Estanzo

Timeline Bar

Registered29 Jul 2017
Promised31 Dec 2024
Today4 Aug 2026

Timeline

Promised completion31 Dec 2024
Revised completion31 Dec 2024
Actual completion
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹55,000
Project cost (in ₹ Lakhs)₹11,528 Lakhs
Project duration138 months
Project categoryResidential
Locality
Original start date1 Jan 2013
Proposed start date1 Jan 2014

Inventory

Total units399876
Unit TypeUnitsCarpet Area (sqm)
3 BHK21095176.593–77.73
OTHER18892582.71–84.48

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8586928776
Emailrera_2017@imperiastructures.in
Coordinator964303550/011-46469999
AddressA-25, Mohan Co-operative Industrial Estate Mathura Road, New Delhi-110044

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
YEA/Niyojan/BP-15/9148 May 20147 May 201931 Dec 202431 Dec 2024

Land Parcels

Khasra No.AreaPlot Type
GH-F39993
GH-F320234Plot

Approved Unit Plan

Unit plan rows on file314
Total flats (sum of rows)399876
Blocks4, 5, 6
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
108643 May 2013
108643 May 2013

Frequently Asked Questions

What is the RERA registration number of Mirage Phase II?

The RERA registration number of Mirage Phase II is UPRERAPRJ4008, as recorded on the UP-RERA portal.

What is the RERA status of Mirage Phase II?

As reported by UP-RERA, the status of Mirage Phase II is "Registered".

Where is Mirage Phase II located?

As reported to UP-RERA, Mirage Phase II is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Mirage Phase II be completed?

The latest completion date reported to UP-RERA for Mirage Phase II is 31 Dec 2024.

Is Mirage Phase II delayed?

Measured against the latest completion date reported to UP-RERA, Mirage Phase II is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026