NU Phase-1 is a RERA-registered residential project by Paarth Infrabuild Private Limited in Lucknow (RERA ID UPRERAPRJ3492). Registered with a completion deadline of 30 Jun 2026.
RERA status as reported: Registered.Construction progress
Construction stayed at 16% across 4 consecutive filed quarters (Jul–Sep 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ3492 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 5 Dec 2013 |
| Original start | 5 Dec 2013 |
| Project duration | 151 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Company |
| Applicant address | Flat Number 311-315, 3rd floor,Naurang House,Kasturba Gandhi Marg, New-Delhi-110001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Building permit sanctioned
37617
Permit revalidated
38814
3 building permits sanctioned
Permit revalidated (2)
Registered with RERA
- valid to
Permit revalidated
38884
Building permit sanctioned
38884
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 10 Aug 2017 |
| Original completion | 21 Jan 2022 |
| Revised completion | 30 Jun 2026 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹41,500 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- STUDIO152 58%
- 1 BHK111 42%
| Configuration | Units | Carpet area |
|---|---|---|
| STUDIO | 152 | 26 |
| 1 BHK | 111 | 39 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Tower 1 · STUDIO, 1 BHK, OTHER | 23 | 263 | 26-39 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots As per approval from competent authority |
| 2 | Boundary Wall as per approved plan |
| 3 | Road Work cement concerete/bituminous road network |
| 4 | Footpaths as per by law |
| 5 | Water Supply Including Drinking Water Facilities water supply as per requirement provided |
| 6 | Sewer System provosion as per by law |
| 7 | Drain provsion as per by law |
| 8 | Parks provided as per approved plan |
| 9 | Tree Planting provsion as per by law |
| 10 | Design For Electric Supply Including Street Lighting provoision as per by law |
| 11 | Community Buildings as per approved plan |
| 12 | Treatment and Disposal System of Sewage and Sullage water provision as per by law |
| 13 | Solid Waste Management And Disposal System provision as per by law |
| 14 | Water Conservation System provision as per by law |
| 15 | Energy Management System Including Use of Renewable Energy provision as per by law |
| 16 | Fire Protection And Fire Safety System provision asper by law |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services provision as per by law at township level |
| 18 | Emergency Evacuation Services provosion as per by law |
| 19 | Other Miscellaneous Work all necessary facilities provided as per by law |
Registered agents
5 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
| 2 | PROPSHOP | UPRERAAGT10129 |
| 3 | RANVEER PROPERTIES | UPRERAAGT10234 |
| 4 | SDR INFRA BUILD PVT LTD | UPRERAAGT11062 |
| 5 | Varun Properties Inc. | UPRERAAGT11985 |
Permits & extensions
5 permits
An approval and the date it runs to - not proof the work matching it was done.
5 sanctioning permits are on record with UPRERA, the latest valid to 20 Sept 2020. 4 of them carry a revalidation, the latest valid to 2 Apr 2025.
Sanctioned by Lucknow Development Authority · 7,241 sqm of land · an approved plan of 1 block and 263 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 37617 | 27 Jan 2015 | 20 Sept 2020 | 20 Sept 2023 | 21 Jan 2022 | — | |
| 38814 | 21 Sept 2015 | 20 Sept 2020 | 20 Sept 2023 | 21 Jan 2022 | 21 Sept 2015 | |
| 38814 | 21 Sept 2015 | 20 Sept 2020 | 21 Feb 2025 | 21 Feb 2022 | 23 Feb 2017 valid to 22 Feb 2022 as 41248 | |
| 38814 | 21 Sept 2015 | 20 Sept 2020 | 21 Feb 2025 | 21 Feb 2022 | 23 Feb 2017 valid to 22 Feb 2022 as 41248 | |
| 38884 | 21 Sept 2017 | 20 Sept 2020 | 2 Apr 2029 | 31 Dec 2023 | 21 Sept 2017 valid to 2 Apr 2025 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Sanctioned layout plan The approved layout of the whole site: where the towers, roads and open areas sit on the plot. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
| Floor plans of all unit types The approved plan of each unit type, which is what a carpet-area figure is measured from. | PDF ↗ |
UPRERA’s record carries 3 completion extensions for this project, the latest running to 30 Jun 2026.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 21 Jan 2022 | 20 Jul 2022 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 20 Jul 2022 | 31 Dec 2023 | — |
| 3 | 31 Dec 2023 | 30 Jun 2026 | — |
Land & documents
28 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 181 | 620 | — |
| 182 | 921 | — |
| 183 | 1200 | — |
| 18 | 2100 | — |
| 19 | 1200 | — |
| 20 | 1200 | — |
| 181 | 620 | Khasra |
| 182 | 921 | Khasra |
| 183 | 1200 | Khasra |
| 18 | 2100 | Khasra |
| 19 | 1200 | Khasra |
| 20 | 1200 | Khasra |
4 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 20 Nov 2013.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 40903 | 20 Nov 2013 | self | — |
| 40904 | 20 Nov 2013 | self | — |
| 40905 | 20 Nov 2013 | self | — |
| 40906 | 20 Nov 2013 | self | — |
| Khatauni extract · 1418-1423 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Registry document · 19 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 29 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · ---- The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 5 Jul 2018 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 5 Jul 2018 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 5 Jul 2018 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 5 Jul 2018 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 31 Dec 2018 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 5 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 5 Jul 2018 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 5 Jul 2018 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 5 Jul 2018 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 5 Jul 2018 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 28 Jul 2017 ↗ |
| Registry document (own land) The registered deed for land the promoter holds itself, rather than under an agreement with a landowner. | Old | 13 Oct 2017 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | Old | 19 Dec 2017 ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | provided as per building byelaws |
| Fire safety (as filed with RERA) | provided as per building byelaws |
| Health service | provided as per building byelaws |
| Renewable energy | provided as per building byelaws |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
25 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 16% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 16% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 16% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 16% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Paarth Infrabuild Private Limited |
| Role | Promoter · current |
| RERA ID | UPRERAPRM1883 |
| PAN | AAECP0249B |
| CIN / TAN | U70109DL2006PTC152197 |
| Name of chairman | Anubha Yadav |
| Registered address | Flat Number 311-315, 3rd floor,Naurang House,Kasturba Gandhi Marg, New-Delhi-110001 |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | PAARTH INFRABUILD PVT LTDBankHDFC BankBranchHDFC BANK LimitedA/C no.IFSCHDFC0000584 |
What has changed on this record
9 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Promoter’s complaints tally (all their projects) | 449 (Under Registration - 4 ) → 452 (Under Registration - 7 ) changed in Estanzo’s record | 11 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 449 (Under Registration - 5 ) → 449 (Under Registration - 4 ) changed in Estanzo’s record | 1 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 448 (Under Registration - 4 ) → 449 (Under Registration - 5 ) changed in Estanzo’s record | 21 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 447 (Under Registration - 3 ) → 448 (Under Registration - 4 ) changed in Estanzo’s record | 17 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 446 (Under Registration - 2 ) → 447 (Under Registration - 3 ) changed in Estanzo’s record | 15 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 446 (Under Registration - 3 ) → 446 (Under Registration - 2 ) changed in Estanzo’s record | 7 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 445 (Under Registration - 3 ) → 446 (Under Registration - 3 ) changed in Estanzo’s record | 23 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 445 (Under Registration - 4 ) → 445 (Under Registration - 3 ) changed in Estanzo’s record | 16 Aug 2026 |
| Promoter’s complaints tally (all their projects) | 444 (Under Registration - 3 ) → 445 (Under Registration - 4 ) changed in Estanzo’s record | 10 Aug 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 11 Oct 2026 · 9 movements on record |
Common questions about NU Phase-1
Is NU Phase-1 RERA registered?
Yes. NU Phase-1 is registered with UPRERA under registration number UPRERAPRJ3492, registered on 10 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for NU Phase-1?
The completion date filed with UPRERA is 30 Jun 2026. No completion certificate is on record yet.
Who is the builder of NU Phase-1?
Paarth Infrabuild Private Limited is the promoter entity that filed NU Phase-1 with UPRERA (promoter RERA ID UPRERAPRM1883). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted NU Phase-1 more time to complete?
UPRERA's record carries 3 completion extensions for NU Phase-1, the latest running to 30 Jun 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does NU Phase-1 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is NU Phase-1 located?
NU Phase-1 is registered in Lucknow, as filed with UPRERA.
What configurations are available in NU Phase-1?
The unit plan filed with UPRERA lists STUDIO, 1 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in NU Phase-1?
The approved unit plan filed with UPRERA runs from 26 to 39 m² of carpet area (about 276 to 424 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in NU Phase-1?
The approved unit plan describes 1 block and 263 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is NU Phase-1?
About 147 units per acre: 263 planned units across 1.79 acres (7,241 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗