Paarth Infrabuild Private Limited (RERA ID: UPRERAPRM1883) is a company registered with UP-RERA since 2017. It has 21 projects on record with Estanzo.
One legal entity’s record; a brand may register through several. Complaint counts are allegations, with no outcome attached.
Projects by this promoter
21 on record
Showing 20 of 21 projects on record. See all 21 projects
Filings for more time
38 filings
| Extension filings | 38 |
| Projects with at least one | 20 of 21 |
| Longest single extension | 1,096 days - Gardenia Residency Phase 1 |
| Latest extension runs to | 30 Jun 2026 - NU Phase-1 |
| Permits carrying a revalidation | 27 across 16 projects |
Directors & ownership
2 named by UPRERA
Promoter timeline
9 Dec 2013 - 10 Jul 2025
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 20 Oct 2025as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Completion certificate filedofficial source ↗
- Extension filednew completion date on file 20 Oct 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2026official source ↗
- Extension filednew completion date on file 29 Feb 2024as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Permit revalidatedvalid to 23 Jul 2028as recorded by UPRERA: 1019official source ↗
- Permit revalidatedvalid to 24 Sept 2024as recorded by UPRERA: 413official source ↗
- Permit revalidatedvalid to 24 Jul 2024as recorded by UPRERA: 413official source ↗
- Extension filednew completion date on file 29 May 2024official source ↗
- Extension filednew completion date on file 28 Apr 2024official source ↗
- Extension filednew completion date on file 28 Mar 2024official source ↗
Show 76 earlier filings
- Extension filednew completion date on file 28 Mar 2024official source ↗
- Extension filednew completion date on file 27 Aug 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 May 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 27 Nov 2025official source ↗
- Extension filednew completion date on file 30 Apr 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Mar 2023as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 27 Aug 2025official source ↗
- Extension filednew completion date on file 31 Dec 2023official source ↗
- Extension filednew completion date on file 27 Nov 2022official source ↗
- Extension filednew completion date on file 27 Aug 2022official source ↗
- Extension filednew completion date on file 20 Jul 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Jun 2022as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 Dec 2021official source ↗
- Extension filednew completion date on file 28 May 2022official source ↗
- Extension filednew completion date on file 29 Dec 2021official source ↗
- Extension filednew completion date on file 27 Aug 2022official source ↗
- Extension filednew completion date on file 28 Feb 2022official source ↗
- Extension filednew completion date on file 29 Jun 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 29 May 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 30 Apr 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 28 Feb 2021as recorded by UPRERA: Six months extension in view of force majeure caused by covid-19 pandemicofficial source ↗
- Extension filednew completion date on file 31 Oct 2020official source ↗
- Extension filednew completion date on file 30 Dec 2020official source ↗
- Extension filednew completion date on file 31 Dec 2019official source ↗
- Extension filednew completion date on file 30 Jun 2019official source ↗
- Extension filednew completion date on file 31 Dec 2019official source ↗
- Extension filednew completion date on file 20 Dec 2019official source ↗
- Extension filednew completion date on file 30 Nov 2019official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 1238official source ↗
- Permit revalidatedas recorded by UPRERA: 1238official source ↗
- Permit revalidatedvalid to 20 Jul 2028as recorded by UPRERA: 1019official source ↗
- Permit revalidatedvalid to 23 Jul 2028as recorded by UPRERA: 1019official source ↗
- Permit revalidatedas recorded by UPRERA: 1019official source ↗
- Permit revalidatedas recorded by UPRERA: 1019official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 1018official source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 2 Apr 2025as recorded by UPRERA: 38884official source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Project registeredofficial source ↗
- Permit revalidatedvalid to 22 Feb 2022as recorded by UPRERA: 41248official source ↗
- Permit revalidatedvalid to 22 Feb 2022as recorded by UPRERA: 41248official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 434official source ↗
- Permit revalidatedas recorded by UPRERA: 433official source ↗
- Permit revalidatedvalid to 5 Nov 2025as recorded by UPRERA: 432official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 434official source ↗
- Permit revalidatedas recorded by UPRERA: 38814official source ↗
- Permit revalidatedas recorded by UPRERA: 38814official source ↗
- Permit revalidatedas recorded by UPRERA: 38814official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
- Permit revalidatedvalid to 12 Aug 2025as recorded by UPRERA: 281official source ↗
- Permit revalidatedas recorded by UPRERA: 37617official source ↗
- Permit revalidatedas recorded by UPRERA: 37617official source ↗
- Permit revalidatedas recorded by UPRERA: 35791official source ↗
- Permit revalidatedas recorded by UPRERA: 35791official source ↗
Quarterly reports filed, by financial year
Common questions about Paarth Infrabuild Private Limited
How many projects has Paarth Infrabuild Private Limited registered with RERA?
Estanzo holds 21 projects on record with UPRERA, filed by Paarth Infrabuild Private Limited (promoter RERA ID UPRERAPRM1883). This counts filings by this legal entity only - a builder brand may file through several entities.
Who are the directors of Paarth Infrabuild Private Limited?
Paarth Infrabuild Private Limited disclosed 2 directors or partners to UPRERA, listed on this page as published. Estanzo shows the names and roles from that filing only.
When was Paarth Infrabuild Private Limited registered with RERA?
Paarth Infrabuild Private Limited has been registered with UPRERA since 26 Jul 2017.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗