthetics
3Road Work
Proposed internal road of 12 m and 9 m wide have been designed with cobble to promote, slow, safe vehicle movement
4Footpaths
One sided shaded pedestrian pathways integrated alongwtih internal roads oriented towards greenpark and community nodes.
5Water Supply Including Drinking Water Facilities
Provision of centralised water supply with necessary piping; drinking water points to be added at key park and community nodes
6Sewer System
Underground sever system designed in coordination with manhole and ramp locations, to ensure efficient drainage and low maintenance.
7Drain
Surface and stormwater drains integrated in road design using sustainable techniques.
8Parks
Five theme park developed across the layout including children park, elderly zone, sports corner, club lawn with unique landscaping amenities
9Tree Planting
Seasonal high canopy trees like Jacaranda, Gulmohar and amaltas planted along street for shade and visual identity, enhancing biodeiversity and microclimate
10Design For Electric Supply Including Street Lighting
Underground cabling proposed for electricity with smart street lighting along all road and park peripheries using energy efficient fixtures
11Community Buildings
Banquet lawn and pool deck with pavilioin designated as central gathering nodes to foster social gathering
12Treatment and Disposal System of Sewage and Sullage water
Project is facilitated with public seveage line by Meerut Development Authority and internal sever line will be conencted with it.
13Solid Waste Management And Disposal System
Planned waste seggregation at source with community collection areas and partnership proposed for waste to green initiatives.
14Water Conservation System
Including rain water harvesting through preamble pavements, recharge puts and water cachement zones, integrated into landscape design
15Energy Management System Including Use of Renewable Energy
Township design integrates smart lighting and provision for rooftop solar installation for residents.
16Fire Protection And Fire Safety System
Provision for fire hydrants along internal roads, with access planned for emergency services in accordance with building code and emergency services
17Social Infrastructure And Other Public Amenities Including Public Health Services
Incorporation of convenience retail space and health service to be added at later stage
18Emergency Evacuation Services
Wide Roadways with loop design will ensure clear emergency services and evacuation routes, open space and parks serve as assembly zones
19Other Miscellaneous Work
Include signages entry gate feature wall with township branding, art murals, community seating areas and instalaltion inspired by local ecology and culture
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 8 Jun 2030.

Sanctioned by Meerut Development Authority · 26,071 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Plotted resi development/Plotted Housing/07607/MDA/LD/24-25/1341/030320259 Jun 20258 Jun 20308 Jun 20308 Jun 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
BL-0226071Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · IN-UP7930515394613X
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Allotment letter from the authority · BBB04240875187
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New5 Jul 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Jul 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Jul 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Jul 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Jul 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Jul 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Jul 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New5 Jul 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Jul 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New5 Jul 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Jul 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Jul 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New5 Jul 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New5 Jul 2025 ↗

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2025-Q4.

QuarterConstructionCertificates
2025-Q237.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q326.74%CA ↗ · Arch ↗ · Eng ↗
2025-Q495%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameShakuntalam Habitats Private Limited
RolePromoter · current
RERA IDUPRERAPRM375150
PANAATCS8361E
CIN / TANU70102DL2013PTC259187
Name of chairmanAshish Gupta
Registered addressH-27, W8, Western Avenue, Sainik Farm House, South Delhi, Delhi-110062
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Meerut

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Shakuntalam Habitats Pvt Ltd Collection A/c Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave, Garh Road, Meerut, Uttar PradeshBranch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975Branch emailkratika.chauhan@icicibank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Shakuntalam Habitats Pvt Ltd. Separate Bank A/C Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave, Garh Road, Meerut- Uttar Pradesh 250001Branch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Shakuntalam Habitats Pvt Ltd Rera Transaction A/C Fairfield ResidencyBankICICI BankBranchMeerut Garh RoadBranch addressBDS Complex, Samrat Enclave Garh Road, Meerut, Uttar Pradesh 250001Branch districtMeerut, Uttar PradeshA/C no.IFSCICIC0000975
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about FairField Residency

Is FairField Residency RERA registered?

Yes. FairField Residency is registered with UPRERA under registration number UPRERAPRJ255302, registered on 7 Aug 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for FairField Residency?

The completion date filed with UPRERA is 8 Jun 2030. No completion certificate is on record yet.

Who is the builder of FairField Residency?

Shakuntalam Habitats Private Limited is the promoter entity that filed FairField Residency with UPRERA (promoter RERA ID UPRERAPRM375150). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does FairField Residency have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is FairField Residency located?

FairField Residency is registered in Meerut, Meerut, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗