Timeline Bar
Registered18 Feb 2022
Promised30 Sept 2024
Today4 Aug 2026
Timeline
Promised completion30 Sept 2024
Revised completion30 Sept 2024
Actual completion—
Possession delay22 mo delay
Registration & Cost Details
Registration fee (in ₹)₹89,000
Project cost (in ₹ Lakhs)₹1,480 Lakhs
Project duration33 months
Project categoryResidential
Locality—
Original start date—
Proposed start date14 Jan 2022
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9837009757
Emailrera@ganpatigroupindia.com
Coordinator9837885425
Address31/472 C1,IST FLORE ,GANASH PLAZA SULTAN GANJ PULIYA PIPASS ROAD AGRA
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1388/BFAH/02/06-07 | 31 Mar 2020 | 6 Oct 2023 | 30 Sept 2024 | 5 Oct 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 16, 17, 20, 23 | 33590 | Khasra |
Frequently Asked Questions
What is the RERA registration number of GANPATI WONDER CITY PHASE -I?
The RERA registration number of GANPATI WONDER CITY PHASE -I is UPRERAPRJ749543, as recorded on the UP-RERA portal.
What is the RERA status of GANPATI WONDER CITY PHASE -I?
As reported by UP-RERA, the status of GANPATI WONDER CITY PHASE -I is "Registered".
Where is GANPATI WONDER CITY PHASE -I located?
As reported to UP-RERA, GANPATI WONDER CITY PHASE -I is located at Agra, Agra, Uttar Pradesh.
When will GANPATI WONDER CITY PHASE -I be completed?
The latest completion date reported to UP-RERA for GANPATI WONDER CITY PHASE -I is 30 Sept 2024.
Is GANPATI WONDER CITY PHASE -I delayed?
Measured against the latest completion date reported to UP-RERA, GANPATI WONDER CITY PHASE -I is 22 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026