Timeline Bar
Registered30 Aug 2017
Promised20 Jan 2020
Completed20 Dec 2024
Timeline
Promised completion20 Jan 2020
Revised completion20 Jan 2020
Actual completion20 Dec 2024
Possession delay59 mo delay
Registration & Cost Details
Registration fee (in ₹)₹77,500
Project cost (in ₹ Lakhs)₹555 Lakhs
Project duration60 months
Project categoryResidential
Locality—
Original start date21 Jan 2015
Proposed start date21 Jan 2015
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeIndividual
Mobile7417351268
EmailASHOKTYAGIMEERUT@GMAIL.COM
Coordinator9927961342
Address162/7 shastri nagar meerut.
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 24/13 | 21 Jan 2015 | 20 Jan 2020 | 20 Jan 2020 | 31 Dec 2024 |
| 24/13 | 21 Jan 2015 | 20 Jan 2020 | 20 Jan 2020 | 31 Dec 2024 |
| 24/13 | 21 Jan 2015 | 20 Jan 2020 | 20 Jan 2020 | 31 Dec 2024 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 401/1 | 15385 | Khasra |
Frequently Asked Questions
What is the RERA registration number of MEERUT RESIDENCY?
The RERA registration number of MEERUT RESIDENCY is UPRERAPRJ12508, as recorded on the UP-RERA portal.
What is the RERA status of MEERUT RESIDENCY?
As reported by UP-RERA, the status of MEERUT RESIDENCY is "Registered".
Where is MEERUT RESIDENCY located?
As reported to UP-RERA, MEERUT RESIDENCY is located at Meerut, Meerut, Uttar Pradesh.
Is MEERUT RESIDENCY completed?
As reported to UP-RERA, MEERUT RESIDENCY was completed on 20 Dec 2024.
Is MEERUT RESIDENCY delayed?
Measured against the latest completion date reported to UP-RERA, MEERUT RESIDENCY is 59 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.