Midtown Home is a RERA-registered residential project by M/s OM DEVELOPERS in Amroha (RERA ID UPRERAPRJ936952). Registered with a completion deadline of 15 Mar 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
99.47%Q3'25
99%Q4'25
100%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ936952
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAny Other Competent Authority
Proposed start1 Oct 2021
Project duration54 months
AddressAmroha, Amroha
TehsilAmroha
Applicant typePartnership Firm
Applicant addressNEAR BUS STAND, JOYA ROAD, AMROHA,Amroha,244221
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    420-106/2017

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  6. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Nov 2021
Original completion15 Mar 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary30 Apr 2026
Registration fee₹24,500
Sanctioning authorityAny Other Competent Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors76 · 1 · 8 (units from plan)
  • 2 BHK60 79%
  • 3 BHK16 21%
ConfigurationUnitsCarpet area
2 BHK6076
3 BHK16104
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block B · 2 BHK, 3 BHK87676-104
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Jaswant Singh
License CA/04/34670
Jigar Colony Road, Opp. Poultary Farm, Moradabad (U.P.)
Engineer
Kamal Sabarwal
HS-25, 2nd Floor Kailash Colony Market, New Delhi - 110048
Contractor
Mr. Shahadat S.O Barkat Ali
Bareilly Gate, Rampur 244901
Sr.Development work declared to RERA
1Demarcation of Plots
Total plot area is 6420.72 sq.mtr. (Net plot area after road widening -5870.46 sq.mtr. ) plot is bifurcated approved by regulatory body in two parts , 1- commercial area-2051.32 sq. mtr. , 2- residential area -3819.14 sq.mtr.
2Boundary Wall
2.50 mtr. high and 230 mm thick brickwork rcc work in column and beam. At the center face of boundary wall there would be a Logo of Om Developers which give a beautiful iconic design to boundary wall.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick road through out the project. Whose wideness starts from 12mtr.
4Footpaths
N.A.
5Water Supply Including Drinking Water Facilities
We will provide two no of pump for the requirement of township through underground pipelines and over head storage tank.
6Sewer System
Inspection chamber ,septic tank shall be connect with the Municipal sewerage drains.
7Drain
Storm water shall be provided . Storm water from roads and other landscape area shall be connect to the storm water drain channel and go to the rain water harvesting pit for recharge
8Parks
We will provide green area with the different activities and the green area will have gaming facilities for kids.
9Tree Planting
We will provide 200 nos many type of trees all along the boundary wall and green area
10Design For Electric Supply Including Street Lighting
We will design and implement the system as per local electricity board and will consider Transformer, HT panel, LT panel, Feeder pillar, and DG back for common service like External Lighting , Fountain , Pump room etc.
11Community Buildings
N.A.
12Treatment and Disposal System of Sewage and Sullage water
Modular sewerage system shall be provided. All sewerage water shall go to the septic tank and overflow from the septic tank shall be connect with the Municipal sewerage lines.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggested to individual to use low flow fixtures as well dual flush cistern to reduce the water consumption and provide water harvesting system to improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In pump room also all the equipment shall have energy efficient motor. and we will suggest to individual also to use.
16Fire Protection And Fire Safety System
This project have only residential flats. Hence we have provide Fire fighting facility in common areas while individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A.
18Emergency Evacuation Services
Open area are provided for mass gathering during fire break and stair case directly open in these area.
19Other Miscellaneous Work
N.A.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 16 Mar 2026.

Sanctioned by Any Other Competent Authority · 3,819 sqm of land · an approved plan of 1 block and 76 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
420-106/201717 Mar 202116 Mar 202616 Mar 202915 Mar 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
3344, 3344/1, 33463819.137Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 1830
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3148
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3590
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6121
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7588
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 15982
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · 11711
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1426-1431
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Additional Documents w.r.t. Land
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New29 Oct 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New12 Oct 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New12 Oct 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New12 Oct 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New12 Oct 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New12 Oct 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New12 Oct 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New12 Oct 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New28 Oct 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New12 Oct 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 Oct 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New28 Oct 2021 ↗

Quarterly progress reports

18 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

18 quarterly progress reports are on file with UPRERA, covering 2021-Q3 to 2025-Q4.

QuarterConstructionCertificates
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q299.47%CA ↗ · Arch ↗ · Eng ↗
2025-Q399%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameM/s OM DEVELOPERS
RolePromoter · current
RERA IDUPRERAPRM84957
PANAAFFO0629N
CIN / TANLKNO05771D
Registered addressNEAR BUS STAND, JOYA ROAD, AMROHA,Amroha,244221
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameDHEERAJ KHURANA
RoleCo-promoter
Applicant typeIndividual
Address22 Pushpanjali kanth road moradabad 244001
RERA contact
Legal nameDHARAM CHAND KHURANA
RoleCo-promoter
Applicant typeIndividual
Address22 Pushpanjali kanth road moradabad 244001
RERA contact
Legal nameSAVITRI KHURANA
RoleCo-promoter
Applicant typeIndividual
Address22 Pushpanjali kanth road moradabad 244001
RERA contact

Nearby projects

Amroha

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Om Developers Collection Account for Midtown HomeBankState Bank of IndiaBranchJat Bazar, AmrohaBranch addressJat Bazar, AmrohaBranch districtAmroha, Uttar PradeshA/C no.IFSCSBIN0000610Branch emailsbi.00610@sbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Om Developers Separate Account For Midtown HomeBankState Bank of IndiaBranchJat Bazar, AmrohaBranch addressJat Bazar, AmrohaBranch districtAmroha, Uttar PradeshA/C no.IFSCSBIN0000610Branch emailsbi.00610@sbi.co.in
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Om Developers RERA Transaction Account for Midtown HomeBankState Bank of IndiaBranchJat Bazar, AmrohaBranch addressJat Bazar, AmrohaBranch districtAmroha, Uttar PradeshA/C no.IFSCSBIN0000610Branch emailsbi.00610@sbi.co.in
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Midtown Home

Is Midtown Home RERA registered?

Yes. Midtown Home is registered with UPRERA under registration number UPRERAPRJ936952, registered on 3 Nov 2021. Estanzo reproduces that filing; it does not verify the work behind it.

Has Midtown Home been completed?

UPRERA still lists Midtown Home as Registered, so it is not shown as completed here. A completion certificate dated 30 Apr 2026 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Midtown Home?

M/s OM DEVELOPERS is the promoter entity that filed Midtown Home with UPRERA (promoter RERA ID UPRERAPRM84957). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Midtown Home have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Midtown Home located?

Midtown Home is registered in Amroha, as filed with UPRERA.

What configurations are available in Midtown Home?

The unit plan filed with UPRERA lists 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Midtown Home?

The approved unit plan filed with UPRERA runs from 76 to 104 m² of carpet area (about 815 to 1,124 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Midtown Home?

The approved unit plan describes 1 block and 76 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Midtown Home?

About 81 units per acre: 76 planned units across 0.94 acres (3,819 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.