NMBPL TOWERUPRERADelayed 37 mo
Home › Projects › Lucknow › NMBPL TOWER

NMBPL TOWER

UPRERADelayed 37 moRegisteredConstruction 36% · 2025 Q3updated 4 Aug 2026

NMBPL TOWER is a RERA-registered real-estate project in Lucknow (RERA ID UPRERAPRJ581302). Its RERA-registered completion deadline (30 Jun 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
▲
37 months past deadline — no completion certificate on record, including the extension already granted.
Project cost
₹71
Land area
not reported
Units (from plan)
195
Density (derived)
not reported
Towers
not reported
Config
1 BHK/SHOP/STUDIO/OTHER
Carpet
190–398
Registered
26 Mar 2019

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2025 Q3
—Q4'23
—Q1'24
—Q2'24
—Q3'24
—Q4'24
—Q1'25
36%Q2'25
36%Q3'25

Basic details

RERA IDUPRERAPRJ581302
Applicant typeCompany
Project categoryCommercial
Project typeother
RERA statusRegistered
Proposed start1 Jan 2019
Project duration84
AddressMalihabad, Lucknow

Registration & timeline

RERA registered26 Mar 2019
Promised completion31 Dec 2022
Revised completion30 Jun 2023
Completion certificate filed— not on record
Registration fee₹35,000

Inventory

derived from unit plan
Total units · towers · floors195 · 1 · 17 (units from plan)
195units
  • STUDIO110 56%
  • 1 BHK55 28%
  • OTHER20 10%
  • SHOP10 5%
ConfigurationUnitsCarpet area
SHOP10190
OTHER20292–398
STUDIO110201
1 BHK55203
Towers as filedNMBPL Tower
Unit counts derived from the approved unit plan, which RERA files as a row per block and floor — the block names are the project's towers, and the authority publishes no separate tower count. Floors counts the distinct levels the plan describes, not the height of any one tower. RERA does not publish a live units-sold figure either, so no “% sold” is shown.

Permits & extensions

5 permits
Permit no.DateValid uptoRevised end
3881421 Sept 201520 Sept 202031 Dec 2022
4142823 Feb 201722 Feb 202230 Jun 2023
4142823 Feb 201722 Feb 202230 Jun 2023
4142823 Feb 201722 Feb 202230 Jun 2023
4142823 Feb 201722 Feb 202230 Jun 2023

Land & documents

4 filings
KhasraAreaType
21P411.66Khasra
20P603.58Khasra
19P791.65Khasra
18P329.98Khasra

Quarterly progress reports

23 filed reports
QuarterConstructionCertificatesSource
2020-Q1—CA · Arch · Engview ↗
2020-Q2—CA · Arch · Engview ↗
2020-Q3—CA · Arch · Engview ↗
2020-Q4—CA · Arch · Engview ↗
2021-Q1—CA · Arch · Engview ↗
2021-Q2—CA · Arch · Engview ↗
2021-Q3—CA · Arch · Engview ↗
2021-Q4—CA · Arch · Engview ↗
2022-Q1—CA · Arch · Engview ↗
2022-Q2—CA · Arch · Engview ↗
2022-Q3—CA · Arch · Engview ↗
2022-Q4—CA · Arch · Engview ↗
2023-Q1—CA · Arch · Engview ↗
2023-Q2—CA · Arch · Engview ↗
2023-Q3—CA · Arch · Engview ↗
2023-Q4—CA · Arch · Engview ↗
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q236%CA · Arch · Engview ↗
2025-Q336%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q3.

Nearby projects

Lucknow

Other projects registered in Lucknow.

UPRERA no delay on record
UPRERA no delay on record
1OAK NATURA
UPRERA ▲ 6 mo
48 Nos. EWS Houses in Sec-7A at Awadh Vihar Yojna, Lucknow
UPRERA ▲ 59 mo
72 SUGAM AWAS RASHMIKHAND
UPRERA ▲ 88 mo
7th Avenue
UPRERA ▲ 29 mo

Common questions about NMBPL TOWER

Is NMBPL TOWER RERA registered?

Yes. NMBPL TOWER is registered with UPRERA under registration number UPRERAPRJ581302, registered on 26 Mar 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Is NMBPL TOWER delayed?

NMBPL TOWER is 37 months past the completion date filed with UPRERA (30 Jun 2023), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.

Where is NMBPL TOWER located?

NMBPL TOWER is registered in Lucknow, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusDelayed 37 mo
QPR filingNo default reported
DistrictLucknow
Last updated4 Aug 2026

Location

AddressLucknow
View on map ↗

RERA buyer helpline

Coordinator8800918677
official grievance contact, as published by RERA
Generated from Estanzo (estanzo.com) · Source: UPRERA public filings (https://www.up-rera.in/Projectsummary?UI0aPA1ISD=gwOHBaLL4GU=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=qZX+whmrahod9xg+oOsBuQ==&PaURJEMAN4=ZL9MNERkNdZ6TbgNPO9V7g==&IRSAHEB=D6PY3lyims8=)