Timeline Bar
Registered15 Aug 2017
Promised31 Dec 2019
Today29 Jul 2026
Timeline
Promised completion31 Dec 2019
Revised completion31 Dec 2019
Actual completion—
Possession delay79 mo delay
Registration & Cost Details
Registration fee (in ₹)₹20,000
Project cost (in ₹ Lakhs)₹1,800 Lakhs
Project duration84 months
Project categoryResidential
Locality—
Original start date1 Jan 2013
Proposed start date1 Jan 2013
Inventory
Total units70
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 7 | 67.75 |
| 2 BHK | 42 | 72.85–95.85 |
| 3 BHK | 7 | 100.9 |
| 4 BHK | 14 | 112.28–117.8 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9412206042
Emailrajenderchauhan10@gmail.com
Coordinator9412206042
Address5 / II, VIVEK VIHAR, RORKEE ROAD, MEERUT - 250002
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1057/2011 | 19 May 2012 | 18 May 2017 | 31 Dec 2019 | 31 Dec 2019 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 1751,1752, 1753, 1763/2, 1764/2,1749/2, 1750/1 | 2994.44 | — |
Approved Unit Plan
Unit plan rows on file58
Total flats (sum of rows)70
Blocks1
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| NIl | 24 Sept 2013 | — | — |
Frequently Asked Questions
What is the RERA registration number of LOTUS TOWER?
The RERA registration number of LOTUS TOWER is UPRERAPRJ8753, as recorded on the UP-RERA portal.
What is the RERA status of LOTUS TOWER?
As reported by UP-RERA, the status of LOTUS TOWER is "Registered".
Where is LOTUS TOWER located?
As reported to UP-RERA, LOTUS TOWER is located at Meerut, Meerut, Uttar Pradesh.
When will LOTUS TOWER be completed?
The latest completion date reported to UP-RERA for LOTUS TOWER is 31 Dec 2019.
Is LOTUS TOWER delayed?
Measured against the latest completion date reported to UP-RERA, LOTUS TOWER is 79 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026