Timeline Bar
Registered2 Aug 2017
Promised23 Apr 2021
Today4 Aug 2026
Timeline
Promised completion23 Apr 2021
Revised completion23 Apr 2021
Actual completion—
Possession delay63 mo delay
Registration & Cost Details
Registration fee (in ₹)₹34,000
Project cost (in ₹ Lakhs)₹8,583 Lakhs
Project duration52 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Jul 2017
Inventory
Total units240
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 182 | 74.25 |
| 3 BHK | 58 | 95.82–112.06 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9956397026
Emailgoldstardelhi01@gmail.com
Coordinator9015733539
Address1106, ANTRIKSH BHAWAN, 22 K.G. MARG, CONNOUGHT PLACE, NEW DELHI-110001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1037 | 25 Apr 2016 | 24 Apr 2021 | 23 Apr 2021 | 24 Apr 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 4A/GH3 SECTOR 4A, VRINDAVAN YOJNA-NO.-2 PART-1, TE | 5717 | — |
| GH-3 | 5717 | Plot |
Approved Unit Plan
Unit plan rows on file57
Total flats (sum of rows)240
BlocksT-3 Block
Floor types2 BHK, 3 BHK
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 907 | 20 Jan 2011 | — | — |
Frequently Asked Questions
What is the RERA registration number of GOLD STAR HOMES PHASE-II?
The RERA registration number of GOLD STAR HOMES PHASE-II is UPRERAPRJ6220, as recorded on the UP-RERA portal.
What is the RERA status of GOLD STAR HOMES PHASE-II?
As reported by UP-RERA, the status of GOLD STAR HOMES PHASE-II is "Registered".
Where is GOLD STAR HOMES PHASE-II located?
As reported to UP-RERA, GOLD STAR HOMES PHASE-II is located at Lucknow, Lucknow, Uttar Pradesh.
When will GOLD STAR HOMES PHASE-II be completed?
The latest completion date reported to UP-RERA for GOLD STAR HOMES PHASE-II is 23 Apr 2021.
Is GOLD STAR HOMES PHASE-II delayed?
Measured against the latest completion date reported to UP-RERA, GOLD STAR HOMES PHASE-II is 63 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026