NX ONE

UPRERARegistered

NX ONE is a RERA-registered commercial project by S.P.SAI.IT.PVT. LTD in Gautam Budh Nagar (RERA ID UPRERAPRJ4746). Registered with a completion deadline of 25 Nov 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
87%Q3'25
88%Q4'25
90%Q1'26
90%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ4746
Project categoryCommercial
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start1 Jun 2014
Original start1 Jun 2014
Project duration162 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressA-115, Office No-301, Old No.-51, 3rd Floor, Gali No.-1, Vakil Chamber, SHA, Karpur, East Delhi, New Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/(BP)3109/5612

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Completion certificate filed

  7. to

    Extension granted

  8. Permit revalidated (4)

  9. 6 building permits sanctioned

  10. to

    Extension granted

  11. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Aug 2017
Original completion29 Aug 2023
Revised completion25 Nov 2027
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary31 Jan 2024
Registration fee₹9,11,000
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors2,533 · 8 · 22 (units from plan)
Homes · commercial units2,245 · 288 (shops and offices filed in the same plan)
  • OTHER1,977 78%
  • SHOP288 11%
  • 2 BHK268 11%
ConfigurationUnitsCarpet area
SHOP2886-53
OTHER1,97729-39
2 BHK26865-67
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
DOT COM · SHOP, OTHER42896-53
Residential Block-A · 2 BHK176765-67
Residential Block-B · 2 BHK176765-67
Residential Block-C · 2 BHK176765-67
Residential Block-D · 2 BHK176765-67
T2 · OTHER1877429
T3 · OTHER2076039
T4 · OTHER1744239
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 190.91 m² for a SHOP, 602.42 m² for a SHOP, 295.32 m² for a SHOP and 2 other units like them, far outside the rest of that type, so the ranges above leave them out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Ashok Narayan Pandit
License CA/87/10461
E-24, South Extension Part-I, New Delhi
Engineer
Lokesh Kumar Tyagi
10/14 Subhash Nagar, New Delhi
Contractor
Modern Construction Company (Delhi)
902, Akash Deep Building, 26A Barakhamba Road, New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
NA
2Boundary Wall
RCC foundation, RCC columns, RCC beams, brickwork with plastering and painting
3Road Work
Soling and compacting by road roller, PCC with RCC tremix surface
4Footpaths
Soling and compacting by road roller, PCC with chequered/paverred tile
5Water Supply Including Drinking Water Facilities
As per authority norms
6Sewer System
As per authority norms
7Drain
As per authority norms
8Parks
As per landscape plan
9Tree Planting
As per landscape plan
10Design For Electric Supply Including Street Lighting
As per authority norms
11Community Buildings
Clubhouse
12Treatment and Disposal System of Sewage and Sullage water
As per authority norms
13Solid Waste Management And Disposal System
Sewage Treatment Plant as per authority norms
14Water Conservation System
As per authority norms
15Energy Management System Including Use of Renewable Energy
As per authority norms
16Fire Protection And Fire Safety System
As per authority norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per authority norms
18Emergency Evacuation Services
As per authority norms
19Other Miscellaneous Work
As per authority norms
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

2 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1DIVYA KUMARIUPRERAAGT12330
2SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

7 permits

An approval and the date it runs to - not proof the work matching it was done.

7 sanctioning permits are on record with UPRERA, the latest valid to 27 Oct 2029. 4 of them carry a revalidation.

Sanctioned by Greater Noida Authority · 82,327 sqm of land · an approved plan of 8 blocks and 2533 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
PLG/(BP)3109/561230 Aug 201330 Aug 201829 Aug 202329 Aug 2023—
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203428 Feb 202428 Oct 2024
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203428 Feb 202428 Oct 2024
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203428 Feb 2024—
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203428 Feb 2024—
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203426 Nov 202528 Oct 2024
PLG/BP/SM-06-Aug-2024:2213628 Oct 202427 Oct 202926 Oct 203425 Nov 202728 Oct 2024
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Sanctioned building plan
The plan the sanctioning authority approved for each building - what was permitted to be built, and at what height and footprint.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 25 Nov 2027.

#Granted fromExtended uptoNote
129 Aug 202328 Feb 2024Six months extension in view of force majeure caused by covid-19 pandemic
228 Feb 202426 Nov 2025—
326 Nov 202525 Nov 2027—

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
17100020Plot
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

3 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 28 Dec 2011.

Registry no.DateTypeArea
2500228 Dec 2011self—
2500228 Dec 2011self—
2500228 Dec 2011self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Allotment letter from the authority · IND/IT/2008/155
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New29 Jan 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New29 Jan 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Jan 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Jan 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Jan 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New29 Jan 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New5 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New5 Jul 2018 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New24 Jan 2022 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old22 Feb 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old22 Feb 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAuthority supply
Fire safety (as filed with RERA)As per NBC norms

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q287%CA ↗ · Arch ↗ · Eng ↗
2025-Q388%CA ↗ · Arch ↗ · Eng ↗
2025-Q490%CA ↗ · Arch ↗ · Eng ↗
2026-Q190%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameS.P.SAI.IT.PVT. LTD
RolePromoter · current
RERA IDUPRERAPRM2562
PANAAPCS4269P
CIN / TANDELS46221A
Name of chairmanArvind Kumar Singh
Registered addressA-115, Office No-301, Old No.-51, 3rd Floor, Gali No.-1, Vakil Chamber, SHA, Karpur, East Delhi, New Delhi-110092
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
SP SAI IT PVT LTD RERA A/CBankYES BANK LIMITEDBranchYES BANK LIMITEDA/C no.IFSCYESB0000014
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)174 (Under Registration - 3 ) → 174 (Under Registration - 2 )
changed in Estanzo’s record
18 Oct 2026
Promoter’s complaints tally (all their projects)174 (Under Registration - 6 ) → 174 (Under Registration - 3 )
changed in Estanzo’s record
7 Oct 2026
Promoter’s complaints tally (all their projects)173 (Under Registration - 5 ) → 174 (Under Registration - 6 )
changed in Estanzo’s record
29 Sept 2026
Promoter’s complaints tally (all their projects)170 (Under Registration - 2 ) → 173 (Under Registration - 5 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)169 (Under Registration - 1 ) → 170 (Under Registration - 2 )
changed in Estanzo’s record
21 Sept 2026
Promoter’s complaints tally (all their projects)169 (Under Registration - 2 ) → 169 (Under Registration - 1 )
changed in Estanzo’s record
16 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 18 Oct 2026 · 6 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about NX ONE

Is NX ONE RERA registered?

Yes. NX ONE is registered with UPRERA under registration number UPRERAPRJ4746, registered on 1 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has NX ONE been completed?

UPRERA still lists NX ONE as Registered, so it is not shown as completed here. A completion certificate dated 31 Jan 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of NX ONE?

S.P.SAI.IT.PVT. LTD is the promoter entity that filed NX ONE with UPRERA (promoter RERA ID UPRERAPRM2562). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted NX ONE more time to complete?

UPRERA's record carries 3 completion extensions for NX ONE, the latest running to 25 Nov 2027. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does NX ONE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is NX ONE located?

NX ONE is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in NX ONE?

The unit plan filed with UPRERA lists SHOP, OTHER and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in NX ONE?

The approved unit plan filed with UPRERA runs from 6 to 67 m² of carpet area (about 63 to 718 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in NX ONE?

The approved unit plan describes 8 blocks and 2,533 units of which 2,245 are homes and 288 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is NX ONE?

About 125 units per acre: 2,533 planned units across 20.34 acres (82,327 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗