Registered15 Aug 2017
Promised28 Nov 2019
Revised25 Nov 2020
Completed10 Feb 2021

Timeline

Promised completion28 Nov 2019
Revised completion25 Nov 2020
Actual completion10 Feb 2021
Possession delay3 mo delay

Registration & Cost Details

Registration fee (in ₹)₹41,500
Project cost (in ₹ Lakhs)₹6,100 Lakhs
Project duration72 months
Project categoryResidential
Locality
Original start date7 Dec 2014
Proposed start date7 Dec 2014

Inventory

Total units144
Unit TypeUnitsCarpet Area (sqm)
1 BHK351.26
2 BHK5763.2–280.43
3 BHK7580.12–409.93
4 BHK471.39–154.29
5 BHK390.65–213.17
OTHER2241.72

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9935167382
Emailgargrakesh091@gmail.com
Coordinator7388508221
Address35, catiappa cantoment, Knapur

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
MAP73/342/BHAVAN/15-164 Aug 20163 Aug 202125 Nov 20203 Aug 2024
MAP73/342/BHAVAN/15-164 Aug 20163 Aug 202125 Nov 20203 Aug 2024

Land Parcels

Khasra No.AreaPlot Type
00
127/219-A, JUHI KALAN, HAMIRPUR ROAD, KANPUR7388.63Plot

Approved Unit Plan

Unit plan rows on file57
Total flats (sum of rows)144
BlocksTower A, Tower B
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, 5 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1378424 Sept 2012
552025 Mar 2013
1039524 Jul 2013
252527 Feb 2013
90656 Jul 2013
132730 Jan 2013

Frequently Asked Questions

What is the RERA registration number of JYOTI HEIGHTS APARTMENT?

The RERA registration number of JYOTI HEIGHTS APARTMENT is UPRERAPRJ11369, as recorded on the UP-RERA portal.

What is the RERA status of JYOTI HEIGHTS APARTMENT?

As reported by UP-RERA, the status of JYOTI HEIGHTS APARTMENT is "Registered".

Where is JYOTI HEIGHTS APARTMENT located?

As reported to UP-RERA, JYOTI HEIGHTS APARTMENT is located at Kanpur, Kanpur Nagar, Uttar Pradesh.

Is JYOTI HEIGHTS APARTMENT completed?

As reported to UP-RERA, JYOTI HEIGHTS APARTMENT was completed on 10 Feb 2021.

Is JYOTI HEIGHTS APARTMENT delayed?

Measured against the latest completion date reported to UP-RERA, JYOTI HEIGHTS APARTMENT is 3 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026