Estanzo

Timeline Bar

Registered31 Jul 2017
Promised31 Dec 2021
Completed30 Sept 2022

Timeline

Promised completion31 Dec 2021
Revised completion31 Dec 2021
Actual completion30 Sept 2022
Possession delay9 mo delay

Registration & Cost Details

Registration fee (in ₹)₹50,000
Project cost (in ₹ Lakhs)₹8,500 Lakhs
Project duration75 months
Project categoryResidential
Locality
Original start date15 Sept 2014
Proposed start date1 Apr 2016

Inventory

Total units74
Unit TypeUnitsCarpet Area (sqm)
3 BHK48133.49–133.98
4 BHK26170.33

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7570007505
Emailacct.crestinfracon@gmail.com
Coordinator7570007505
AddressCORONATION ANAND TOWER, 116-117, 1ST FLOOR, VIBHUTI KHAND, GOMTI NAGAR, LUCKNOW

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
417008 Mar 20177 Mar 202231 Dec 20216 Mar 2025

Land Parcels

Khasra No.AreaPlot Type
GH-5 SECTOR-H SUSHANT GOLF CITY8986Plot

Approved Unit Plan

Unit plan rows on file78
Total flats (sum of rows)74
BlocksBLOCK-A TOWER -1, BLOCK-A TOWER -2
Floor types3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2)?

The RERA registration number of GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) is UPRERAPRJ6392, as recorded on the UP-RERA portal.

What is the RERA status of GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2)?

As reported by UP-RERA, the status of GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) is "Registered".

Where is GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) located?

As reported to UP-RERA, GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) is located at Lucknow, Lucknow, Uttar Pradesh.

Is GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) completed?

As reported to UP-RERA, GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) was completed on 30 Sept 2022.

Is GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) delayed?

Measured against the latest completion date reported to UP-RERA, GOLF RIDGE TOWER - BLOCK-A (TOWER- 1 & 2) is 9 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.