Paarth Infrabuild Private Limited

UPRERACompany

Paarth Infrabuild Private Limited (RERA ID: UPRERAPRM1883) is a company registered with UP-RERA since 2017. It has 21 projects on record with Estanzo.

Summarize this record with:ChatGPTPerplexityClaudeGrok

One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.

Projects by this promoter

21 on record
Registered21each project counted once, under the authority’s own step
Aadyant Phase-1 UPRERA
UPRERAPRJ5585 · Lucknow
Promised completion 30 Nov 2019 · Extended
Registered
Aadyant Phase-2 UPRERA
UPRERAPRJ3388 · Lucknow
Promised completion 31 Dec 2019 · Extended
Registered
Aadyant Phase-3 UPRERA
UPRERAPRJ3410 · Lucknow
Promised completion 16 Sept 2018
Registered
Aadyant Phase-4 UPRERA
UPRERAPRJ3462 · Lucknow
Promised completion 31 Dec 2019 · Extended
Registered
Aadyant Phase 5 (Revati B) UPRERA
UPRERAPRJ4179 · Lucknow
Promised completion 30 Jun 2022 · Extended
Registered
Arka Phase 1 (EWS/LIG) UPRERA
UPRERAPRJ4188 · Lucknow
Promised completion 20 Dec 2019 · Extended
Registered
Arka Phase-2 UPRERA
UPRERAPRJ3599 · Lucknow
Promised completion 29 Dec 2021 · Extended
Registered
Arka Phase-3 UPRERA
UPRERAPRJ3607 · Lucknow
Promised completion 27 Aug 2022 · Extended
Registered
Canary Phase 1 UPRERA
UPRERAPRJ8549 · Lucknow
Promised completion 28 Mar 2024 · Extended
Registered
Canary Phase 2 UPRERA
UPRERAPRJ8652 · Lucknow
Promised completion 28 Mar 2024 · Extended
Registered
Gardenia Residency Phase 1 UPRERA
UPRERAPRJ9326 · Lucknow
Promised completion 27 Aug 2025 · Extended
Registered
Gardenia Residency Phase-2 UPRERA
UPRERAPRJ14996 · Lucknow
Promised completion 27 Aug 2023 · Extended
Registered
Goldfinch Phase 1 UPRERA
UPRERAPRJ8691 · Lucknow
Promised completion 29 Dec 2021 · Extended
Registered
Goldfinch Phase-2 UPRERA
UPRERAPRJ8072 · Lucknow
Promised completion 30 Jun 2023 · Extended
Registered
Humming Phase-1 UPRERA
UPRERAPRJ8271 · Lucknow
Promised completion 29 May 2024 · Extended
Registered
Humming Phase-2 UPRERA
UPRERAPRJ8168 · Lucknow
Promised completion 29 Feb 2024 · Extended
Registered
Humming Retreat Phase-1 UPRERA
UPRERAPRJ17775 · Lucknow
Promised completion 20 Oct 2024 · Extended
Registered
Humming Retreat Phase-2 UPRERA
UPRERAPRJ17781 · Lucknow
Promised completion 20 Oct 2025 · Extended
Registered
NU Phase-1 UPRERA
UPRERAPRJ3492 · Lucknow
Promised completion 30 Jun 2026 · Extended
Registered
Paarth Republic - EWS/LIG UPRERA
UPRERAPRJ8607 · Lucknow
Promised completion 28 Apr 2024 · Extended
Registered

Showing 20 of 21 projects on record. See all 21 projects

Promoters sharing a director

1 other

Linked by a director’s DIN, never by name alone. Each company is its own record.

2Promoters22Projects466Complaints40Extensions0QPR defaultNone completed, de-registered, in NCLT or in abeyance.

Projects of promoters sharing a director

1 project

Registered by the promoters above, not under this registration.

Sort by

Filings for more time

38 filings
Extension filings38
Projects with at least one20 of 21
Longest single extension1,096 days - Gardenia Residency Phase 1
Latest extension runs to30 Jun 2026 - NU Phase-1
Permits carrying a revalidation27 across 16 projects

Directors & ownership

2 named by UPRERA
Chairman
ANUBHA YADAV
Director
Aditya Yadav

Promoter timeline

9 Dec 2013 - 10 Jul 2025
  1. Completion certificate filed
    official source ↗
  2. Extension filed
    new completion date on file 20 Oct 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  3. Completion certificate filed
    official source ↗
  4. Extension filed
    new completion date on file 20 Oct 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  5. Extension filed
    new completion date on file 30 Jun 2026official source ↗
  6. Extension filed
    new completion date on file 29 Feb 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  7. Permit revalidated
    valid to 23 Jul 2028as recorded by UPRERA: 1019official source ↗
  8. Permit revalidated
    valid to 24 Sept 2024as recorded by UPRERA: 413official source ↗
  9. Permit revalidated
    valid to 24 Jul 2024as recorded by UPRERA: 413official source ↗
  10. Extension filed
    new completion date on file 29 May 2024official source ↗
  11. Extension filed
    new completion date on file 28 Apr 2024official source ↗
  12. Extension filed
    new completion date on file 28 Mar 2024official source ↗
Show 76 earlier filings
  1. Extension filed
    new completion date on file 28 Mar 2024official source ↗
  2. Extension filed
    new completion date on file 27 Aug 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  3. Extension filed
    new completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  4. Extension filed
    new completion date on file 29 May 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  5. Extension filed
    new completion date on file 27 Nov 2025official source ↗
  6. Extension filed
    new completion date on file 30 Apr 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  7. Extension filed
    new completion date on file 29 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  8. Extension filed
    new completion date on file 29 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  9. Extension filed
    new completion date on file 27 Aug 2025official source ↗
  10. Extension filed
    new completion date on file 31 Dec 2023official source ↗
  11. Extension filed
    new completion date on file 27 Nov 2022official source ↗
  12. Extension filed
    new completion date on file 27 Aug 2022official source ↗
  13. Extension filed
    new completion date on file 20 Jul 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  14. Extension filed
    new completion date on file 30 Jun 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  15. Extension filed
    new completion date on file 29 Dec 2021official source ↗
  16. Extension filed
    new completion date on file 28 May 2022official source ↗
  17. Extension filed
    new completion date on file 29 Dec 2021official source ↗
  18. Extension filed
    new completion date on file 27 Aug 2022official source ↗
  19. Extension filed
    new completion date on file 28 Feb 2022official source ↗
  20. Extension filed
    new completion date on file 29 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  21. Extension filed
    new completion date on file 29 May 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  22. Extension filed
    new completion date on file 30 Apr 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  23. Extension filed
    new completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  24. Extension filed
    new completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
  25. Extension filed
    new completion date on file 31 Oct 2020official source ↗
  26. Extension filed
    new completion date on file 30 Dec 2020official source ↗
  27. Extension filed
    new completion date on file 31 Dec 2019official source ↗
  28. Extension filed
    new completion date on file 30 Jun 2019official source ↗
  29. Extension filed
    new completion date on file 31 Dec 2019official source ↗
  30. Extension filed
    new completion date on file 20 Dec 2019official source ↗
  31. Extension filed
    new completion date on file 30 Nov 2019official source ↗
  32. Project registered
    official source ↗
  33. Project registered
    official source ↗
  34. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 1238official source ↗
  35. Permit revalidated
    as recorded by UPRERA: 1238official source ↗
  36. Permit revalidated
    valid to 20 Jul 2028as recorded by UPRERA: 1019official source ↗
  37. Permit revalidated
    valid to 23 Jul 2028as recorded by UPRERA: 1019official source ↗
  38. Permit revalidated
    as recorded by UPRERA: 1019official source ↗
  39. Permit revalidated
    as recorded by UPRERA: 1019official source ↗
  40. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 1018official source ↗
  41. Project registered
    official source ↗
  42. Permit revalidated
    valid to 2 Apr 2025as recorded by UPRERA: 38884official source ↗
  43. Project registered
    official source ↗
  44. Project registered
    official source ↗
  45. Project registered
    official source ↗
  46. Project registered
    official source ↗
  47. Project registered
    official source ↗
  48. Project registered
    official source ↗
  49. Project registered
    official source ↗
  50. Project registered
    official source ↗
  51. Project registered
    official source ↗
  52. Project registered
    official source ↗
  53. Project registered
    official source ↗
  54. Project registered
    official source ↗
  55. Project registered
    official source ↗
  56. Project registered
    official source ↗
  57. Project registered
    official source ↗
  58. Project registered
    official source ↗
  59. Project registered
    official source ↗
  60. Project registered
    official source ↗
  61. Permit revalidated
    valid to 22 Feb 2022as recorded by UPRERA: 41248official source ↗
  62. Permit revalidated
    valid to 22 Feb 2022as recorded by UPRERA: 41248official source ↗
  63. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 434official source ↗
  64. Permit revalidated
    as recorded by UPRERA: 433official source ↗
  65. Permit revalidated
    valid to 5 Nov 2025as recorded by UPRERA: 432official source ↗
  66. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 434official source ↗
  67. Permit revalidated
    as recorded by UPRERA: 38814official source ↗
  68. Permit revalidated
    as recorded by UPRERA: 38814official source ↗
  69. Permit revalidated
    as recorded by UPRERA: 38814official source ↗
  70. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
  71. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
  72. Permit revalidated
    valid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
  73. Permit revalidated
    as recorded by UPRERA: 37617official source ↗
  74. Permit revalidated
    as recorded by UPRERA: 37617official source ↗
  75. Permit revalidated
    as recorded by UPRERA: 35791official source ↗
  76. Permit revalidated
    as recorded by UPRERA: 35791official source ↗

Quarterly reports filed, by financial year

FY 2020-21
72 reports across 18 projects
FY 2021-22
68 reports across 18 projects
FY 2022-23
51 reports across 14 projects
FY 2023-24
44 reports across 12 projects
FY 2024-25
22 reports across 8 projects
FY 2025-26
12 reports across 4 projects
FY 2026-27
1 report across 1 project
Counts the reports UPRERA publishes as filed.
A filing is not an outcome.

Common questions about Paarth Infrabuild Private Limited

How many projects has Paarth Infrabuild Private Limited registered with RERA?

Estanzo holds 21 projects on record with UPRERA, filed by Paarth Infrabuild Private Limited (promoter RERA ID UPRERAPRM1883). This counts filings by this legal entity only - a builder brand may file through several entities.

Who are the directors of Paarth Infrabuild Private Limited?

Paarth Infrabuild Private Limited disclosed 2 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.

When was Paarth Infrabuild Private Limited registered with RERA?

Paarth Infrabuild Private Limited has been registered with UPRERA since 26 Jul 2017.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗