Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ10020
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAligarh Development Authority
Proposed start1 Jul 2015
Original start1 Jul 2015
Project duration97 months
AddressKoil, Aligarh
TehsilKoil
Applicant typeCompany
Applicant address38-4B/1F,FRIENDS CENTER,SANJAY PLACE,AGRA -282002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  2. 2 building permits sanctioned

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. valid to

    Permit revalidated

    860/15/14-15/ada/2020

  7. to

    Extension granted

  8. to

    Extension granted

  9. to

    Extension granted

  10. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered13 Aug 2017
Original completion30 Jun 2020
Revised completion16 Jul 2023
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹63,500
Sanctioning authorityAligarh Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors242 · 2 · 17 (units from plan)
  • 3 BHK177 73%
  • 2 BHK39 16%
  • 4 BHK26 11%
ConfigurationUnitsCarpet area
4 BHK26120
3 BHK17793-94
2 BHK3965-68
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER A · OTHER, 4 BHK, 3 BHK, 2 BHK1711268-120
TOWER B · OTHER, 2 BHK, 3 BHK1713065-93
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
PIYUSH AGARWAL
License CA/2009/46059
H-25 2ND FLOOR GREEN PARK EXTENSION NEW DELHI-16
Engineer
PARESH JAUHRI
20 CENTRAL LANE BABAR ROAD NEW DELHI-01
Contractor
SELF
SANJAY PLACE AGRA
Sr.Development work declared to RERA
1Demarcation of Plots
PLOT IS DEMARCATED AS PER GIVEN DRAWING
2Boundary Wall
BOUNDARY WALL 7 FEET HEIGHT IN BRICKWORK
3Road Work
INTERLOCKING TILES
4Footpaths
INTERLOCKING TILES
5Water Supply Including Drinking Water Facilities
SUPPLY BY NAGAR NIGAM
6Sewer System
SEWAR LINE AVAILABLE
7Drain
BRICK WORK DRAIN
8Parks
WELL MAINTAINED GREEN AREA
9Tree Planting
DECORATIVE PLANT AND TREES ALONG THE BOUNDARY
10Design For Electric Supply Including Street Lighting
POWER SUPPLY THROUGH DVVNL ,AN ADDITIONAL POWER BACKUP THROUGH GENSET/ LED LIGHTING
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
GOVERNMENT SEWERAGE SYSTEM
13Solid Waste Management And Disposal System
NA
14Water Conservation System
RAIN WATER HARVESTING
15Energy Management System Including Use of Renewable Energy
LED LIGHTING WITH SOLAR PANELS WHEREVER FEASIBLE
16Fire Protection And Fire Safety System
ACCORDING TO FIRE SAFETY NORMS
17Social Infrastructure And Other Public Amenities Including Public Health Services
CHILDERN PLAY AREA AND GREEN AREA
18Emergency Evacuation Services
EMERGENCY STAIRCASE
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1BALAJI PROPERTIES & ARCADE PRIVATE LIMITEDUPRERAAGT11143
2SPN PROPMART LLPUPRERAAGT10604
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

2 permits

An approval and the date it runs to - not proof the work matching it was done.

2 sanctioning permits are on record with UPRERA, the latest valid to 17 Jul 2020. 1 of them carries a revalidation, valid to 16 Jul 2023.

Sanctioned by Aligarh Development Authority · 11,700 sqm of land · an approved plan of 2 blocks and 242 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
860/15/14-15/ADA17 Jul 201517 Jul 202016 Jul 202316 Jul 2023—
860/15/14-15/ADA17 Jul 201516 Jul 202016 Jul 202316 Jul 20235 Oct 2020
valid to 16 Jul 2023
as 860/15/14-15/ada/2020
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 4 completion extensions for this project, the latest running to 16 Jul 2023.

#Granted fromExtended uptoNote
130 Jun 202029 Dec 2020Six months extension in view of force majeure caused by covid-19 pandemic
229 Dec 202028 Dec 2021—
328 Dec 202127 Jun 2022—
427 Jun 202216 Jul 2023—

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
2328 MAUZA KOIL5070—
2329 MAUZA KOIL4720—
2342 MAUZA KOIL2650—
2328,2329,234211700Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 8 Sept 2014.

Registry no.DateTypeArea
235/4(2014-15)8 Sept 2014other—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · 799/S.V./N.N.A/2020-21
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New6 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Agreement for other land
The agreement under which the promoter is developing land it does not own - worth reading for who actually holds the title.
Old12 Aug 2017 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old12 Aug 2017 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old12 Aug 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAS PER PLAN
Fire safety (as filed with RERA)AS PER PLAN
Health serviceAS PER PLAN
Renewable energyAS PER PLAN
Other facilitiesIF REQUIRED

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

14 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

14 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Eng ↗
2022-Q3—CA ↗ · Eng ↗
2022-Q4—CA ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameKUSHAGR INFRA DEVELOPERS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM8510
PANAAJCS3855R
CIN / TANU93020UP2005PTC030937
Name of chairmanRAVINDRA KUMAR AGARWAL
Registered address38-4B/1F,FRIENDS CENTER,SANJAY PLACE,AGRA -282002
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Aligarh

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
KUSHAGR INFRA DEVELOPERS PVT LTD ESCROW ACCOUNTBankCANARA BANKBranchKAMLA NAGARA/C no.IFSCCNRB0001469
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about NAGAR NIGAM SKY TOWER

Is NAGAR NIGAM SKY TOWER RERA registered?

Yes. NAGAR NIGAM SKY TOWER is registered with UPRERA under registration number UPRERAPRJ10020, registered on 13 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for NAGAR NIGAM SKY TOWER?

The completion date filed with UPRERA is 16 Jul 2023. No completion certificate is on record yet.

Who is the builder of NAGAR NIGAM SKY TOWER?

KUSHAGR INFRA DEVELOPERS PRIVATE LIMITED is the promoter entity that filed NAGAR NIGAM SKY TOWER with UPRERA (promoter RERA ID UPRERAPRM8510). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted NAGAR NIGAM SKY TOWER more time to complete?

UPRERA's record carries 4 completion extensions for NAGAR NIGAM SKY TOWER, the latest running to 16 Jul 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does NAGAR NIGAM SKY TOWER have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is NAGAR NIGAM SKY TOWER located?

NAGAR NIGAM SKY TOWER is registered in Aligarh, as filed with UPRERA.

What configurations are available in NAGAR NIGAM SKY TOWER?

The unit plan filed with UPRERA lists OTHER, 4 BHK, 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in NAGAR NIGAM SKY TOWER?

The approved unit plan filed with UPRERA runs from 65 to 120 m² of carpet area (about 704 to 1,294 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in NAGAR NIGAM SKY TOWER?

The approved unit plan describes 2 blocks and 242 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is NAGAR NIGAM SKY TOWER?

About 84 units per acre: 242 planned units across 2.89 acres (11,700 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗