Gardenia Residency Phase 1

UPRERARegistered

Gardenia Residency Phase 1 is a RERA-registered residential project by Paarth Infrabuild Private Limited in Lucknow (RERA ID UPRERAPRJ9326). Registered with a completion deadline of 27 Aug 2025.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ9326
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Industrial Development Authority
Proposed start1 May 2015
Original start1 May 2015
Project duration124 months
AddressLucknow, Lucknow
TehsilLucknow
Applicant typeCompany
Applicant addressFlat Number 311-315, 3rd floor,Naurang House,Kasturba Gandhi Marg, New-Delhi-110001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. valid to

    Permit revalidated

    281

  3. Building permit sanctioned

    281

  4. valid to

    Permit revalidated

    434

  5. 2 building permits sanctioned

  6. Registered with RERA

  7. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  8. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  9. to

    Extension granted

  10. to

    Extension granted

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered11 Aug 2017
Original completion31 Aug 2020
Revised completion27 Aug 2025
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹17,500
Sanctioning authorityLucknow Industrial Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors56 · 1 · 6 (units from plan)
  • 3 BHK52 93%
  • 4 BHK4 7%
ConfigurationUnitsCarpet area
3 BHK52103-127
4 BHK4140
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Cluster 1AA · OTHER, 3 BHK, 4 BHK656103-140
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Rudrabhishek Enterprises Pvt. Ltd.
License CA/2005/35401
A-6, Sector-58, Noida, U.P.
Engineer
Rudrabhishek Enterprises Pvt. Ltd.
A-6, Sector-58, Noida, U.P.
Contractor
M/s. New Modern Buildwell (P) Ltd.
511, Ambadeep Building, New Delhi-110001
Sr.Development work declared to RERA
1Demarcation of Plots
As per layout approved from competent authority
2Boundary Wall
As per approved plan
3Road Work
Cement Concrete/Bituminous Road Network
4Footpaths
As per Bye-Laws
5Water Supply Including Drinking Water Facilities
Water Supply as per requirement provided
6Sewer System
Provision as per Bye-Laws
7Drain
Provision as per Bye-Laws
8Parks
Provided as per approved plan
9Tree Planting
As per Bye-Laws
10Design For Electric Supply Including Street Lighting
As per Bye-Laws
11Community Buildings
As per approved plan
12Treatment and Disposal System of Sewage and Sullage water
Provision as per Bye-Laws
13Solid Waste Management And Disposal System
Provision as per Bye-Laws
14Water Conservation System
Provision as per Bye-Laws
15Energy Management System Including Use of Renewable Energy
Provision as per Bye-Laws
16Fire Protection And Fire Safety System
Provision as per Bye-Laws
17Social Infrastructure And Other Public Amenities Including Public Health Services
Provision as per Bye-Laws at township level
18Emergency Evacuation Services
Provision as per Bye-Laws
19Other Miscellaneous Work
All necessary facilities provided as per Bye-Laws
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 5 Nov 2020. 2 of them carry a revalidation, the latest valid to 12 Aug 2025.

Sanctioned by Lucknow Industrial Development Authority · 2,411 sqm of land · an approved plan of 1 block and 56 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
4346 Nov 20155 Nov 20205 Nov 202531 Aug 2020—
4346 Nov 20155 Nov 202012 Aug 202827 Aug 20226 Nov 2015
valid to 12 Aug 2025
28113 Aug 201512 Aug 202012 Aug 202827 Aug 202213 Aug 2015
valid to 12 Aug 2025
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 27 Aug 2025.

#Granted fromExtended uptoNote
131 Aug 202028 Feb 2021Six months extension in view of force majeure caused by covid-19 pandemic
228 Feb 202127 Aug 2022—
327 Aug 202227 Aug 2025—

Land & documents

30 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
137150—
138150—
139500—
140200—
141200—
146200—
147531.05—
148180—
192300—
139700Khasra
140260Khasra
141280Khasra
18880Khasra
1921091Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 1 Nov 2014.

Registry no.DateTypeArea
235121 Nov 2014other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1419-1424
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New3 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New3 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New3 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New3 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New3 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New3 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New3 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New3 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New3 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New3 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New3 Jul 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old11 Aug 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old11 Aug 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old19 Dec 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterFacility provided as per building bye laws
Fire safety (as filed with RERA)Facility provided as per building bye laws
Health serviceFacility provided as per building bye laws wherever possible at township level
Renewable energyProvided at township level wherever possible as per building bye laws

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

22 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

22 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q234.4%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q2. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePaarth Infrabuild Private Limited
RolePromoter · current
RERA IDUPRERAPRM1883
PANAAECP0249B
CIN / TANU70109DL2006PTC152197
Name of chairmanAnubha Yadav
Registered addressFlat Number 311-315, 3rd floor,Naurang House,Kasturba Gandhi Marg, New-Delhi-110001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
PAARTH INFRABUILD PVT LTDBankHDFC BankBranchHDFC Bank LimitedA/C no.IFSCHDFC0002840
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

9 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)449 (Under Registration - 4 ) → 452 (Under Registration - 7 )
changed in Estanzo’s record
11 Oct 2026
Promoter’s complaints tally (all their projects)449 (Under Registration - 5 ) → 449 (Under Registration - 4 )
changed in Estanzo’s record
1 Oct 2026
Promoter’s complaints tally (all their projects)448 (Under Registration - 4 ) → 449 (Under Registration - 5 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)447 (Under Registration - 3 ) → 448 (Under Registration - 4 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)446 (Under Registration - 2 ) → 447 (Under Registration - 3 )
changed in Estanzo’s record
15 Sept 2026
Promoter’s complaints tally (all their projects)446 (Under Registration - 3 ) → 446 (Under Registration - 2 )
changed in Estanzo’s record
7 Sept 2026
Promoter’s complaints tally (all their projects)445 (Under Registration - 3 ) → 446 (Under Registration - 3 )
changed in Estanzo’s record
23 Aug 2026
Promoter’s complaints tally (all their projects)445 (Under Registration - 4 ) → 445 (Under Registration - 3 )
changed in Estanzo’s record
16 Aug 2026
Promoter’s complaints tally (all their projects)444 (Under Registration - 3 ) → 445 (Under Registration - 4 )
changed in Estanzo’s record
10 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 11 Oct 2026 · 9 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about Gardenia Residency Phase 1

Is Gardenia Residency Phase 1 RERA registered?

Yes. Gardenia Residency Phase 1 is registered with UPRERA under registration number UPRERAPRJ9326, registered on 11 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Gardenia Residency Phase 1?

The completion date filed with UPRERA is 27 Aug 2025. No completion certificate is on record yet.

Who is the builder of Gardenia Residency Phase 1?

Paarth Infrabuild Private Limited is the promoter entity that filed Gardenia Residency Phase 1 with UPRERA (promoter RERA ID UPRERAPRM1883). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Gardenia Residency Phase 1 more time to complete?

UPRERA's record carries 3 completion extensions for Gardenia Residency Phase 1, the latest running to 27 Aug 2025. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Gardenia Residency Phase 1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Gardenia Residency Phase 1 located?

Gardenia Residency Phase 1 is registered in Lucknow, as filed with UPRERA.

What configurations are available in Gardenia Residency Phase 1?

The unit plan filed with UPRERA lists OTHER, 3 BHK and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Gardenia Residency Phase 1?

The approved unit plan filed with UPRERA runs from 103 to 140 m² of carpet area (about 1,109 to 1,503 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Gardenia Residency Phase 1?

The approved unit plan describes 1 block and 56 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Gardenia Residency Phase 1?

About 94 units per acre: 56 planned units across 0.60 acres (2,411 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗