KRISHNA CARNIVAL

UPRERARegistered

KRISHNA CARNIVAL is a RERA-registered residential project by PG INFRADEVELOPERS LLP in Maghtai, Agra (RERA ID UPRERAPRJ325978). Registered with a completion deadline of 1 Jan 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'25
0%Q3'25
14.5%Q4'25
14.5%Q1'26
15%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ325978
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAgra Development Authority
Proposed start4 Apr 2025
Project duration57 months
AddressKhasra No. 72, 74, 75(p), 76, 77, 78, Situated at Mauza Maghtai, Maghtai, Agra, Agra
TehsilAgra
Applicant typeLimited Liability Partnership (LLP)
Applicant address1/5, 1/6 KHOJA HAVELI, GARG COMPLEX,DHAKRAN CROSSING, M.G. RORAD,AGRA,Agra,Uttar Pradesh,282010,India
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Plottet Resi Development/Plotted Housing/06372/ADA/LD/23-24/1514/23082024

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered13 Jun 2025
Original completion1 Jan 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹1,18,000
Sanctioning authorityAgra Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
VISHNU UPADHYAY
License CA/2022/148821
56, JAIPUR HOUSE MARKET, AGRA
Engineer
A.K. UPADHYAY
56, JAIPUR HOUSE MARKET, AGRA
Contractor
PG INFRADEVELOPERS LLP
1/5,1/6, khoja Haveli, Garg Complex, Dhakran Crossing, Agra 282010
Sr.Development work declared to RERA
1Demarcation of Plots
The Project is to be developed in total area of 22521.49 square meter. The project has 124 residentiona plots. All the plots and roads along with Park and other amenities will be demarcated as per the approved map from Agra Development Authority in size , shape and Orientation
2Boundary Wall
A 6 to 8 feet high boundary wall will be constructed for the project land. Te Earth quake resistatant boundaruy wall will be constructed as per design in brick and mortar. The wall wlll be plastered and painted
3Road Work
The roads, 7.5 m and 9 m wde will have the compacted subgrade, Granular Sub -base of min 150mm, granular base for flexible pavement . The CC road or paver interlocking shall be provided at the required location.
4Footpaths
The Inerlocking paver blocks of minimum 60mm having strength of M-25 will be laid over compacted erath and a bed of sand 30-40mm thck.
5Water Supply Including Drinking Water Facilities
The water will be supplied to each unit through 80mm wide PVC pipe line connected to the water tank of capacity 200000 liter. The underground water will be pumped through submersible set p.
6Sewer System
200 mm diameter NP3 hume pipe will be laid in the project to cater for the residential needs of each unit. The Inspection chambers of sixze 1.00 x 1.20 x . 1.50 will be constructed in concrete. The slopes will be to ensure the gravtional flow and early clearance.
7Drain
The trapezoidal shape lined drain, subsurface/ surface will be constructed in the project in concrete. The base thickness will be minimum 75 mm with with of minimum 200mm and height as per design.
8Parks
The 3 lush green par with amenities for ids and elderly will be developed in the project at locations specified in the approved map.
9Tree Planting
Trees will be planted at all suitable locations of the project. Near boundary wall and Periphery of Parks.
10Design For Electric Supply Including Street Lighting
Fxing of electric poles, underground cable and feeder pillars with conductors and suitable street lights will be constructed in the project along the roads and common areas.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
The sewer lines will lead to the multi stage sewage treatment plant of minimum size 3mx4mx5m. The STP will be designed to get the efflunts within permissible limit before disposal at designated location of municipal corporation
13Solid Waste Management And Disposal System
The Dalab ghars will be constructed in the project to collect and dispose off the solid waste of the project.
14Water Conservation System
PVC slotted pipe 150mmm dia, with bail plugh at the bottom will be inserted to the required depth. Te rectagular collect chamber will be constructed at the p with multi layer filteration medium in layers
15Energy Management System Including Use of Renewable Energy
Not Applicable
16Fire Protection And Fire Safety System
Not Applicable
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not Applicable
18Emergency Evacuation Services
Not Applicable
19Other Miscellaneous Work
As per Project requirements
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 1 Jan 2030.

Sanctioned by Agra Development Authority · 22,521 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Plottet Resi Development/Plotted Housing/06372/ADA/LD/23-24/1514/230820247 Jan 20251 Jan 203031 Dec 20331 Jan 2030
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

23 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
78, Mauja Maghtai, Agra3000Khasra
77, Mauja Maghtai, Agra3000Khasra
74, Mauja Maghtai, Agra3000Khasra
76, Mauja Maghtai, Agra3000Khasra
75(p), Mauja Magtai, Agra2485Khasra
75(p), Mauja Maghtai, Agra3727Khasra
72, Mauja Maghtai, Agra5860Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 12002
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 11863
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 3381
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4624
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 68
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9064
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9107
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1426-1431
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New17 Mar 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New16 Mar 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New16 Mar 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New19 Mar 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New16 Mar 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New16 Mar 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 May 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New19 Mar 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New3 May 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New19 Mar 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 Mar 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New19 Mar 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New10 Apr 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New17 Mar 2025 ↗

Quarterly progress reports

5 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

5 quarterly progress reports are on file with UPRERA, covering 2025-Q1 to 2026-Q1.

QuarterConstructionCertificates
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q314.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q414.5%CA ↗ · Arch ↗ · Eng ↗
2026-Q115%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal namePG INFRADEVELOPERS LLP
RolePromoter · current
RERA IDUPRERAPRM347272
PANAAWFP8599B
CIN / TANAGRP12520E
Registered address1/5, 1/6 KHOJA HAVELI, GARG COMPLEX,DHAKRAN CROSSING, M.G. RORAD,AGRA,Agra,Uttar Pradesh,282010,India
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Agra

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
PG INFRADEVELOPERS LLP RERA DEIGNATED COLLECTION ACC FOR KRISHNA CARNIVALBankIDBI BANK LIMITEDBranchSANJAY PLACE, AGRABranch addressPadamdeep Tower Sanjay Place _AgraBranch districtAgraA/C no.IFSCIBKL0000080Branch emailibkl0000080@idbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
PG INFRADEVELOPERS LLP RERA DESIGNATED SEPARATE ACC FOR KRISHNA CARNIVALBankIDBI BANK LIMITEDBranchSanjay Place, AgraBranch addressPadamdeep Tower, Sanjay Place, AgraBranch districtAgra, Uttar PradeshA/C no.IFSCIBKL0000080
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
PG INFRADEVELOPERS LLP RERA DESIGNATED TRANSACTION AC FOR KRISHNA CARNIVALBankIDBI BANK LIMITEDBranchSanjay Place, AgraBranch addressPadamdeep Tower, Sanjay Place, AgraBranch districtAgra, Uttar PradeshA/C no.IFSCIBKL0000080
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about KRISHNA CARNIVAL

Is KRISHNA CARNIVAL RERA registered?

Yes. KRISHNA CARNIVAL is registered with UPRERA under registration number UPRERAPRJ325978, registered on 13 Jun 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for KRISHNA CARNIVAL?

The completion date filed with UPRERA is 1 Jan 2030. No completion certificate is on record yet.

Who is the builder of KRISHNA CARNIVAL?

PG INFRADEVELOPERS LLP is the promoter entity that filed KRISHNA CARNIVAL with UPRERA (promoter RERA ID UPRERAPRM347272). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does KRISHNA CARNIVAL have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is KRISHNA CARNIVAL located?

KRISHNA CARNIVAL is registered in Maghtai, Agra, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗