Timeline Bar

Registered28 Jul 2017
Promised31 Mar 2019
Today4 Aug 2026

Timeline

Promised completion31 Mar 2019
Revised completion31 Mar 2019
Actual completion
Possession delay88 mo delay

Registration & Cost Details

Registration fee (in ₹)₹61,000
Project cost (in ₹ Lakhs)₹0 Lakhs
Project duration108 months
Project categoryResidential
Locality
Original start date10 Aug 2011
Proposed start date24 Jul 2017

Inventory

Total units64
Unit TypeUnitsCarpet Area (sqm)
4 BHK64293.54

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9211221221
Emailrera.jil@jilindia.in
Coordinator9650222583
AddressSector - 128, Noida - 201304, Uttar Pradesh (India)

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q220.0%
2025-Q361.4%
2025-Q462.0%
2026-Q162.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Noida/CAP/III-253/91920 Jul 201619 Jul 202131 Mar 2019
Noida/CAP/III-253/919

Revalidated: Noida/CAP/III-253/919 (20 Jul 2016)

20 Jul 201620 Jul 2021

Revalidated upto: 18 Jul 2026

31 Mar 201918 Jul 2026

Land Parcels

Khasra No.AreaPlot Type
as per attached Lease Deeds-
B-2611102Plot

Approved Unit Plan

Unit plan rows on file68
Total flats (sum of rows)64
BlocksPB-01, PB-02, PB-03, PB-04
Floor types4 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
5766/576717 Apr 2003
7473/74727 Jun 2003
10197/1019626 Jul 2003

Frequently Asked Questions

What is the RERA registration number of Pebble Court?

The RERA registration number of Pebble Court is UPRERAPRJ2623, as recorded on the UP-RERA portal.

What is the RERA status of Pebble Court?

As reported by UP-RERA, the status of Pebble Court is "Registered".

Where is Pebble Court located?

As reported to UP-RERA, Pebble Court is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Pebble Court be completed?

The latest completion date reported to UP-RERA for Pebble Court is 31 Mar 2019.

Is Pebble Court delayed?

Measured against the latest completion date reported to UP-RERA, Pebble Court is 88 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026