Paras Avenue is a RERA-registered commercial project by AMBIT BUILDWELL PVT.LTD. in Gautam Budh Nagar (RERA ID UPRERAPRJ297873). Registered with a completion deadline of 8 Sept 2027.
RERA status as reported: Registered.Construction progress
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ297873 |
| Project category | Commercial |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Noida Authority |
| Proposed start | 1 Nov 2022 |
| Project duration | 59 months |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| Tehsil | Gautam Buddha Nagar |
| Applicant type | Company |
| Applicant address | Room No.205, Welcome Plaza, School Block-II, Shakarpur, Delhi-110092 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Permit revalidated (2)
3 building permits sanctioned
Registered with RERA
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 22 Oct 2022 |
| Original completion | 8 Sept 2027 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹93,000 |
| Sanctioning authority | Noida Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- SHOP508 94%
- OTHER31 6%
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 31 | 149-611 |
| SHOP | 508 | 5-78 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| Paras Avenue · OTHER, SHOP | 24 | 539 | 5-611 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots The Project land will be demarcated by its boundary wall to the exact Shape. Size and orientation as per sanctioned map by Noida Development authority. |
| 2 | Boundary Wall A 2.4 mtr. High boundary wall made of brick and plaster will be constructed with deep foundations to be earthquake resistant. The wall then be plastered and painted as per aesthetics look. |
| 3 | Road Work The road shall be constructed in M-20 grade RCC will be laid in thickness of + 150mm on top of compacted PCC and compacted base metal and using colored paper as per design for aesthetic look. |
| 4 | Footpaths M-30 Grade paver block/ interlocking pavers will be laid in the walking areas. The pavers shall be 3"-4" thickness and shall be laid on compacted sand bed. The paver block/ interlocking pavers shall be used in colored patters. |
| 5 | Water Supply Including Drinking Water Facilities A portable ground water supply through the pumping arrangement will be delivered to the water tank of 4.0 Lac liter capacity on terrace. |
| 6 | Sewer System The sewage shall be collected through a soil pipe arrangement, U bends and inspection chambers leading to the STP of the project. |
| 7 | Drain The roof top water shall be brought to the ground floor level with the 150 mm-200 mm rain Upvc water down take pipes which along with the surface run off water shall be transported to the rain water harvesting pits through under ground 300mm -450mm Rcc hume pipes. |
| 8 | Parks Not applicable. |
| 9 | Tree Planting The trees will be planted at all suitable location as per the development plan. |
| 10 | Design For Electric Supply Including Street Lighting Electrical layout and capacity will be installed to suffice the commercial use of the project as per load sanction approval. |
| 11 | Community Buildings Not applicable |
| 12 | Treatment and Disposal System of Sewage and Sullage water Centralized STP to treat the sewage. |
| 13 | Solid Waste Management And Disposal System Project shall have waste segregation area. |
| 14 | Water Conservation System Rain water harvesting with dual flush system shall be provided. |
| 15 | Energy Management System Including Use of Renewable Energy LED light and timer control panels shall be used. |
| 16 | Fire Protection And Fire Safety System Fire Alarm system shall be provided. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Not applicable. |
| 18 | Emergency Evacuation Services As per approved building plan. |
| 19 | Other Miscellaneous Work As per approved building plan. |
Registered agents
4 agents
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | GATEWAY PROPMART PVT LTD | UPRERAAGT10384 |
| 2 | INVESTORS CLINIC INFRATECH PRIVATE LIMITED | UPRERAAGT10052 |
| 3 | SQUARE YARDS CONSULTING PRIVATE LIMITED | UPRERAAGT10119 |
| 4 | WEALTH CLINIC PRIVATE LIMITED | UPRERAAGT10521 |
Permits & extensions
3 permits
An approval and the date it runs to - not proof the work matching it was done.
3 sanctioning permits are on record with UPRERA, the latest valid to 8 Sept 2027. 2 of them carry a revalidation, the latest valid to 23 Mar 2028.
Sanctioned by Noida Authority · 8,240 sqm of land · an approved plan of 1 block and 539 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | RevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossary | Documents filed |
|---|---|---|---|---|---|---|
| 2022/04/12/6707 | 9 Sept 2022 | 8 Sept 2027 | 8 Sept 2030 | 8 Sept 2027 | — | |
| 2022/04/12/6707 | 9 Sept 2022 | 8 Sept 2027 | 23 Feb 2031 | 8 Sept 2027 | 9 Sept 2022 valid to 23 Mar 2028 | |
| 2022/04/12/6707 | 9 Sept 2022 | 8 Sept 2027 | 8 Sept 2030 | 8 Sept 2027 | 9 Sept 2022 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| C3H1,BlockNo. C3, Sector 129 | 8240 | Plot |
| Registry document · 12622 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Allotment letter from the authority · layoutplan The development authority’s letter allotting the plot - usually the step before a lease deed is executed. | PDF ↗ |
| Sale deed · Search Report The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 8565 Sub Lease Jaypee To South Indian Bank The registered deed by which the promoter bought the land. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 14 Sept 2022 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 6 Oct 2022 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 6 Oct 2022 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 6 Oct 2022 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 15 Sept 2022 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 15 Sept 2022 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 15 Sept 2022 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 15 Sept 2022 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 14 Sept 2022 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 15 Sept 2022 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 15 Sept 2022 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 6 Oct 2022 ↗ |
| Affidavit on balance development work The promoter’s sworn statement about the development work still to be finished. | New | 12 Nov 2025 ↗ |
Quarterly progress reports
16 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
16 quarterly progress reports are on file with UPRERA, covering 2022-Q3 to 2026-Q2.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 29% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 23.4% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q1 | 0% | CA ↗ · Arch ↗ · Eng ↗ |
| 2026-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | AMBIT BUILDWELL PVT.LTD. |
| Role | Promoter · current |
| RERA ID | UPRERAPRM196073 |
| PAN | AAHCA1601M |
| CIN / TAN | CA1601M1ZR |
| Name of chairman | Aman Nagar |
| Registered address | Room No.205, Welcome Plaza, School Block-II, Shakarpur, Delhi-110092 |
| RERA contact | |
| Registered since | 2022 |
Nearby projects
Gautam Budh Nagar
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | Ambit Buildwell Pvt. Ltd. Collection Account for Paras AvenueBankHDFC BankBranchSector 18Branch addressAnsal Arcade Sector-18 NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | Ambit Buildwell Pvt. Ltd. Separate Bank Account For Paras AvenueBankHDFC BankBranchSector-18Branch addressAnsals Arcade K-Block, Sector18, NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | Ambit Buildwell Pvt. Ltd. Rera Transaction Account for Paras AvenueBankHDFC BankBranchSector-18Branch addressAnsals Arcade K-Block NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088 |
What has changed on this record
3 movements
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026.
| Field | What moved | Observed |
|---|---|---|
| Quarterly progress report 2026-Q2 | QPR 2026-Q2 newly filed with RERA | 15 Oct 2026 |
| Promoter’s complaints tally (all their projects) | 5 (Under Registration - 3 ) → 6 (Under Registration - 4 ) changed in Estanzo’s record | 29 Sept 2026 |
| Promoter’s complaints tally (all their projects) | 4 (Under Registration - 2 ) → 5 (Under Registration - 3 ) changed in Estanzo’s record | 25 Sept 2026 |
| Promoter’s complaints tally (all their projects) | changed in Estanzo’s record · 29 Sept 2026 · 2 movements on record |
What to verify and what to ask
1 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about Paras Avenue
Is Paras Avenue RERA registered?
Yes. Paras Avenue is registered with UPRERA under registration number UPRERAPRJ297873, registered on 22 Oct 2022. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for Paras Avenue?
The completion date filed with UPRERA is 8 Sept 2027. No completion certificate is on record yet.
Who is the builder of Paras Avenue?
AMBIT BUILDWELL PVT.LTD. is the promoter entity that filed Paras Avenue with UPRERA (promoter RERA ID UPRERAPRM196073). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does Paras Avenue have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is Paras Avenue located?
Paras Avenue is registered in Gautam Budh Nagar, as filed with UPRERA.
What configurations are available in Paras Avenue?
The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in Paras Avenue?
The approved unit plan filed with UPRERA runs from 5 to 611 m² of carpet area (about 52 to 6,581 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in Paras Avenue?
The approved unit plan describes 1 block and 539 units of which 31 are homes and 508 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is Paras Avenue?
About 265 units per acre: 539 planned units across 2.04 acres (8,240 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗