Timeline Bar
Registered31 Jul 2021
Promised26 Sept 2024
Today4 Aug 2026
Timeline
Promised completion26 Sept 2024
Revised completion26 Sept 2024
Actual completion—
Possession delay22 mo delay
Registration & Cost Details
Registration fee (in ₹)₹24,500
Project cost (in ₹ Lakhs)₹2,985 Lakhs
Project duration58 months
Project categoryResidential
Locality—
Original start date—
Proposed start date1 Dec 2019
Inventory
Total units71
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 7 | 70.83 |
| 3 BHK | 64 | 86.631–98.094 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile8171781111
Emailinfo@buoyantbuildtech.com
Coordinator8171781111
Address214 ALIG CORPORATE PLAZA, MARRIS ROAD, ALIGARH
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| MAP20190330174114323 | 27 Sept 2019 | 26 Sept 2024 | 26 Sept 2024 | 25 Sept 2027 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 387/2,388/2,390 | 3894.05 | Khasra |
Approved Unit Plan
Unit plan rows on file40
Total flats (sum of rows)71
Blocks1
Floor types2 BHK, 3 BHK, OTHER
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of MADHAVAS?
The RERA registration number of MADHAVAS is UPRERAPRJ984315, as recorded on the UP-RERA portal.
What is the RERA status of MADHAVAS?
As reported by UP-RERA, the status of MADHAVAS is "Registered".
Where is MADHAVAS located?
As reported to UP-RERA, MADHAVAS is located at Koil, Aligarh, Uttar Pradesh.
When will MADHAVAS be completed?
The latest completion date reported to UP-RERA for MADHAVAS is 26 Sept 2024.
Is MADHAVAS delayed?
Measured against the latest completion date reported to UP-RERA, MADHAVAS is 22 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026