Paras Avenue

UPRERARegistered

Paras Avenue is a RERA-registered commercial project by AMBIT BUILDWELL PVT.LTD. in Gautam Budh Nagar (RERA ID UPRERAPRJ297873). Registered with a completion deadline of 8 Sept 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
0%Q3'25
29%Q4'25
23.4%Q1'26
0%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ297873
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Nov 2022
Project duration59 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRoom No.205, Welcome Plaza, School Block-II, Shakarpur, Delhi-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 Oct 2022
Original completion8 Sept 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹93,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors539 · 1 · 24 (units from plan)
Homes · commercial units31 · 508 (shops and offices filed in the same plan)
  • SHOP508 94%
  • OTHER31 6%
ConfigurationUnitsCarpet area
OTHER31149-611
SHOP5085-78
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Paras Avenue · OTHER, SHOP245395-611
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Kulmeet Shangari ACPL Design Ltd.
License 927/21741
E-24, South Extention-1, New Delhi-110049
Engineer
Vintech Consultants
C-35, Pamposh Enclave, G.K.-1, New Delhi-110048
Contractor
Krishna Buildestates Pvt. Ltd.
252, Okhla industrial area, Phase-III, New Delhi-110020
Sr.Development work declared to RERA
1Demarcation of Plots
The Project land will be demarcated by its boundary wall to the exact Shape. Size and orientation as per sanctioned map by Noida Development authority.
2Boundary Wall
A 2.4 mtr. High boundary wall made of brick and plaster will be constructed with deep foundations to be earthquake resistant. The wall then be plastered and painted as per aesthetics look.
3Road Work
The road shall be constructed in M-20 grade RCC will be laid in thickness of + 150mm on top of compacted PCC and compacted base metal and using colored paper as per design for aesthetic look.
4Footpaths
M-30 Grade paver block/ interlocking pavers will be laid in the walking areas. The pavers shall be 3"-4" thickness and shall be laid on compacted sand bed. The paver block/ interlocking pavers shall be used in colored patters.
5Water Supply Including Drinking Water Facilities
A portable ground water supply through the pumping arrangement will be delivered to the water tank of 4.0 Lac liter capacity on terrace.
6Sewer System
The sewage shall be collected through a soil pipe arrangement, U bends and inspection chambers leading to the STP of the project.
7Drain
The roof top water shall be brought to the ground floor level with the 150 mm-200 mm rain Upvc water down take pipes which along with the surface run off water shall be transported to the rain water harvesting pits through under ground 300mm -450mm Rcc hume pipes.
8Parks
Not applicable.
9Tree Planting
The trees will be planted at all suitable location as per the development plan.
10Design For Electric Supply Including Street Lighting
Electrical layout and capacity will be installed to suffice the commercial use of the project as per load sanction approval.
11Community Buildings
Not applicable
12Treatment and Disposal System of Sewage and Sullage water
Centralized STP to treat the sewage.
13Solid Waste Management And Disposal System
Project shall have waste segregation area.
14Water Conservation System
Rain water harvesting with dual flush system shall be provided.
15Energy Management System Including Use of Renewable Energy
LED light and timer control panels shall be used.
16Fire Protection And Fire Safety System
Fire Alarm system shall be provided.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not applicable.
18Emergency Evacuation Services
As per approved building plan.
19Other Miscellaneous Work
As per approved building plan.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1GATEWAY PROPMART PVT LTDUPRERAAGT10384
2INVESTORS CLINIC INFRATECH PRIVATE LIMITEDUPRERAAGT10052
3SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
4WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 8 Sept 2027. 2 of them carry a revalidation, the latest valid to 23 Mar 2028.

Sanctioned by Noida Authority · 8,240 sqm of land · an approved plan of 1 block and 539 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
2022/04/12/67079 Sept 20228 Sept 20278 Sept 20308 Sept 2027—
2022/04/12/67079 Sept 20228 Sept 202723 Feb 20318 Sept 20279 Sept 2022
valid to 23 Mar 2028
2022/04/12/67079 Sept 20228 Sept 20278 Sept 20308 Sept 20279 Sept 2022
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
C3H1,BlockNo. C3, Sector 1298240Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 12622
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Allotment letter from the authority · layoutplan
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Sale deed · Search Report
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 8565 Sub Lease Jaypee To South Indian Bank
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New14 Sept 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New6 Oct 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Oct 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Oct 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New15 Sept 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New15 Sept 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New15 Sept 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New15 Sept 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New14 Sept 2022 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New15 Sept 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New15 Sept 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Oct 2022 ↗
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
New12 Nov 2025 ↗

Quarterly progress reports

16 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

16 quarterly progress reports are on file with UPRERA, covering 2022-Q3 to 2026-Q2.

QuarterConstructionCertificates
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q329%CA ↗ · Arch ↗ · Eng ↗
2025-Q423.4%CA ↗ · Arch ↗ · Eng ↗
2026-Q10%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAMBIT BUILDWELL PVT.LTD.
RolePromoter · current
RERA IDUPRERAPRM196073
PANAAHCA1601M
CIN / TANCA1601M1ZR
Name of chairmanAman Nagar
Registered addressRoom No.205, Welcome Plaza, School Block-II, Shakarpur, Delhi-110092
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Ambit Buildwell Pvt. Ltd. Collection Account for Paras AvenueBankHDFC BankBranchSector 18Branch addressAnsal Arcade Sector-18 NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Ambit Buildwell Pvt. Ltd. Separate Bank Account For Paras AvenueBankHDFC BankBranchSector-18Branch addressAnsals Arcade K-Block, Sector18, NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Ambit Buildwell Pvt. Ltd. Rera Transaction Account for Paras AvenueBankHDFC BankBranchSector-18Branch addressAnsals Arcade K-Block NoidaBranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
Promoter’s complaints tally (all their projects)5 (Under Registration - 3 ) → 6 (Under Registration - 4 )
changed in Estanzo’s record
29 Sept 2026
Promoter’s complaints tally (all their projects)4 (Under Registration - 2 ) → 5 (Under Registration - 3 )
changed in Estanzo’s record
25 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 29 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Paras Avenue

Is Paras Avenue RERA registered?

Yes. Paras Avenue is registered with UPRERA under registration number UPRERAPRJ297873, registered on 22 Oct 2022. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Paras Avenue?

The completion date filed with UPRERA is 8 Sept 2027. No completion certificate is on record yet.

Who is the builder of Paras Avenue?

AMBIT BUILDWELL PVT.LTD. is the promoter entity that filed Paras Avenue with UPRERA (promoter RERA ID UPRERAPRM196073). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Paras Avenue have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Paras Avenue located?

Paras Avenue is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in Paras Avenue?

The unit plan filed with UPRERA lists OTHER and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Paras Avenue?

The approved unit plan filed with UPRERA runs from 5 to 611 m² of carpet area (about 52 to 6,581 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Paras Avenue?

The approved unit plan describes 1 block and 539 units of which 31 are homes and 508 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Paras Avenue?

About 265 units per acre: 539 planned units across 2.04 acres (8,240 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗