Himalaya City Center Phase-1 is a RERA-registered real-estate project in Ghaziabad (RERA ID UPRERAPRJ728824). Its RERA-registered completion deadline (31 Dec 2024) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ728824 |
| Applicant type | Company |
| Project category | Commercial |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Jan 2021 |
| Project duration | 56 |
| Address | Ghaziabad, Ghaziabad |
| RERA registered | 22 Jan 2021 |
| Promised completion | 31 Dec 2024 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹1,38,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 548 | 6–82 |
| OTHER | 6 | 4–3,226 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| 2614/MasterPlan/Zone-1/2020 | 7 Oct 2020 | 17 Aug 2025 | 31 Dec 2024 |
| Khasra | Area | Type |
|---|---|---|
| 537 | 6240 | Khasra |
| 538 | 843 | Khasra |
| 538 | 4804 | Khasra |
| 538 | 843 | Khasra |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
| 2024-Q4 | — | CA · Arch · Eng | view ↗ |
| 2025-Q1 | — | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 85.27% | CA · Arch · Eng | view ↗ |
Other projects registered in Ghaziabad.
Yes. Himalaya City Center Phase-1 is registered with UPRERA under registration number UPRERAPRJ728824, registered on 22 Jan 2021. Estanzo reproduces that filing; it does not verify the work behind it.
Himalaya City Center Phase-1 is 19 months past the completion date filed with UPRERA (31 Dec 2024), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Himalaya City Center Phase-1 is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗