Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
1.41%Q3'25
1.41%Q4'25
1.41%Q1'26
6.12%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ344049
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start8 Jul 2024
Project duration58 months
AddressGroup Housing II, Omaxe Metro City, Lucknow U.P., Kalli Paschim, Sarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant address10, Local Shopping Centre, Kalkaji, New Delhi - 110019, Delhi, INDIA
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    LDA/BP/23-24/4232/26022024

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered10 Jul 2024
Original completion8 Apr 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹72,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors318 · 4 · 13 (units from plan)
  • 3 BHK210 66%
  • 2 BHK108 34%
ConfigurationUnitsCarpet area
3 BHK210106-116
2 BHK10862-85
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower - 3 · 3 BHK13104106-116
Tower - 4 · 3 BHK13106106-116
Tower - 5 · 2 BHK135462-85
Tower - 6 · 2 BHK135462-85
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Apurba Borah
License CA/2013/61818
10, LSC, Kalka ji, New Delhi
Engineer
Sanjeev Jain
I-1738, Lower Ground Floor, CR park New Delhi-19
Contractor
Omaxe Garv Buildtech Pvt Ltd
10 LSC, Kalkaji, New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of project to be done at site.
2Boundary Wall
Boundary wall will be constructed by brick work/MS railing as per requirement and designed by promoter.
3Road Work
Internal drive way 6 mtr wide, will be developed by RCC/Interlocking paver/Bitumen as per approved layout, as per requiremet and designed by promoter.
4Footpaths
Both side of road, Footpath will be developed, width 1.0 to 1.5 mtr, as per requirement and designed by promoter.
5Water Supply Including Drinking Water Facilities
Water supply including drinking water facilities will be provided by promoter through roof tank/bore well.
6Sewer System
Common S.T.P will be constructed by promoter, for GH-2, at site for Sewer disposal.
7Drain
Drainage system will be developed and connected with RWH over flow will be connected with Exiting Drains.
8Parks
Common parks/green area approx 2300 sqm will be planted in GH-2 within parks, road side and boundary, as per requirment and norms.
9Tree Planting
Required Tree approx 100-120 nos, will be planted in GH-2 within parks, road side and boundary, as per requirement and norms.
10Design For Electric Supply Including Street Lighting
Common ESS developed for metrocity township. electric supply will be provided from ESS. Street light wil be fixed at road berms as per requirement and design.
11Community Buildings
Common community building as per approved layout, will be provided for GH-2
12Treatment and Disposal System of Sewage and Sullage water
S.T.P will be constructed for GH-2, and treated water will be use in Irrigation of green areas and as per Govt. norms.
13Solid Waste Management And Disposal System
Solid waste management and disposal system will be provided as per requirement and Govt. norms
14Water Conservation System
water conservation system will be provided as per Govt. Norms
15Energy Management System Including Use of Renewable Energy
Energy management system will be provided as per Govt. Norms
16Fire Protection And Fire Safety System
Fire safety system will be provided as per approval, design Norms
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
As per Norms
19Other Miscellaneous Work
As per specification finalize by approved map all works will be developed.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

3 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 DEGREE VENTURES PRIVATE LIMITEDUPRERAAGT18728
2360 PROP GUIDE LLPUPRERAAGT20190
3360 REALTORS LLPUPRERAAGT10868
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 8 Apr 2029.

Sanctioned by Lucknow Development Authority · 13,481 sqm of land · an approved plan of 4 blocks and 318 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
LDA/BP/23-24/4232/260220249 Apr 20248 Apr 20297 Apr 20328 Apr 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

34 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
6295600Khasra
630520Khasra
2291150Khasra
2293400Khasra
22944920Khasra
22921891Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 15315
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 10504
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 13060
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 14356
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 9096
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1429-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1434
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1434
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1434
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1434
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1434 (630,2291)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Sale deed · 6787
The registered deed by which the promoter bought the land.
PDF ↗
Lease deed · 8611
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Khatauni extract · 1429-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1429-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New27 May 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 Jun 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New21 Jun 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 Jun 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New27 May 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New27 May 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New27 May 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New24 May 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Jun 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New25 Jun 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New28 May 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Jun 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New21 Jun 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New21 Jun 2024 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2024-Q2 to 2026-Q1.

QuarterConstructionCertificates
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q21.41%CA ↗ · Arch ↗ · Eng ↗
2025-Q31.41%CA ↗ · Arch ↗ · Eng ↗
2025-Q41.41%CA ↗ · Arch ↗ · Eng ↗
2026-Q16.12%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOmaxe Garv Buildtech Private Limited (fomerly Garv Buildtech Private Limited)
RolePromoter · current
RERA IDUPRERAPRM5708
PANAADCG1919Q
CIN / TANDELG12028C
Name of chairmanMr. Manoj Tiwari
Registered address10, Local Shopping Centre, Kalkaji, New Delhi - 110019, Delhi, INDIA
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
OMAXE GARV COLLECTION ACCOUNT GH-2 OMAXE CASSIA PH-1BankIDBI BANKBranchIDBI BANK, INDIRA NAGARBranch addressIDBI BANK, INDIRA NAGAR LUCKNOWBranch districtLucknowA/C no.IFSCIBKL0000277Branch emailibkl0000277@idbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
OMAXE GARV SEPARATE ACCOUNT GH-2 OMAXE CASSIA PH-1BankIDBI BANKBranchIDBI BANK, INDIRA NAGARBranch addressIDBI BANK, INDIRA NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCIBKL0000277
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
OMAXE GARV RERA TRANSACTION ACCOUNT GH-2 OMAXE CASSIA PH-1BankIDBI BANKBranchIDBI BANK, INDIRA NAGARBranch addressIDBI BANK, INDIRA NAGAR, LUCKNOWBranch districtLucknow, Uttar PradeshA/C no.IFSCIBKL0000277
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)40 (Under Registration - 2 ) → 41 (Under Registration - 3 )
changed in Estanzo’s record
17 Sept 2026
Promoter’s complaints tally (all their projects)40 (Under Registration - 3 ) → 40 (Under Registration - 2 )
changed in Estanzo’s record
15 Sept 2026
Promoter’s complaints tally (all their projects)39 (Under Registration - 4 ) → 40 (Under Registration - 3 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 17 Sept 2026 · 3 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Omaxe Cassia GH II, Phase I

Is Omaxe Cassia GH II, Phase I RERA registered?

Yes. Omaxe Cassia GH II, Phase I is registered with UPRERA under registration number UPRERAPRJ344049, registered on 10 Jul 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Omaxe Cassia GH II, Phase I?

The completion date filed with UPRERA is 8 Apr 2029. No completion certificate is on record yet.

Who is the builder of Omaxe Cassia GH II, Phase I?

Omaxe Garv Buildtech Private Limited (fomerly Garv Buildtech Private Limited) is the promoter entity that filed Omaxe Cassia GH II, Phase I with UPRERA (promoter RERA ID UPRERAPRM5708). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Omaxe Cassia GH II, Phase I have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Omaxe Cassia GH II, Phase I located?

Omaxe Cassia GH II, Phase I is registered in Kalli Paschim, Lucknow, as filed with UPRERA.

What configurations are available in Omaxe Cassia GH II, Phase I?

The unit plan filed with UPRERA lists 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Omaxe Cassia GH II, Phase I?

The approved unit plan filed with UPRERA runs from 62 to 116 m² of carpet area (about 667 to 1,249 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Omaxe Cassia GH II, Phase I?

The approved unit plan describes 4 blocks and 318 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Omaxe Cassia GH II, Phase I?

About 95 units per acre: 318 planned units across 3.33 acres (13,481 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗