Promised18 Apr 2017
Registered15 Aug 2017
Completed22 Apr 2019

Timeline

Promised completion18 Apr 2017
Revised completion
Actual completion22 Apr 2019
Possession delay24 mo delay

Registration & Cost Details

Registration fee (in ₹)₹2,64,000
Project cost (in ₹ Lakhs)₹17,500 Lakhs
Project duration43 months
Project categoryResidential
Locality
Original start date17 Oct 2013
Proposed start date17 Oct 2013

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8130074912
Emailrera@alpha-corp.com
Coordinator8171979666
AddressRegistered Office: UPPER BASEMENT, ALPHA MALL, MBM FARM, GT ROAD, SULTAN WIND SUB URBAN, AMRITSAR, P

No promoter data available.

Land Parcels

Khasra No.AreaPlot Type
1674mi, 1730mi, 1743, 1731, 1732, 1734, 1676, 173345589.13 square meter
212, 213mi, 214, 215, 216, 217/1, 218/1, 219/1, 3333125.94 square meter

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1084624 Oct 2007
744727 Jul 2007
745227 Jul 2007
745127 Jul 2007
745327 Jul 2007
432824 Apr 2007
745527 Jul 2007
745627 Jul 2007
432623 Apr 2007
432723 Apr 2007
433024 Apr 2007
432924 Apr 2007
744527 Apr 2007
744627 Jul 2007
1304022 Dec 2007
1304022 Dec 2007
1309524 Dec 2007
1305522 Dec 2007
158913 Feb 2008
159213 Feb 2008
1186720 Nov 2007
874021 Aug 2008
873621 Aug 2008
296629 Feb 2012
31553 Mar 2012
385017 Mar 2012
1474628 Sept 2012
1474528 Sept 2012
1473528 Sept 2012
1474928 Sept 2012
1163417 Jul 2013
1163517 Jul 2013

Frequently Asked Questions

What is the RERA registration number of MEERUTONE (RESIDENTIAL GROUP HOUSING)?

The RERA registration number of MEERUTONE (RESIDENTIAL GROUP HOUSING) is UPRERAPRJ11528, as recorded on the UP-RERA portal.

What is the RERA status of MEERUTONE (RESIDENTIAL GROUP HOUSING)?

As reported by UP-RERA, the status of MEERUTONE (RESIDENTIAL GROUP HOUSING) is "Registered".

Where is MEERUTONE (RESIDENTIAL GROUP HOUSING) located?

As reported to UP-RERA, MEERUTONE (RESIDENTIAL GROUP HOUSING) is located at Sardhana, Meerut, Uttar Pradesh.

Is MEERUTONE (RESIDENTIAL GROUP HOUSING) completed?

As reported to UP-RERA, MEERUTONE (RESIDENTIAL GROUP HOUSING) was completed on 22 Apr 2019.

Is MEERUTONE (RESIDENTIAL GROUP HOUSING) delayed?

Measured against the latest completion date reported to UP-RERA, MEERUTONE (RESIDENTIAL GROUP HOUSING) is 24 months beyond that date.