Mahalakshmi Apartments

UPRERARegistered

Mahalakshmi Apartments is a RERA-registered residential project by MAHALAKSHMI APARTMENTS LLP in Chak Daondi Arail, Prayagraj, Prayagraj (RERA ID UPRERAPRJ221486). Registered with a completion deadline of 29 Jan 2028.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
9.9%Q3'25
12.5%Q4'25
15.94%Q1'26
17.56%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ221486
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAllahabad Development Authority
Proposed start1 Feb 2024
Project duration48 months
AddressArazi No. 43MI and 41/1 having H No. 536/221 Chak Daondi Arail, Prayagraj, Chak Daondi Arail, Prayagraj, Karchhana, Prayagraj
TehsilKarchhana
Applicant typeLimited Liability Partnership (LLP)
Applicant addressArazi No. 5, Chak Dondi, Allahabad Uttar Pradesh - 211008
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Affordable Housing/02601/PDA/BP/22-23/0022/27062023

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered27 May 2024
Original completion29 Jan 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹38,000
Sanctioning authorityAllahabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors181 · 1 · 13 (units from plan)
  • 2 BHK103 57%
  • 3 BHK78 43%
ConfigurationUnitsCarpet area
3 BHK7888-91
2 BHK10371-72
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
1 · 3 BHK, 2 BHK1318171-91
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Shiarpit Katoch
License CA/1999/25542
S-6, Second Floor, Ashirwad Complex, Block No F, Secor 53, Noida Ut Pradesh - 201301
Engineer
D & R Consultant
100A, 3rd Floor, harat nagar, Nefriends Colony, New Delhi - 110025
Contractor
Self
26-B Strachy Road, Civil Lines, Prayagraj
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot of size 6592.00 sq. mtr.having 1 main entrance gate from the 18 m wide front road.
2Boundary Wall
2 m high and 230 mm thick Brick work and rcc work in column and beam. At the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick /RCC road through out the project. Whose wideness starts from 10 mtr.
4Footpaths
We would not provide any footpath
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of pump for the requirement of blocks through underground pipelines.
6Sewer System
All Sewerage water shall be go through the sewer lines and shall be connected with the Municipal sewerage system.
7Drain
Storm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
We will provide green area with the different activities and the green area will have gaming facilities for kids.
9Tree Planting
We will provide many type of trees all along the boundary wall & green area
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer, HT panel, LT Panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP, Pump room etc.
11Community Buildings
We will provide community hall as sanctioned in the Map
12Treatment and Disposal System of Sewage and Sullage water
All Sewerage water shall be go through the sewer lines and shall be connected with the Municipal sewerage system.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
This Project has only Residential flats. Hence we will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We will have staircases which will be provided with emergency exit doors and emergency exit gates
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Jan 2029.

Sanctioned by Allahabad Development Authority · 6,592 sqm of land · an approved plan of 1 block and 181 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Affordable Housing/02601/PDA/BP/22-23/0022/2706202330 Jan 202429 Jan 202929 Jan 203229 Jan 2028
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

22 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
41/1, 436592Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 6137
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 1372
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Apr 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New29 Mar 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New29 Mar 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New29 Mar 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New30 Apr 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New2 Mar 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New2 Mar 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New2 Mar 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New16 Apr 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New16 Apr 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New16 Apr 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New16 Apr 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New29 Mar 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New29 Mar 2024 ↗

Quarterly progress reports

10 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

10 quarterly progress reports are on file with UPRERA, covering 2023-Q4 to 2026-Q1.

QuarterConstructionCertificates
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q29.9%CA ↗ · Arch ↗ · Eng ↗
2025-Q312.5%CA ↗ · Arch ↗ · Eng ↗
2025-Q415.94%CA ↗ · Arch ↗ · Eng ↗
2026-Q117.56%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMAHALAKSHMI APARTMENTS LLP
RolePromoter · current
RERA IDUPRERAPRM276899
PANABXFM3116F
CIN / TANALDM05355A
Registered addressArazi No. 5, Chak Dondi, Allahabad Uttar Pradesh - 211008
RERA contact
Registered since2024
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameVISHAL CHAWLA
RoleCo-promoter
Applicant typeIndividual
Address161/116 Dharbhanga Colony Prayagraj 211003
RERA contact

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
M/S. M.A.LLP-COLL A/C MAHALAKSHMI APARTMENTSBankHDFC BANK LTDBranchCivil Lines, PrayagrajBranch address18-A, SP Marg, Civil Lines, Prayagraj, 211001Branch districtPrayagrajA/C no.IFSCHDFC0000226Branch emailshubham.agarwal@hdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
M/S. M.A.LLP-SPT A/C MAHALAKSHMI APARTMENTSBankHDFC BANK LTDBranchCivil Lines, PrayagrajBranch address18-A, SP Marg, Civil Lines, Prayagraj, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCHDFC0000226
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
M/S. M.A.LLP-TRN A/C MAHALAKSHMI APARTMENTSBankHDFC BANK LTDBranchCivil Lines, PrayagrajBranch address18-A, SP Marg, Civil Lines, Prayagraj, 211001Branch districtPrayagraj, Uttar PradeshA/C no.IFSCHDFC0000226
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Mahalakshmi Apartments

Is Mahalakshmi Apartments RERA registered?

Yes. Mahalakshmi Apartments is registered with UPRERA under registration number UPRERAPRJ221486, registered on 27 May 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Mahalakshmi Apartments?

The completion date filed with UPRERA is 29 Jan 2028. No completion certificate is on record yet.

Who is the builder of Mahalakshmi Apartments?

MAHALAKSHMI APARTMENTS LLP is the promoter entity that filed Mahalakshmi Apartments with UPRERA (promoter RERA ID UPRERAPRM276899). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Mahalakshmi Apartments have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Mahalakshmi Apartments located?

Mahalakshmi Apartments is registered in Chak Daondi Arail, Prayagraj, Prayagraj, as filed with UPRERA.

What configurations are available in Mahalakshmi Apartments?

The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Mahalakshmi Apartments?

The approved unit plan filed with UPRERA runs from 71 to 91 m² of carpet area (about 764 to 982 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Mahalakshmi Apartments?

The approved unit plan describes 1 block and 181 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Mahalakshmi Apartments?

About 111 units per acre: 181 planned units across 1.63 acres (6,592 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗