Estanzo

Timeline Bar

Registered17 Jan 2018
Promised30 Jun 2018
Completed12 Nov 2021

Timeline

Promised completion30 Jun 2018
Revised completion30 Jun 2018
Actual completion12 Nov 2021
Possession delay40 mo delay

Registration & Cost Details

Registration fee (in ₹)₹18,500
Project cost (in ₹ Lakhs)₹100 Lakhs
Project duration6 months
Project categoryResidential
Locality
Original start date
Proposed start date17 Jan 2018

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9997366666
Emailvibhuaryav@gmail.com
Coordinator9997366666
Address174, VIP COLONY RAHE RAZA, RAMPUR

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
025 Nov 201622 Nov 202130 Jun 201822 Nov 2021

Land Parcels

Khasra No.AreaPlot Type
756/2900 METRE
754/235 METRE
7551690 METRE
7551690Khasra
756/2, 754/2935Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
6298/798729 Nov 2014
6969/1938 Jan 2016

Frequently Asked Questions

What is the RERA registration number of NEW CIVIL LINES, PHASE 1?

The RERA registration number of NEW CIVIL LINES, PHASE 1 is UPRERAPRJ14907, as recorded on the UP-RERA portal.

What is the RERA status of NEW CIVIL LINES, PHASE 1?

As reported by UP-RERA, the status of NEW CIVIL LINES, PHASE 1 is "Registered".

Where is NEW CIVIL LINES, PHASE 1 located?

As reported to UP-RERA, NEW CIVIL LINES, PHASE 1 is located at Rampur, Rampur, Uttar Pradesh.

Is NEW CIVIL LINES, PHASE 1 completed?

As reported to UP-RERA, NEW CIVIL LINES, PHASE 1 was completed on 12 Nov 2021.

Is NEW CIVIL LINES, PHASE 1 delayed?

Measured against the latest completion date reported to UP-RERA, NEW CIVIL LINES, PHASE 1 is 40 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 4 Aug 2026